3501 N CAHUENGA BLVD 90068

Certificate Information: 3501 N CAHUENGA BLVD 90068

Application / Permit
20014-10000-01866
Plan Check / Job No.
B20LA07958
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(13) Office
Work Description
ADDITION OF ENTRY UNCOVERED STRUCTURE (9' X 9.5', 85.5 SF) AND TENANT IMPROVEMENT TO (E) 7,574 SF OFFICE BUILDING WITH. SCOPE OF WORK TO INCLUDE NEW OPENINGS THROUGH EXISITING EXTERIOR CMU WALL, NON-LOAD BEARING PARTITION WALLS FOR OFFICE, NEW SKYLIGHTS, AND 2 ADA BATHROOMS.
Permit Issued
Issued on 10/6/2020
Issuing Office
Current Status
Permit Finaled on 2/1/2022

Permit Application Status History

Submitted 5/1/2020 APPLICANT
Assigned to Plan Check Engineer 5/22/2020 ARSALAN SHABESTARI
Corrections Issued 5/28/2020 ARSALAN SHABESTARI
Quality Review Completed 6/5/2020 HERNAN ARREOLA
Disabled Access Plans Picked Up 7/17/2020 APPLICANT
Applicant returned to address corrections 7/29/2020 ARSALAN SHABESTARI
Applicant returned to address corrections 8/6/2020 ARSALAN SHABESTARI
Plan Check Approved 9/17/2020 ARSALAN SHABESTARI
Issued 10/6/2020 APPLICANT
Building Plans Picked Up 10/7/2020 APPLICANT
Permit Finaled 2/1/2022 ROBERT DAVIS

Permit Application Clearance Information

Miscellaneous Cleared 6/26/2020 MAXFIELD VERMY
Specific Plan Cleared 7/2/2020 OLGA AYALA
Eng Process Fee Ord 176,300 Cleared 7/6/2020 GABRIEL ROBLES
Highway dedication Cleared 7/6/2020 GABRIEL ROBLES
Roof/Waste drainage to street Cleared 7/6/2020 GABRIEL ROBLES
Sewer availability Cleared 7/6/2020 GABRIEL ROBLES
Green Code Cleared 7/29/2020 ARSALAN SHABESTARI
DAS Clearance Cleared 9/10/2020 ARSALAN SHABESTARI
Specific Plan Cleared 9/11/2020 LIZZI BEDUYA
Grading Pre-Inspection Cleared 9/13/2020 ARSALAN SHABESTARI

Contact Information

Contractor City Constructors Inc; Lic. No.: 834591-B 450 S RAYMOND AVENUE      PASADENA, CA 91105
Engineer Phillips,, Craig Richard; Lic. No.: C69673 2123 VESTAL AVE      LOS ANGELES, CA 90026

Inspector Information

JEFFREY FULTON, (818) 374-1132 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 12/24/2020 Conditional Approval ROBERT DAVIS
Deputy Reinf. Concrete 12/30/2020 Conditional Approval ROBERT DAVIS
Deputy Steel/Welding 1/21/2021 Conditional Approval ROBERT DAVIS
Light Gage Steel Frame 2/4/2021 Partial Approval ROBERT DAVIS
Drywall Nailing 2/17/2021 Partial Approval ROBERT DAVIS
Excavation/Setback/Form/Re-Bar 2/17/2021 Conditional Approval ROBERT DAVIS
Footing/Foundation/Slab 2/17/2021 Approved ROBERT DAVIS
Light Gage Steel Frame 2/22/2021 Order to Comply Issued ROBERT DAVIS
Drywall Nailing 3/2/2021 Partial Approval ROBERT DAVIS
Wood Frame 3/30/2021 Partial Approval ROBERT DAVIS
Drywall Nailing 5/27/2021 Not Ready for Inspection ROBERT DAVIS
Wood Frame 5/27/2021 Approved ROBERT DAVIS
Wood Frame 6/18/2021 Partial Approval ROBERT DAVIS
Final 9/1/2021 Not Ready for Inspection ROBERT DAVIS
SGSOV-Seismic Gas S/O Valve 9/1/2021 SGSOV Not Ready ROBERT DAVIS
Smoke Detectors 9/1/2021 Approved ROBERT DAVIS
Final 1/11/2022 Not Ready for Inspection ROBERT DAVIS
SGSOV-Seismic Gas S/O Valve 1/11/2022 SGSOV Approved ROBERT DAVIS
Final 2/1/2022 Permit Finaled ROBERT DAVIS