416 E 42ND PL 90011

Certificate Information: 416 E 42ND PL 90011

Application / Permit
20014-10000-01896
Plan Check / Job No.
B20LA08096
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ONE STORY ADDITION TO REAR OF SFD: CONVERT (E) ATTACHED CAR-PORT (260SQFT) TO LIVING SPACE, ADD NEW BEDROOM LIVING ROOM AND GARAGE (291SQFT) ALL WORK DONE PER ENGINEERING
Permit Issued
Issued on 5/5/2023
Issuing Office
Metro
Current Status
CofO Issued on 5/18/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/5/2020 APPLICANT
Assigned to Plan Check Engineer 5/6/2020 JESSE JIMENEZ
Corrections Issued 5/6/2020 JESSE JIMENEZ
Applicant returned to address corrections 7/9/2020 SAMUEL GONZALEZ
Building Plans Picked Up 7/10/2020 APPLICANT
Applicant returned to address corrections 10/13/2020 RICARDO RAMIREZ
Applicant returned to address corrections 12/23/2020 LUKE GONZALES
Applicant returned to address corrections 2/18/2021 LUKE GONZALES
Applicant returned to address corrections 3/31/2023 DANIEL SMILEY
Applicant returned to address corrections 4/26/2023 SHANGQIN XIE
Issued 5/5/2023 APPLICANT
CofO in Progress 5/17/2025 ALEJANDRO DE ARTOLA
Permit Finaled 5/18/2025 DEROLD HAUFF
CofO Issued 5/18/2025 DEROLD HAUFF
Permit Finaled 5/18/2025 DEROLD HAUFF

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 11/6/2020 CECILIO NAVARRO
Eng Process Fee Ord 176,300 Cleared 11/12/2020 CECILIO NAVARRO
Sewer availability Cleared 11/12/2020 CECILIO NAVARRO
Low Impact Development Cleared 1/11/2023 LUIS LUVANO

Contact Information

Contractor Owner-Builder       ,
Engineer Demers,, Joe Alan; Lic. No.: C71535 1626 S MAYFLOWER AVE UNIT B      MONROVIA, CA 91016

Inspector Information

ALEJANDRO DE ARTOLA, (213) 202-3128 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 10/30/2023 Corrections Issued ALEJANDRO DE ARTOLA
Excavation/Setback/Form/Re-Bar 11/8/2023 Approved ALEJANDRO DE ARTOLA
Footing/Foundation/Slab 11/8/2023 Approved ALEJANDRO DE ARTOLA
BUILDING-Rough-Frame 1/18/2024 Partial Approval ALEJANDRO DE ARTOLA
PLUMBING-Rough 1/18/2024 Partial Approval ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 1/31/2024 Not Ready for Inspection ALEJANDRO DE ARTOLA
Insulation 1/31/2024 Partial Approval ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 2/12/2024 Partial Approval ALEJANDRO DE ARTOLA
BUILDING-Rough-Frame 6/17/2024 Partial Approval DAVID FEILER
Deputy Wood Construction 6/17/2024 Approved DAVID FEILER
Wood Frame 6/17/2024 Partial Approval DAVID FEILER
BUILDING-Rough-Frame 7/16/2024 Corrections Issued DAVID FEILER
Floor/Roof Diaphrgm/Shear Wall 7/16/2024 Approved DAVID FEILER
ELECTRICAL-Rough 8/5/2024 Partial Approval ALEJANDRO DE ARTOLA
ELECTRICAL-Rough 8/12/2024 Approved ALEJANDRO DE ARTOLA
PLUMBING-Rough 8/12/2024 Corrections Issued ALEJANDRO DE ARTOLA
BUILDING-Rough-Frame 8/22/2024 Not Ready for Inspection ANTHONY EGSON
Green Building Rough 8/22/2024 Not Ready for Inspection ANTHONY EGSON
Insulation 8/22/2024 Partial Inspection ANTHONY EGSON
Interior/Exterior Lathing 8/22/2024 Corrections Issued ANTHONY EGSON
PLUMBING-Rough 9/12/2024 Not Ready for Inspection CRAIG DAVIS
Interior/Exterior Lathing 9/30/2024 Partial Approval ALEJANDRO DE ARTOLA
BUILDING-Rough-Frame 11/19/2024 Corrections Issued ALEJANDRO DE ARTOLA
Green Building Rough 11/19/2024 Approved ALEJANDRO DE ARTOLA
PLUMBING-Rough 11/19/2024 Approved ALEJANDRO DE ARTOLA
BUILDING-Rough-Frame 11/26/2024 Approved ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 11/26/2024 Approved ALEJANDRO DE ARTOLA
Insulation 11/26/2024 Approved ALEJANDRO DE ARTOLA
Drywall Nailing 12/16/2024 Approved ALEJANDRO DE ARTOLA
ELECTRICAL-Final 4/21/2025 Corrections Issued ALEJANDRO DE ARTOLA
Final 4/21/2025 Corrections Issued ALEJANDRO DE ARTOLA
Green Building Final 4/21/2025 Corrections Issued ALEJANDRO DE ARTOLA
HVAC-Final 4/21/2025 Corrections Issued ALEJANDRO DE ARTOLA
PLUMBING-Final 4/21/2025 Approved ALEJANDRO DE ARTOLA
ELECTRICAL-Final 4/28/2025 Approved ALEJANDRO DE ARTOLA
Final 4/28/2025 Corrections Issued ALEJANDRO DE ARTOLA
Green Building Final 4/28/2025 Corrections Issued ALEJANDRO DE ARTOLA
HVAC-Final 4/28/2025 Corrections Issued ALEJANDRO DE ARTOLA
PLUMBING-Final 4/28/2025 Approved ALEJANDRO DE ARTOLA
SGSOV-Seismic Gas S/O Valve 4/28/2025 SGSOV Not Ready ALEJANDRO DE ARTOLA
Smoke Detectors 4/28/2025 Approved ALEJANDRO DE ARTOLA
Final 5/9/2025 Corrections Issued ALEJANDRO DE ARTOLA
Green Building Final 5/9/2025 Approved ALEJANDRO DE ARTOLA
HVAC-Final 5/9/2025 Approved ALEJANDRO DE ARTOLA
SGSOV-Seismic Gas S/O Valve 5/9/2025 SGSOV Not Ready ALEJANDRO DE ARTOLA
Final 5/14/2025 OK to Issue CofO ALEJANDRO DE ARTOLA
SGSOV-Seismic Gas S/O Valve 5/14/2025 SGSOV Approved ALEJANDRO DE ARTOLA