2143 S REDONDO BLVD 90016

Certificate Information: 2143 S REDONDO BLVD 90016

Application / Permit
20014-10000-01925
Plan Check / Job No.
B20LA08255
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
PROPOSED ADDITION TO SFD FOR KITCHEN EXTENSION AND BATHROOM ADDITION.
Permit Issued
Issued on 9/22/2020
Issuing Office
Current Status
CofO Issued on 11/29/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/6/2020 APPLICANT
Assigned to Plan Check Engineer 7/6/2020 SINA KHOSRAVI
Corrections Issued 7/6/2020 SINA KHOSRAVI
Building Plans Picked Up 7/7/2020 APPLICANT
Plan Check Approved 9/15/2020 CRISTINA SALAZAR
Issued 9/22/2020 APPLICANT
CofO in Progress 11/26/2025 BRENDAN MORELLI
Permit Finaled 11/29/2025 DEROLD HAUFF
CofO Issued 11/29/2025 DEROLD HAUFF
Permit Finaled 11/29/2025 DEROLD HAUFF

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 7/30/2020 JAMES KHO
Eng Process Fee Ord 176,300 Cleared 9/10/2020 JAMES KHO

Contact Information

Contractor California Construction Services; Lic. No.: 767434-B 13308 PARAMOUNT BLVE      SOUTH GATE, CA 90280
Engineer Adefeso,, Wole Dayo; Lic. No.: C63361 1608 CENTINELA AVE #13      INGLEWOOD, CA 90302

Inspector Information

DAVID WILLIAMS, (213) 202-3126 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 10/28/2020 Corrections Issued DAVID CHAN
BUILDING-Rough-Frame 12/14/2020 Partial Approval DAVID CHAN
Insulation 12/22/2020 Partial Approval DAVID CHAN
BUILDING-Rough-Frame 1/19/2021 Not Ready for Inspection DAVID CHAN
ELECTRICAL-Rough 1/19/2021 Not Ready for Inspection DAVID CHAN
Green Building Rough 1/19/2021 Not Ready for Inspection DAVID CHAN
PLUMBING-Rough 1/19/2021 Not Ready for Inspection DAVID CHAN
ELECTRICAL-Rough 1/25/2021 Not Ready for Inspection DAVID FEILER
PLUMBING-Rough 1/25/2021 Corrections Issued DAVID FEILER
Interior/Exterior Lathing 2/9/2021 Not Ready for Inspection KATHRYN BUTTERWORTH
BUILDING-Rough-Frame 3/8/2021 Partial Inspection SCOTT FINNILA
ELECTRICAL-Rough 3/8/2021 Corrections Issued SCOTT FINNILA
Green Building Rough 3/8/2021 Corrections Issued SCOTT FINNILA
PLUMBING-Rough 3/8/2021 Approved SCOTT FINNILA
BUILDING-Rough-Frame 3/19/2021 Partial Approval DAVID FEILER
Green Building Rough 3/19/2021 Approved DAVID FEILER
Insulation 3/19/2021 Approved DAVID FEILER
Interior/Exterior Lathing 3/19/2021 Partial Approval DAVID FEILER
Rough-Elec/Plmb/HVAC 3/19/2021 Approved DAVID FEILER
Drywall Nailing 4/15/2021 Partial Approval SABAS ALONSO
Interior/Exterior Lathing 4/15/2021 Partial Inspection SABAS ALONSO
Shower Pan 4/26/2021 Not Ready for Inspection CHRISTOPHER DELLEFIELD
Interior/Exterior Lathing 4/29/2021 Approved CHRISTOPHER DELLEFIELD
Shower Pan 4/29/2021 Approved CHRISTOPHER DELLEFIELD
BUILDING-Rough-Frame 11/19/2025 Approved ARTHUR NEGRETE
Final 11/19/2025 Not Ready for Inspection ARTHUR NEGRETE
Footing/Foundation/Slab 11/19/2025 Approved ARTHUR NEGRETE
Green Building Final 11/19/2025 Not Ready for Inspection ARTHUR NEGRETE
SGSOV-Seismic Gas S/O Valve 11/19/2025 SGSOV Not Required ARTHUR NEGRETE
Smoke Detectors 11/19/2025 Approved ARTHUR NEGRETE
Final 11/25/2025 OK to Issue CofO BRENDAN MORELLI
Green Building Final 11/25/2025 Approved BRENDAN MORELLI