9963 N PALI AVE 91042

Certificate Information: 9963 N PALI AVE 91042

Application / Permit
20014-10000-01835
Plan Check / Job No.
B20LA07822
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ADD GROUND FLOOR AND A 2ND STORY ADDITION TO AN EXISTING FAMILY DWELLING WITH ATTACHED GARAGE.
Permit Issued
Issued on 11/8/2020
Issuing Office
Current Status
CofO Issued on 12/10/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/29/2020 APPLICANT
Assigned to Plan Check Engineer 5/4/2020 MAHNAZ NOURHASHEMI
Corrections Issued 5/14/2020 MAHNAZ NOURHASHEMI
Quality Review Completed 5/14/2020 JASON HEALEY
Building Plans Picked Up 5/18/2020 APPLICANT
Green Plans Picked Up 7/22/2020 APPLICANT
Plan Check Approved 11/6/2020 MAHNAZ NOURHASHEMI
Issued 11/8/2020 APPLICANT
CofO in Progress 12/5/2022 WILLIAM WREN
Permit Finaled 12/10/2022 MICHAEL SMITH
CofO Issued 12/10/2022 MICHAEL SMITH
Permit Finaled 12/10/2022 MICHAEL SMITH

Permit Application Clearance Information

Green Code Cleared 7/21/2020 KHEDER ALRAZAA
Eng Process Fee Ord 176,300 Cleared 8/3/2020 GABRIEL ROBLES
Sewer availability Cleared 8/3/2020 GABRIEL ROBLES
Low Impact Development Cleared 10/1/2020 SARAH YOUSSEF
GPI Written Notices Cleared 10/5/2020 MAHNAZ NOURHASHEMI
Grading Pre-Inspection Cleared 10/5/2020 MAHNAZ NOURHASHEMI
Roof/Waste drainage to street Cleared 10/5/2020 GABRIEL ROBLES

Contact Information

Contractor Owner-Builder       ,
Engineer Hayrapetian,, Vahe; Lic. No.: C87305 PO BOX 2172      PASADENA, CA 91102

Inspector Information

NICHOLAS TROWBRIDGE, (818) 374-1174 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Floor/Roof Diaphrgm/Shear Wall 4/26/2021 Approved MATTHEW NELSON
BUILDING-Rough-Frame 5/11/2021 Not Ready for Inspection MATTHEW NELSON
ELECTRICAL-Rough 5/11/2021 Approved MATTHEW NELSON
Green Building Rough 5/11/2021 Approved MATTHEW NELSON
PLUMBING-Rough 5/11/2021 Approved MATTHEW NELSON
BUILDING-Rough-Frame 5/27/2021 Approved MATTHEW NELSON
Interior/Exterior Lathing 5/27/2021 Approved MATTHEW NELSON
Shower Pan 5/27/2021 Approved MATTHEW NELSON
Insulation 6/3/2021 Approved MATTHEW NELSON
Drywall Nailing 6/16/2021 Approved DEANDRE HOFFMAN
Final 10/14/2022 Corrections Issued MATTHEW NELSON
Footing/Foundation/Slab 10/14/2022 Approved MATTHEW NELSON
Green Building Final 10/14/2022 Corrections Issued MATTHEW NELSON
SGSOV-Seismic Gas S/O Valve 10/14/2022 SGSOV Approved MATTHEW NELSON
Smoke Detectors 10/14/2022 Approved MATTHEW NELSON
ELECTRICAL-Final 11/28/2022 Approved WILLIAM WREN
Final 11/28/2022 Corrections Issued WILLIAM WREN
Green Building Final 11/28/2022 Approved WILLIAM WREN
HVAC-Final 11/28/2022 Approved WILLIAM WREN
PLUMBING-Final 11/28/2022 Approved WILLIAM WREN
Final 12/2/2022 OK to Issue CofO WILLIAM WREN