201 S LORRAINE BLVD 90004

Certificate Information: 201 S LORRAINE BLVD 90004

Application / Permit
20014-10000-01950
Plan Check / Job No.
B20LA08358
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Patio addition to existing 2-story single family dwelling. Remodel SFD with new partitions & exterior windows. No change in building height nor exterior openings.
Permit Issued
Issued on 9/30/2020
Issuing Office
Current Status
CofO Issued on 5/10/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/7/2020 APPLICANT
Assigned to Plan Check Engineer 5/28/2020 CRYSTEL MAALOUF
Corrections Issued 6/10/2020 CRYSTEL MAALOUF
Quality Review Completed 7/22/2020 TU HUA
Applicant returned to address corrections 9/16/2020 CRYSTEL MAALOUF
Plan Check Approved 9/30/2020 CRYSTEL MAALOUF
Issued 9/30/2020 APPLICANT
CofO in Progress 5/7/2025 RAUL BARAJAS
Permit Finaled 5/10/2025 DEROLD HAUFF
CofO Issued 5/10/2025 DEROLD HAUFF
Permit Finaled 5/10/2025 DEROLD HAUFF

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 7/1/2020 ELAINE LEI
Roof/Waste drainage to street Cleared 7/1/2020 ELAINE LEI
Sewer availability Cleared 7/1/2020 ELAINE LEI
HPOZ Cleared 7/20/2020 LYDIA CHAPMAN
ZI Cleared 7/20/2020 LYDIA CHAPMAN
Green Code Cleared 9/30/2020 CRYSTEL MAALOUF

Contact Information

Contractor Alisal Builders Corp; Lic. No.: 732777-B P O BOX 6038      SAN PEDRO, CA 90734
Engineer Roth,, Jennifer Nicole; Lic. No.: C84889 110 THE VILLAGE UNIT 504      REDONDO BEACH, CA 90277

Inspector Information

JEFFREY MEAD, (213) 202-3240 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 11/6/2020 Approved DONALD CRICHLOW
Pre-Inspection 11/6/2020 Approved DONALD CRICHLOW
Deputy Drilled-In Anchors 11/10/2020 No Access for Inspection ELMER BLAND
Deputy Drilled-In Anchors 11/30/2020 No Access for Inspection ELMER BLAND
Deputy Steel/Welding 12/2/2020 Conditional Approval CHRIS CHRISTENSEN
Deputy Drilled-In Anchors 12/16/2020 No Access for Inspection ELMER BLAND
Deputy Wood Construction 1/13/2021 Conditional Approval SABAS ALONSO
Deputy Drilled-In Anchors 2/17/2021 Conditional Approval THOMAS LOGRASSO
BUILDING-Rough-Frame 5/17/2021 Not Ready for Inspection CHRIS CHRISTENSEN
ELECTRICAL-Rough 5/17/2021 Partial Approval CHRIS CHRISTENSEN
HVAC-Rough 5/17/2021 Approved CHRIS CHRISTENSEN
PLUMBING-Rough 5/17/2021 Corrections Issued CHRIS CHRISTENSEN
BUILDING-Rough-Frame 5/27/2021 Partial Approval CHRIS CHRISTENSEN
ELECTRICAL-Rough 5/27/2021 Approved CHRIS CHRISTENSEN
HVAC-Rough 5/27/2021 Approved CHRIS CHRISTENSEN
PLUMBING-Rough 5/27/2021 Approved CHRIS CHRISTENSEN
Shower Pan 6/21/2021 Approved JOSEPH MCGARRY
HVAC-Rough 6/30/2021 Approved HAMIK HARTOUNIAN
BUILDING-Rough-Frame 7/21/2021 Approved CHRIS CHRISTENSEN
Green Building Rough 7/21/2021 Approved CHRIS CHRISTENSEN
Insulation 7/28/2021 Approved ARTHUR SARGSYAN
Drywall Nailing 8/17/2021 Approved CHRIS CHRISTENSEN
Interior/Exterior Lathing 8/17/2021 Not Ready for Inspection CHRIS CHRISTENSEN
Interior/Exterior Lathing 8/19/2021 Approved ARTHUR SARGSYAN
Interior/Exterior Lathing 9/1/2021 Approved ARTHUR SARGSYAN
HVAC-Final 7/19/2022 Corrections Issued JEFFREY MEAD
PLUMBING-Final 7/19/2022 Partial Approval JEFFREY MEAD
ELECTRICAL-Final 8/1/2022 Corrections Issued JEFFREY MEAD
Final 9/16/2022 Partial Approval JEFFREY MEAD
SGSOV-Seismic Gas S/O Valve 9/16/2022 SGSOV Approved JEFFREY MEAD
Smoke Detectors 9/16/2022 Approved JEFFREY MEAD
ELECTRICAL-Final 9/21/2022 Approved JEFFREY MEAD
HVAC-Final 9/21/2022 Approved JEFFREY MEAD
PLUMBING-Final 9/21/2022 Approved JEFFREY MEAD
Final 5/7/2025 OK to Issue CofO RAUL BARAJAS