4393 N SCANDIA WAY 90065

Certificate Information: 4393 N SCANDIA WAY 90065

Application / Permit
20014-10000-01867
Plan Check / Job No.
B20LA07971
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
(N) ADDITON TO (E) SFD
Permit Issued
Issued on 1/8/2021
Issuing Office
Current Status
CofO Issued on 10/1/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/1/2020 APPLICANT
Assigned to Plan Check Engineer 5/22/2020 JESSE ARELLANO
Corrections Issued 6/2/2020 JESSE ARELLANO
Quality Review Completed 6/3/2020 BILL STUTSMAN
Green Plans Picked Up 7/28/2020 APPLICANT
Applicant returned to address corrections 9/26/2020 JESSE ARELLANO
Plan Check Approved 12/17/2020 JESSE ARELLANO
No Progress 12/17/2020 JESSE ARELLANO
Plan Check Approved 12/20/2020 JESSE ARELLANO
Issued 1/8/2021 APPLICANT
Building Plans Picked Up 1/13/2021 APPLICANT
CofO in Progress 9/22/2022 HAMIK HARTOUNIAN
Permit Finaled 10/1/2022 DEROLD HAUFF
CofO Issued 10/1/2022 DEROLD HAUFF
Permit Finaled 10/1/2022 DEROLD HAUFF

Permit Application Clearance Information

Low Impact Development Cleared 6/17/2020 MARTIN FRAGOSO
BHO/Hillside ordinance Cleared 6/30/2020 RENZ SORIANO
Eng Process Fee Ord 176,300 Cleared 6/30/2020 RENZ SORIANO
BHO/Hillside ordinance Cleared 7/1/2020 RENZ SORIANO
BHO/Hillside ordinance Cleared 7/1/2020 RENZ SORIANO
Hydrant and Access approval Cleared 7/13/2020 MATTHEW CRAIG
Green Code Cleared 7/23/2020 KHEDER ALRAZAA
Specific Plan Cleared 10/8/2020 KENTON TRINH

Contact Information

Contractor Williams Christopher; Lic. No.: 711380-B P O BOX 8652      LA CRESCENTA, CA 91224
Engineer Phillips,, Craig Richard; Lic. No.: C69673 2123 VESTAL AVE      LOS ANGELES, CA 90026

Inspector Information

NICHOLAS LOPEZ, (213) 202-3224 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Grading 4/9/2021 Conditional Approval HAMIK HARTOUNIAN
Piling/Pier/Caisson 4/13/2021 Approved HAMIK HARTOUNIAN
Piling/Pier/Caisson 4/27/2021 Approved HAMIK HARTOUNIAN
Deputy Reinf. Concrete 4/28/2021 Conditional Approval THOMAS LOGRASSO
Piling/Pier/Caisson 5/6/2021 Approved HAMIK HARTOUNIAN
PLUMBING-Rough 6/30/2021 Not Ready for Inspection CRAIG VAUGHAN
PLUMBING-Rough 7/2/2021 Corrections Issued HAMIK HARTOUNIAN
PLUMBING-Rough 7/21/2021 Partial Approval HAMIK HARTOUNIAN
Deputy Reinf. Concrete 8/11/2021 Conditional Approval HAMIK HARTOUNIAN
Excavation/Setback/Form/Re-Bar 8/16/2021 Not Ready for Inspection COREY HUPP
Excavation/Setback/Form/Re-Bar 8/17/2021 Corrections Issued COREY HUPP
Excavation/Setback/Form/Re-Bar 8/18/2021 Partial Approval BRIAN SULLIVAN
Deputy Reinf. Concrete 8/20/2021 Partial Approval SCOTT FINNILA
Excavation/Setback/Form/Re-Bar 9/1/2021 Partial Approval HAMIK HARTOUNIAN
Footing/Foundation/Slab 9/1/2021 Approved HAMIK HARTOUNIAN
Deputy Reinf. Concrete 9/2/2021 Partial Approval SCOTT FINNILA
Excavation/Setback/Form/Re-Bar 9/9/2021 Partial Approval HAMIK HARTOUNIAN
Floor/Roof Diaphrgm/Shear Wall 11/9/2021 Partial Approval HAMIK HARTOUNIAN
Green Building Rough 11/9/2021 Approved HAMIK HARTOUNIAN
Floor/Roof Diaphrgm/Shear Wall 12/16/2021 Corrections Issued HAMIK HARTOUNIAN
ELECTRICAL-Rough 2/4/2022 Approved HAMIK HARTOUNIAN
Floor/Roof Diaphrgm/Shear Wall 2/4/2022 Approved HAMIK HARTOUNIAN
PLUMBING-Rough 2/4/2022 Partial Approval HAMIK HARTOUNIAN
BUILDING-Rough-Frame 2/9/2022 Approved HAMIK HARTOUNIAN
HVAC-Rough 2/9/2022 Approved HAMIK HARTOUNIAN
Interior/Exterior Lathing 2/9/2022 Approved HAMIK HARTOUNIAN
PLUMBING-Rough 2/9/2022 Approved HAMIK HARTOUNIAN
Insulation 2/17/2022 Approved CHARLES BOGHOSKHAN
Drywall Nailing 3/10/2022 Approved HAMIK HARTOUNIAN
Shower Pan 3/30/2022 Conditional Approval HAMIK HARTOUNIAN
ELECTRICAL-Final 8/22/2022 Approved HAMIK HARTOUNIAN
PLUMBING-Final 8/22/2022 Approved HAMIK HARTOUNIAN
Final 9/7/2022 Corrections Issued HAMIK HARTOUNIAN
Green Building Final 9/7/2022 Approved HAMIK HARTOUNIAN
HVAC-Final 9/7/2022 Approved HAMIK HARTOUNIAN
SGSOV-Seismic Gas S/O Valve 9/7/2022 SGSOV Approved HAMIK HARTOUNIAN
Smoke Detectors 9/7/2022 Approved HAMIK HARTOUNIAN
Final 9/21/2022 OK to Issue CofO HAMIK HARTOUNIAN