7514 S DUNBARTON AVE 90045

Certificate Information: 7514 S DUNBARTON AVE 90045

Application / Permit
20014-10000-01910
Plan Check / Job No.
B20LA08182
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Pool house addition to exisint single family dwelling. "Comply with Department Order effective date 10/30/19. Permit will expire 30 days from issuance date."
Permit Issued
Issued on 7/16/2020
Issuing Office
Current Status
CofO Issued on 2/2/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/8/2020 APPLICANT
Assigned to Plan Check Engineer 5/11/2020 SHANGQIN XIE
Corrections Issued 5/26/2020 SHANGQIN XIE
Applicant returned to address corrections 6/18/2020 TSE MING HUANG
Plan Check Approved 7/7/2020 CRISTINA SALAZAR
Building Plans Picked Up 7/9/2020 APPLICANT
Issued 7/16/2020 APPLICANT
CofO in Progress 1/13/2021 MARIAN PODPORA
Permit Finaled 2/2/2021 BRUCE TODD
CofO Issued 2/2/2021 BRUCE TODD
Permit Finaled 2/2/2021 BRUCE TODD

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 5/14/2020 CHINH DINH
Sewer availability Cleared 5/14/2020 CHINH DINH
Eng Process Fee Ord 176,300 Cleared 5/18/2020 CHINH DINH
Specific Plan Cleared 5/19/2020 PEDRO AYALA
Grading Pre-Inspection Cleared 5/28/2020 PATRICK MISCHLICH

Contact Information

Contractor Owner-Builder       ,

Inspector Information

ROBERT GARTH, (213) 978-4498 Office Hours: 7:00-8:00 AM MON-FRI
JOHN MATTILLO, (213) 978-4498 Office Hours: 7:00-8:00 AM MON-FRI
PEDRO RIVERA, (213) 978-4498 Office Hours: 7:00-8:00 AM MON-FRI
EUSEBIO GUZMAN, (213) 978-4498 Office Hours: 7:00-8:00 AM MON-FRI
PAUL REECE, (213) 978-4498 Office Hours: 7:00-8:00 AM MON-FRI
ANDREW BEELI, (213) 978-4498 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 11/19/2020 Approved MARIAN PODPORA
METHANE-Barrier 11/19/2020 Approved MARIAN PODPORA
METHANE-Subgrade 11/19/2020 Approved MARIAN PODPORA
Insulation 11/30/2020 Partial Approval JOHN MATTILLO
Wood Frame 11/30/2020 Partial Approval JOHN MATTILLO
Rough-Elec/Plmb/HVAC 12/9/2020 Approved JOHN MATTILLO
Wood Frame 12/9/2020 Approved JOHN MATTILLO
Interior/Exterior Lathing 12/18/2020 Approved JOHN MATTILLO
Insulation 1/11/2021 Approved MARIAN PODPORA
BUILDING-Rough-Frame 1/13/2021 Approved MARIAN PODPORA
ELECTRICAL-Final 1/13/2021 Approved MARIAN PODPORA
Final 1/13/2021 OK to Issue CofO MARIAN PODPORA
HVAC-Final 1/13/2021 Approved MARIAN PODPORA
METHANE-Final 1/13/2021 Approved MARIAN PODPORA
METHANE-Rough 1/13/2021 Approved MARIAN PODPORA
PLUMBING-Final 1/13/2021 Approved MARIAN PODPORA
Smoke Detectors 1/13/2021 Approved MARIAN PODPORA