2143 S REDONDO BLVD 90016
Certificate Information: 2143 S REDONDO BLVD 90016
- Application / Permit
- 20014-10000-01925
- Plan Check / Job No.
- B20LA08255
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- PROPOSED ADDITION TO SFD FOR KITCHEN EXTENSION AND BATHROOM ADDITION.
- Permit Issued
- Issued on 9/22/2020
- Issuing Office
- Current Status
- CofO Issued on 11/29/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/6/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 7/6/2020 | SINA KHOSRAVI |
| Corrections Issued | 7/6/2020 | SINA KHOSRAVI |
| Building Plans Picked Up | 7/7/2020 | APPLICANT |
| Plan Check Approved | 9/15/2020 | CRISTINA SALAZAR |
| Issued | 9/22/2020 | APPLICANT |
| CofO in Progress | 11/26/2025 | BRENDAN MORELLI |
| Permit Finaled | 11/29/2025 | DEROLD HAUFF |
| CofO Issued | 11/29/2025 | DEROLD HAUFF |
| Permit Finaled | 11/29/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 7/30/2020 | JAMES KHO |
| Eng Process Fee Ord 176,300 | Cleared | 9/10/2020 | JAMES KHO |
Contact Information
| Contractor | California Construction Services; Lic. No.: 767434-B | 13308 PARAMOUNT BLVE SOUTH GATE, CA 90280 |
| Engineer | Adefeso,, Wole Dayo; Lic. No.: C63361 | 1608 CENTINELA AVE #13 INGLEWOOD, CA 90302 |
Inspector Information
| DAVID WILLIAMS, (213) 202-3126 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 10/28/2020 | Corrections Issued | DAVID CHAN |
| BUILDING-Rough-Frame | 12/14/2020 | Partial Approval | DAVID CHAN |
| Insulation | 12/22/2020 | Partial Approval | DAVID CHAN |
| BUILDING-Rough-Frame | 1/19/2021 | Not Ready for Inspection | DAVID CHAN |
| ELECTRICAL-Rough | 1/19/2021 | Not Ready for Inspection | DAVID CHAN |
| Green Building Rough | 1/19/2021 | Not Ready for Inspection | DAVID CHAN |
| PLUMBING-Rough | 1/19/2021 | Not Ready for Inspection | DAVID CHAN |
| ELECTRICAL-Rough | 1/25/2021 | Not Ready for Inspection | DAVID FEILER |
| PLUMBING-Rough | 1/25/2021 | Corrections Issued | DAVID FEILER |
| Interior/Exterior Lathing | 2/9/2021 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| BUILDING-Rough-Frame | 3/8/2021 | Partial Inspection | SCOTT FINNILA |
| ELECTRICAL-Rough | 3/8/2021 | Corrections Issued | SCOTT FINNILA |
| Green Building Rough | 3/8/2021 | Corrections Issued | SCOTT FINNILA |
| PLUMBING-Rough | 3/8/2021 | Approved | SCOTT FINNILA |
| BUILDING-Rough-Frame | 3/19/2021 | Partial Approval | DAVID FEILER |
| Green Building Rough | 3/19/2021 | Approved | DAVID FEILER |
| Insulation | 3/19/2021 | Approved | DAVID FEILER |
| Interior/Exterior Lathing | 3/19/2021 | Partial Approval | DAVID FEILER |
| Rough-Elec/Plmb/HVAC | 3/19/2021 | Approved | DAVID FEILER |
| Drywall Nailing | 4/15/2021 | Partial Approval | SABAS ALONSO |
| Interior/Exterior Lathing | 4/15/2021 | Partial Inspection | SABAS ALONSO |
| Shower Pan | 4/26/2021 | Not Ready for Inspection | CHRISTOPHER DELLEFIELD |
| Interior/Exterior Lathing | 4/29/2021 | Approved | CHRISTOPHER DELLEFIELD |
| Shower Pan | 4/29/2021 | Approved | CHRISTOPHER DELLEFIELD |
| BUILDING-Rough-Frame | 11/19/2025 | Approved | ARTHUR NEGRETE |
| Final | 11/19/2025 | Not Ready for Inspection | ARTHUR NEGRETE |
| Footing/Foundation/Slab | 11/19/2025 | Approved | ARTHUR NEGRETE |
| Green Building Final | 11/19/2025 | Not Ready for Inspection | ARTHUR NEGRETE |
| SGSOV-Seismic Gas S/O Valve | 11/19/2025 | SGSOV Not Required | ARTHUR NEGRETE |
| Smoke Detectors | 11/19/2025 | Approved | ARTHUR NEGRETE |
| Final | 11/25/2025 | OK to Issue CofO | BRENDAN MORELLI |
| Green Building Final | 11/25/2025 | Approved | BRENDAN MORELLI |