4715 1/2 W COUNCIL ST 90004
Certificate Information: 4715 1/2 W COUNCIL ST 90004
- Application / Permit
- 20014-10000-01813
- Plan Check / Job No.
- B20LA07735
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT EXISTING ATTACHED 1-STORY GUEST ROOM (240 SF) WITH ADDITION TO 1-STORY ADU (330 SF) PER LAMC 12.22 A.33 (c) AND (e).
- Permit Issued
- Issued on 10/22/2020
- Issuing Office
- Current Status
- CofO Issued on 12/3/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/28/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 5/22/2020 | CHUNG-WEN CHUANG |
| Corrections Issued | 6/9/2020 | CHUNG-WEN CHUANG |
| Quality Review Completed | 6/22/2020 | KESETE HAREGOT |
| Building Plans Picked Up | 6/29/2020 | APPLICANT |
| Green Plans Picked Up | 7/6/2020 | APPLICANT |
| Applicant returned to address corrections | 9/14/2020 | CHUNG-WEN CHUANG |
| Applicant returned to address corrections | 9/28/2020 | CHUNG-WEN CHUANG |
| Plan Check Approved | 10/15/2020 | CHUNG-WEN CHUANG |
| Issued | 10/22/2020 | APPLICANT |
| CofO in Progress | 11/29/2021 | CRAIG DAVIS |
| Permit Finaled | 12/3/2021 | DEROLD HAUFF |
| CofO Issued | 12/3/2021 | DEROLD HAUFF |
| Permit Finaled | 12/3/2021 | DEROLD HAUFF |
Permit Application Clearance Information
| Green Code | Cleared | 8/24/2020 | VIVIAN LAO |
| HPOZ | Cleared | 9/15/2020 | LAMBERT GIESSINGER |
| Address approval | Cleared | 9/18/2020 | JAMES KHO |
| Roof/Waste drainage to street | Cleared | 9/18/2020 | JAMES KHO |
| Sewer availability | Cleared | 9/18/2020 | JAMES KHO |
| Eng Process Fee Ord 176,300 | Cleared | 9/21/2020 | JAMES KHO |
| Tenant Habitability Plan | Cleared | 10/14/2020 | STEVEN HOFSTAD |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Lee,, Cheng; Lic. No.: C24845 | 2725 COLD PLAINS DR HACIENDA HEIGHTS, CA 91745 |
Inspector Information
| JEFFREY MEAD, (213) 202-3240 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 12/9/2020 | Approved | CHRIS CHRISTENSEN |
| Pre-Inspection | 1/7/2021 | Approved | CHRIS CHRISTENSEN |
| BUILDING-Rough-Frame | 11/19/2021 | Partial Approval | CRAIG DAVIS |
| BUILDING-Rough-Frame | 11/24/2021 | Approved | CRAIG DAVIS |
| Drywall Nailing | 11/24/2021 | Approved | CRAIG DAVIS |
| ELECTRICAL-Final | 11/24/2021 | Approved | CRAIG DAVIS |
| Final | 11/24/2021 | OK to Issue CofO | CRAIG DAVIS |
| Footing/Foundation/Slab | 11/24/2021 | Approved | CRAIG DAVIS |
| Green Building Final | 11/24/2021 | Approved | CRAIG DAVIS |
| Green Building Rough | 11/24/2021 | Approved | CRAIG DAVIS |
| HVAC-Final | 11/24/2021 | Approved | CRAIG DAVIS |
| PLUMBING-Final | 11/24/2021 | Approved | CRAIG DAVIS |
| SGSOV-Seismic Gas S/O Valve | 11/24/2021 | SGSOV Approved | CRAIG DAVIS |
| Service/Power Release | 11/24/2021 | Approved | CRAIG DAVIS |
| Smoke Detectors | 11/24/2021 | Approved | CRAIG DAVIS |