415 W AVENUE 42 90065
Certificate Information: 415 W AVENUE 42 90065
- Application / Permit
- 20014-10000-01839
- Plan Check / Job No.
- B20LA07854
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- INTERIOR REMODEL, DEMOLISH COVERED PORCH AND REPAIR (E) RETAINING WALLS OF FIRST LEVEL OF (E) SINGLE FAMILY DWELLING
- Permit Issued
- Issued on 12/11/2020
- Issuing Office
- Current Status
- CofO Issued on 8/13/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/29/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 5/22/2020 | AMIR DANAI |
| Corrections Issued | 5/28/2020 | AMIR DANAI |
| Quality Review Completed | 6/9/2020 | ARMEN JIVALAGIAN |
| Applicant returned to address corrections | 9/18/2020 | AMIR DANAI |
| Building Plans Picked Up | 9/24/2020 | APPLICANT |
| Plan Check Approved | 12/10/2020 | AMIR DANAI |
| Issued | 12/11/2020 | APPLICANT |
| CofO in Progress | 6/25/2022 | OSVALDO PARAMO |
| CofO in Progress | 6/25/2022 | OSVALDO PARAMO |
| Permit Finaled | 8/13/2022 | DEROLD HAUFF |
| CofO Issued | 8/13/2022 | DEROLD HAUFF |
| Permit Finaled | 8/13/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 9/17/2020 | JUAN ASHTON |
| Roof/Waste drainage to street | Cleared | 9/17/2020 | JUAN ASHTON |
| GPI Written Notices | Cleared | 11/30/2020 | AMIR DANAI |
| Grading Pre-Inspection | Cleared | 11/30/2020 | AMIR DANAI |
| Green Code | Cleared | 12/9/2020 | AMIR DANAI |
Contact Information
| Contractor | L A Green Designs; Lic. No.: 988980-B | P O BOX 411603 LOS ANGELES, CA 90041 |
| Engineer | Khazra,, Afshin; Lic. No.: C50250 | 22855 PAUL REVERE DR CALABASAS, CA 91302 |
Inspector Information
| OSVALDO PARAMO, (213) 202-9854 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 1/13/2021 | Partial Approval | OSVALDO PARAMO |
| Piling/Pier/Caisson | 1/13/2021 | Partial Approval | OSVALDO PARAMO |
| Excavation/Setback/Form/Re-Bar | 1/15/2021 | Approved | OSVALDO PARAMO |
| Piling/Pier/Caisson | 1/15/2021 | Approved | OSVALDO PARAMO |
| Excavation/Setback/Form/Re-Bar | 3/9/2021 | Not Ready for Inspection | OSVALDO PARAMO |
| Footing/Foundation/Slab | 3/9/2021 | Not Ready for Inspection | OSVALDO PARAMO |
| Excavation/Setback/Form/Re-Bar | 3/12/2021 | Approved | OSVALDO PARAMO |
| Footing/Foundation/Slab | 3/12/2021 | Approved | OSVALDO PARAMO |
| Deputy Shotcrete | 3/19/2021 | No Access for Inspection | ELMER BLAND |
| Footing/Foundation/Slab | 4/20/2021 | Partial Approval | OSVALDO PARAMO |
| Underground Mechanical | 4/20/2021 | Partial Approval | OSVALDO PARAMO |
| Rough-Elec/Plmb/HVAC | 5/19/2021 | Approved | OSVALDO PARAMO |
| BUILDING-Rough-Frame | 5/25/2021 | Partial Inspection | OSVALDO PARAMO |
| Green Building Rough | 5/25/2021 | Approved | OSVALDO PARAMO |
| Wood Frame | 6/1/2021 | Not Ready for Inspection | OSVALDO PARAMO |
| BUILDING-Rough-Frame | 6/28/2021 | Approved | OSVALDO PARAMO |
| Insulation | 7/2/2021 | Approved | WILLIAM WREN |
| Shower Pan | 8/25/2021 | Approved | RUBEN SALAS |
| Shower Pan | 8/27/2021 | Corrections Issued | ASHLEY THOMPSON |
| Shower Pan | 8/30/2021 | Approved | ALAN MORELOS |
| Interior/Exterior Lathing | 8/31/2021 | Approved | ASHLEY THOMPSON |
| Shower Pan | 8/31/2021 | Approved | ASHLEY THOMPSON |
| Drywall Nailing | 11/23/2021 | Approved | JUSTIN HAWLEY |
| Final | 3/22/2022 | Not Ready for Inspection | OSVALDO PARAMO |
| Green Building Final | 3/22/2022 | Not Ready for Inspection | OSVALDO PARAMO |
| SGSOV-Seismic Gas S/O Valve | 3/22/2022 | SGSOV Not Ready | OSVALDO PARAMO |
| Smoke Detectors | 3/22/2022 | Not Ready for Inspection | OSVALDO PARAMO |
| Final | 5/24/2022 | Conditional Approval | OSVALDO PARAMO |
| Green Building Final | 5/24/2022 | Approved | OSVALDO PARAMO |
| SGSOV-Seismic Gas S/O Valve | 5/24/2022 | SGSOV Approved | OSVALDO PARAMO |
| Smoke Detectors | 5/24/2022 | Approved | OSVALDO PARAMO |
| Final | 5/31/2022 | Partial Inspection | FREDDIE RIVERA |
| Final | 6/13/2022 | OK to Issue CofO | OSVALDO PARAMO |