6912-6914 N TUNNEY AVE 91335

Certificate Information: 6912-6914 N TUNNEY AVE 91335

Application / Permit
20014-10000-01869
Plan Check / Job No.
B20LA07983
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT 1-CAR GARAGE TO NEW ACCESSORY DWELLING UNIT and ONE STORY ADDITIONS [12' X12' TO REAR AND 6'X 10'-6" TO FRONT] . NEW KITCHEN, FULL BATHROOM, AND BEDROOM. (E) GARAGE AREA 224 SF, NEW ADDITION AREA 209, TOTAL NEW ADU: 433 SF
Permit Issued
Issued on 8/18/2020
Issuing Office
Current Status
CofO Issued on 8/10/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/1/2020 APPLICANT
Assigned to Plan Check Engineer 5/5/2020 JESSE JIMENEZ
Corrections Issued 5/6/2020 JESSE JIMENEZ
Applicant returned to address corrections 7/6/2020 CRISTINA SALAZAR
Building Plans Picked Up 7/7/2020 APPLICANT
Plan Check Approved 8/14/2020 ADAM HEGAZI
Issued 8/18/2020 APPLICANT
CofO in Progress 8/6/2021 VINCENT HANLEY
Permit Finaled 8/10/2021 JOHN JANSON
CofO Issued 8/10/2021 JOHN JANSON
Permit Finaled 8/10/2021 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 6/2/2020 ADRIAN CASTRO
Permit Cleared 6/2/2020 ADRIAN CASTRO
Roof/Waste drainage to street Cleared 6/2/2020 ADRIAN CASTRO
Eng Process Fee Ord 176,300 Cleared 6/4/2020 ADRIAN CASTRO
Sewer availability Cleared 7/14/2020 MARKOS PEREZ-BRAN
ZI Cleared 7/15/2020 STEVEN WECHSLER

Contact Information

Contractor Owner-Builder       ,

Inspector Information

ARUTYUN MADATYAN, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI
JUAN ALVARADO, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 8/25/2020 Corrections Issued VINCENT HANLEY
Excavation/Setback/Form/Re-Bar 9/1/2020 Approved VINCENT HANLEY
PLUMBING-Rough 9/14/2020 Partial Approval VINCENT HANLEY
Sewer 9/14/2020 Partial Approval VINCENT HANLEY
BUILDING-Rough-Frame 10/15/2020 Not Ready for Inspection VINCENT HANLEY
ELECTRICAL-Rough 10/15/2020 Not Ready for Inspection VINCENT HANLEY
Floor/Roof Diaphrgm/Shear Wall 10/15/2020 Partial Approval VINCENT HANLEY
Green Building Rough 10/15/2020 Not Ready for Inspection VINCENT HANLEY
PLUMBING-Rough 10/15/2020 Partial Approval VINCENT HANLEY
Sewer 10/15/2020 Not Ready for Inspection VINCENT HANLEY
Wood Frame 10/15/2020 Not Ready for Inspection VINCENT HANLEY
BUILDING-Rough-Frame 10/28/2020 Corrections Issued VINCENT HANLEY
ELECTRICAL-Rough 10/28/2020 Corrections Issued VINCENT HANLEY
Green Building Rough 10/28/2020 Not Ready for Inspection VINCENT HANLEY
PLUMBING-Rough 10/28/2020 Corrections Issued VINCENT HANLEY
BUILDING-Rough-Frame 11/10/2020 Not Ready for Inspection VINCENT HANLEY
ELECTRICAL-Rough 11/10/2020 Approved VINCENT HANLEY
Green Building Rough 11/10/2020 Not Ready for Inspection VINCENT HANLEY
PLUMBING-Rough 11/10/2020 Approved VINCENT HANLEY
ELECTRICAL-Rough 12/30/2020 Approved VINCENT HANLEY
Floor/Roof Diaphrgm/Shear Wall 12/30/2020 Approved VINCENT HANLEY
HVAC-Rough 12/30/2020 Approved VINCENT HANLEY
PLUMBING-Rough 12/30/2020 Approved VINCENT HANLEY
BUILDING-Rough-Frame 3/4/2021 Approved VINCENT HANLEY
ELECTRICAL-Rough 3/4/2021 Approved VINCENT HANLEY
Green Building Rough 3/4/2021 Approved VINCENT HANLEY
Insulation 3/4/2021 Approved VINCENT HANLEY
Interior/Exterior Lathing 3/4/2021 Partial Approval VINCENT HANLEY
Drywall Nailing 3/16/2021 Approved VINCENT HANLEY
Interior/Exterior Lathing 3/16/2021 Approved VINCENT HANLEY
Final 7/16/2021 Corrections Issued VINCENT HANLEY
Footing/Foundation/Slab 7/16/2021 Approved VINCENT HANLEY
Green Building Final 7/16/2021 Not Ready for Inspection VINCENT HANLEY
SGSOV-Seismic Gas S/O Valve 7/16/2021 SGSOV Approved VINCENT HANLEY
Smoke Detectors 7/16/2021 Approved VINCENT HANLEY
ELECTRICAL-Final 8/5/2021 Approved VINCENT HANLEY
Final 8/5/2021 Corrections Issued VINCENT HANLEY
Gas Test 8/5/2021 Approved VINCENT HANLEY
Green Building Final 8/5/2021 Approved VINCENT HANLEY
HVAC-Final 8/5/2021 Approved VINCENT HANLEY
PLUMBING-Final 8/5/2021 Approved VINCENT HANLEY
SGSOV-Seismic Gas S/O Valve 8/5/2021 SGSOV Approved VINCENT HANLEY
Final 8/6/2021 OK to Issue CofO VINCENT HANLEY