1734 S HAYWORTH AVE 90035
Certificate Information: 1734 S HAYWORTH AVE 90035
- Application / Permit
- 20014-10000-01794
- Plan Check / Job No.
- B20LA07647
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW ACCESSORY DWELLING UNIT AT SECOND STORY OF 365 S.F. TO (E) GARAGE (DETACHED) 1 OF 2
- Permit Issued
- Issued on 9/16/2021
- Issuing Office
- Current Status
- CofO Issued on 7/1/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/30/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 5/22/2020 | SERGIO GUTIERREZ |
| Corrections Issued | 5/29/2020 | SERGIO GUTIERREZ |
| Quality Review Completed | 6/18/2020 | KESETE HAREGOT |
| Green Plans Picked Up | 12/31/2020 | APPLICANT |
| Plan Check Approved | 5/20/2021 | SERGIO GUTIERREZ |
| Issued | 9/16/2021 | APPLICANT |
| CofO in Progress | 6/15/2023 | JOSE AVILA |
| Permit Finaled | 7/1/2023 | DEROLD HAUFF |
| CofO Issued | 7/1/2023 | DEROLD HAUFF |
| Permit Finaled | 7/1/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 10/13/2020 | ELENA LOPEZ |
| Eng Process Fee Ord 176,300 | Cleared | 10/16/2020 | PAMELA TENEZA |
| Sewer availability | Cleared | 10/16/2020 | PAMELA TENEZA |
| Green Code | Cleared | 12/30/2020 | SERGIO GUTIERREZ |
| ZI | Cleared | 1/7/2021 | TERRI OSBORNE |
| Hydrant and Access approval | Cleared | 1/29/2021 | KURT CORRAL |
| Low Impact Development | Cleared | 4/12/2021 | ORVAL HERNANDEZ-MARCI |
| Roof/Waste drainage to street | Cleared | 4/16/2021 | JEANIE LAM |
Contact Information
| Contractor | Addition Building & Design Inc; Lic. No.: 925471-B | 4335 VAN NUYS BLVD STE 354 SHERMAN OAKS, CA 91403 |
| Engineer | Garcia,, Ricardo Ray; Lic. No.: C66957 | 27702 QUINCY ST CASTAIC, CA 91384 |
Inspector Information
| DAVID WILLIAMS, (213) 202-3126 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 10/5/2021 | Corrections Issued | STUART CHAPMAN |
| METHANE-Barrier | 10/5/2021 | Approved | STUART CHAPMAN |
| METHANE-Subgrade | 10/5/2021 | Approved | STUART CHAPMAN |
| Deputy Reinf. Concrete | 10/6/2021 | Partial Approval | RUBEN SALAS |
| Deputy Drilled-In Anchors | 10/18/2021 | Approved | JOSE AVILA |
| Footing/Foundation/Slab | 10/18/2021 | Corrections Issued | SCOTT FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 10/27/2021 | Corrections Issued | JOSE AVILA |
| Floor/Roof Diaphrgm/Shear Wall | 11/2/2021 | Corrections Issued | STUART CHAPMAN |
| Footing/Foundation/Slab | 11/2/2021 | Approved | JOSE AVILA |
| Footing/Foundation/Slab | 11/2/2021 | Approved | STUART CHAPMAN |
| Rough-Elec/Plmb/HVAC | 11/12/2021 | Corrections Issued | JOSE AVILA |
| PLUMBING-Rough | 11/18/2021 | Approved | STUART CHAPMAN |
| Underground Mechanical | 11/18/2021 | Approved | STUART CHAPMAN |
| Insulation | 11/23/2021 | Conditional Approval | JOSE AVILA |
| BUILDING-Rough-Frame | 11/30/2021 | No Access for Inspection | JOSE AVILA |
| Floor/Roof Diaphrgm/Shear Wall | 11/30/2021 | No Access for Inspection | JOSE AVILA |
| Green Building Rough | 11/30/2021 | No Access for Inspection | JOSE AVILA |
| METHANE-Rough | 11/30/2021 | No Access for Inspection | JOSE AVILA |
| Floor/Roof Diaphrgm/Shear Wall | 12/6/2021 | Approved | JOSE AVILA |
| BUILDING-Rough-Frame | 12/8/2021 | Corrections Issued | JOSE AVILA |
| Shower Pan | 12/8/2021 | Approved | JOSE AVILA |
| BUILDING-Rough-Frame | 12/27/2021 | Partial Approval | JOSE AVILA |
| Drywall Nailing | 12/27/2021 | Approved | JOSE AVILA |
| Interior/Exterior Lathing | 1/10/2022 | Corrections Issued | JOSE AVILA |
| BUILDING-Rough-Frame | 3/22/2022 | Partial Approval | JOSE AVILA |
| ELECTRICAL-Final | 3/22/2022 | Not Ready for Inspection | JOSE AVILA |
| Green Building Final | 3/22/2022 | Not Ready for Inspection | JOSE AVILA |
| Green Building Rough | 3/22/2022 | Approved | JOSE AVILA |
| HVAC-Final | 3/22/2022 | Not Ready for Inspection | JOSE AVILA |
| Interior/Exterior Lathing | 3/22/2022 | Approved | JOSE AVILA |
| METHANE-Final | 3/22/2022 | Approved | JOSE AVILA |
| METHANE-Rough | 3/22/2022 | Approved | JOSE AVILA |
| PLUMBING-Final | 3/22/2022 | Not Ready for Inspection | JOSE AVILA |
| SGSOV-Seismic Gas S/O Valve | 3/22/2022 | SGSOV Not Ready | JOSE AVILA |
| Smoke Detectors | 3/22/2022 | Approved | JOSE AVILA |
| BUILDING-Rough-Frame | 3/29/2022 | Approved | JOSE AVILA |
| Final | 3/29/2022 | Corrections Issued | JOSE AVILA |
| Green Building Final | 3/29/2022 | Approved | JOSE AVILA |
| SGSOV-Seismic Gas S/O Valve | 3/29/2022 | SGSOV Approved | JOSE AVILA |
| Final | 4/4/2022 | Corrections Issued | JOSE AVILA |
| Final | 5/23/2022 | Corrections Issued | JOSE AVILA |
| Final | 6/14/2023 | OK to Issue CofO | JOSE AVILA |