4393 N SCANDIA WAY 90065
Certificate Information: 4393 N SCANDIA WAY 90065
- Application / Permit
- 20014-10000-01867
- Plan Check / Job No.
- B20LA07971
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- (N) ADDITON TO (E) SFD
- Permit Issued
- Issued on 1/8/2021
- Issuing Office
- Current Status
- CofO Issued on 10/1/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/1/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 5/22/2020 | JESSE ARELLANO |
| Corrections Issued | 6/2/2020 | JESSE ARELLANO |
| Quality Review Completed | 6/3/2020 | BILL STUTSMAN |
| Green Plans Picked Up | 7/28/2020 | APPLICANT |
| Applicant returned to address corrections | 9/26/2020 | JESSE ARELLANO |
| Plan Check Approved | 12/17/2020 | JESSE ARELLANO |
| No Progress | 12/17/2020 | JESSE ARELLANO |
| Plan Check Approved | 12/20/2020 | JESSE ARELLANO |
| Issued | 1/8/2021 | APPLICANT |
| Building Plans Picked Up | 1/13/2021 | APPLICANT |
| CofO in Progress | 9/22/2022 | HAMIK HARTOUNIAN |
| Permit Finaled | 10/1/2022 | DEROLD HAUFF |
| CofO Issued | 10/1/2022 | DEROLD HAUFF |
| Permit Finaled | 10/1/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| Low Impact Development | Cleared | 6/17/2020 | MARTIN FRAGOSO |
| BHO/Hillside ordinance | Cleared | 6/30/2020 | RENZ SORIANO |
| Eng Process Fee Ord 176,300 | Cleared | 6/30/2020 | RENZ SORIANO |
| BHO/Hillside ordinance | Cleared | 7/1/2020 | RENZ SORIANO |
| BHO/Hillside ordinance | Cleared | 7/1/2020 | RENZ SORIANO |
| Hydrant and Access approval | Cleared | 7/13/2020 | MATTHEW CRAIG |
| Green Code | Cleared | 7/23/2020 | KHEDER ALRAZAA |
| Specific Plan | Cleared | 10/8/2020 | KENTON TRINH |
Contact Information
| Contractor | Williams Christopher; Lic. No.: 711380-B | P O BOX 8652 LA CRESCENTA, CA 91224 |
| Engineer | Phillips,, Craig Richard; Lic. No.: C69673 | 2123 VESTAL AVE LOS ANGELES, CA 90026 |
Inspector Information
| NICHOLAS LOPEZ, (213) 202-3224 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Grading | 4/9/2021 | Conditional Approval | HAMIK HARTOUNIAN |
| Piling/Pier/Caisson | 4/13/2021 | Approved | HAMIK HARTOUNIAN |
| Piling/Pier/Caisson | 4/27/2021 | Approved | HAMIK HARTOUNIAN |
| Deputy Reinf. Concrete | 4/28/2021 | Conditional Approval | THOMAS LOGRASSO |
| Piling/Pier/Caisson | 5/6/2021 | Approved | HAMIK HARTOUNIAN |
| PLUMBING-Rough | 6/30/2021 | Not Ready for Inspection | CRAIG VAUGHAN |
| PLUMBING-Rough | 7/2/2021 | Corrections Issued | HAMIK HARTOUNIAN |
| PLUMBING-Rough | 7/21/2021 | Partial Approval | HAMIK HARTOUNIAN |
| Deputy Reinf. Concrete | 8/11/2021 | Conditional Approval | HAMIK HARTOUNIAN |
| Excavation/Setback/Form/Re-Bar | 8/16/2021 | Not Ready for Inspection | COREY HUPP |
| Excavation/Setback/Form/Re-Bar | 8/17/2021 | Corrections Issued | COREY HUPP |
| Excavation/Setback/Form/Re-Bar | 8/18/2021 | Partial Approval | BRIAN SULLIVAN |
| Deputy Reinf. Concrete | 8/20/2021 | Partial Approval | SCOTT FINNILA |
| Excavation/Setback/Form/Re-Bar | 9/1/2021 | Partial Approval | HAMIK HARTOUNIAN |
| Footing/Foundation/Slab | 9/1/2021 | Approved | HAMIK HARTOUNIAN |
| Deputy Reinf. Concrete | 9/2/2021 | Partial Approval | SCOTT FINNILA |
| Excavation/Setback/Form/Re-Bar | 9/9/2021 | Partial Approval | HAMIK HARTOUNIAN |
| Floor/Roof Diaphrgm/Shear Wall | 11/9/2021 | Partial Approval | HAMIK HARTOUNIAN |
| Green Building Rough | 11/9/2021 | Approved | HAMIK HARTOUNIAN |
| Floor/Roof Diaphrgm/Shear Wall | 12/16/2021 | Corrections Issued | HAMIK HARTOUNIAN |
| ELECTRICAL-Rough | 2/4/2022 | Approved | HAMIK HARTOUNIAN |
| Floor/Roof Diaphrgm/Shear Wall | 2/4/2022 | Approved | HAMIK HARTOUNIAN |
| PLUMBING-Rough | 2/4/2022 | Partial Approval | HAMIK HARTOUNIAN |
| BUILDING-Rough-Frame | 2/9/2022 | Approved | HAMIK HARTOUNIAN |
| HVAC-Rough | 2/9/2022 | Approved | HAMIK HARTOUNIAN |
| Interior/Exterior Lathing | 2/9/2022 | Approved | HAMIK HARTOUNIAN |
| PLUMBING-Rough | 2/9/2022 | Approved | HAMIK HARTOUNIAN |
| Insulation | 2/17/2022 | Approved | CHARLES BOGHOSKHAN |
| Drywall Nailing | 3/10/2022 | Approved | HAMIK HARTOUNIAN |
| Shower Pan | 3/30/2022 | Conditional Approval | HAMIK HARTOUNIAN |
| ELECTRICAL-Final | 8/22/2022 | Approved | HAMIK HARTOUNIAN |
| PLUMBING-Final | 8/22/2022 | Approved | HAMIK HARTOUNIAN |
| Final | 9/7/2022 | Corrections Issued | HAMIK HARTOUNIAN |
| Green Building Final | 9/7/2022 | Approved | HAMIK HARTOUNIAN |
| HVAC-Final | 9/7/2022 | Approved | HAMIK HARTOUNIAN |
| SGSOV-Seismic Gas S/O Valve | 9/7/2022 | SGSOV Approved | HAMIK HARTOUNIAN |
| Smoke Detectors | 9/7/2022 | Approved | HAMIK HARTOUNIAN |
| Final | 9/21/2022 | OK to Issue CofO | HAMIK HARTOUNIAN |