6017 N SIMPSON AVE 91606
Certificate Information: 6017 N SIMPSON AVE 91606
- Application / Permit
- 20014-10000-01795
- Plan Check / Job No.
- B20LA07650
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT DETACHED GARAGE (374 SQ.FT.) TO AN ACCESSORY DWELLING UNIT WITH 1-STORY ADDITION [16'-4" X 12'-6"] IN FRONT.
- Permit Issued
- Issued on 7/17/2020
- Issuing Office
- Metro
- Current Status
- CofO Issued on 6/5/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/28/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 4/28/2020 | ADAM HEGAZI |
| Corrections Issued | 5/1/2020 | ADAM HEGAZI |
| Applicant returned to address corrections | 5/20/2020 | JESSE JIMENEZ |
| Plan Check Approved | 5/21/2020 | JESSE JIMENEZ |
| Building Plans Picked Up | 5/21/2020 | APPLICANT |
| Issued | 7/17/2020 | APPLICANT |
| CofO in Progress | 5/10/2021 | DANIEL DREW |
| CofO Issued | 6/5/2021 | MICHAEL SMITH |
| Permit Finaled | 6/5/2021 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 5/8/2020 | ADRIAN CASTRO |
| Construction within easement | Cleared | 5/8/2020 | WALTER RAMIREZ |
| Roof/Waste drainage to street | Cleared | 5/8/2020 | ADRIAN CASTRO |
| Eng Process Fee Ord 176,300 | Cleared | 5/12/2020 | ADRIAN CASTRO |
| Sewer availability | Cleared | 5/12/2020 | ADRIAN CASTRO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Landers,, Jesse Eugene; Lic. No.: C83060 | 2101 BENECIA AVE LOS ANGELES, CA 90025 |
Inspector Information
| GAREN HAYRAPETYAN, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
| ROBERTO PALACIOS-LOPEZ, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 9/17/2020 | Approved | DANIEL DREW |
| Sewer | 9/17/2020 | Approved | DANIEL DREW |
| BUILDING-Rough-Frame | 10/27/2020 | Corrections Issued | JOHN HAYES |
| ELECTRICAL-Rough | 10/27/2020 | Not Ready for Inspection | JOHN HAYES |
| Green Building Rough | 10/27/2020 | Not Ready for Inspection | JOHN HAYES |
| ELECTRICAL-Rough | 11/17/2020 | Approved | DANIEL DREW |
| Gas Test | 11/17/2020 | Approved | DANIEL DREW |
| PLUMBING-Rough | 11/17/2020 | Corrections Issued | DANIEL DREW |
| BUILDING-Rough-Frame | 12/1/2020 | Corrections Issued | JOHN HAYES |
| Floor/Roof Diaphrgm/Shear Wall | 12/1/2020 | Not Ready for Inspection | JOHN HAYES |
| Green Building Rough | 12/1/2020 | Not Ready for Inspection | JOHN HAYES |
| PLUMBING-Rough | 12/1/2020 | Not Ready for Inspection | JOHN HAYES |
| Rough-Elec/Plmb/HVAC | 12/1/2020 | Not Ready for Inspection | JOHN HAYES |
| Shower Pan | 12/1/2020 | Not Ready for Inspection | JOHN HAYES |
| BUILDING-Rough-Frame | 3/1/2021 | Not Ready for Inspection | DANIEL DREW |
| Floor/Roof Diaphrgm/Shear Wall | 3/1/2021 | Conditional Approval | DANIEL DREW |
| Green Building Rough | 3/1/2021 | Not Ready for Inspection | DANIEL DREW |
| PLUMBING-Rough | 3/1/2021 | Approved | DANIEL DREW |
| Pre-Inspection | 3/1/2021 | Approved | DANIEL DREW |
| Shower Pan | 3/1/2021 | Approved | DANIEL DREW |
| Insulation | 3/8/2021 | Approved | DANIEL DREW |
| Interior/Exterior Lathing | 3/8/2021 | Approved | DANIEL DREW |
| BUILDING-Rough-Frame | 3/24/2021 | Approved | DANIEL DREW |
| Drywall Nailing | 3/24/2021 | Approved | DANIEL DREW |
| Green Building Rough | 3/24/2021 | Approved | DANIEL DREW |
| Special/Order Compliance | 3/24/2021 | Approved | DANIEL DREW |
| ELECTRICAL-Final | 4/28/2021 | Approved | DANIEL DREW |
| Final | 4/28/2021 | Not Ready for Inspection | DANIEL DREW |
| Green Building Final | 4/28/2021 | Approved | DANIEL DREW |
| HVAC-Final | 4/28/2021 | Approved | DANIEL DREW |
| PLUMBING-Final | 4/28/2021 | Corrections Issued | DANIEL DREW |
| SGSOV-Seismic Gas S/O Valve | 4/28/2021 | SGSOV Not Ready | DANIEL DREW |
| Smoke Detectors | 4/28/2021 | Approved | DANIEL DREW |
| Final | 5/6/2021 | OK to Issue CofO | DANIEL DREW |
| PLUMBING-Final | 5/6/2021 | Approved | DANIEL DREW |
| SGSOV-Seismic Gas S/O Valve | 5/6/2021 | SGSOV Approved | DANIEL DREW |