1468 W MORTON PL 90026

Certificate Information: 1468 W MORTON PL 90026

Application / Permit
20014-10000-01792
Plan Check / Job No.
B20LA07641
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
PROPOSED ADDITIONS AT TWO LOCATIONS (7'-11" X22'-7" , 7'-10" X24'-2") TO ATTACH 3 DETACHED SINGLE FAMILY DWELLINGS TO CREATE 1 SINGLE FAMILY DWELLING.
Permit Issued
Issued on 9/21/2021
Issuing Office
Current Status
CofO Issued on 3/28/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/29/2020 APPLICANT
Assigned to Plan Check Engineer 5/22/2020 MICHAEL LOPEZ
Corrections Issued 5/28/2020 MICHAEL LOPEZ
Green Plans Picked Up 5/28/2020 APPLICANT
Quality Review Completed 6/5/2020 QUAN NGHIEM
Building Plans Picked Up 6/15/2020 APPLICANT
Applicant returned to address corrections 6/28/2021 MICHAEL LOPEZ
Applicant returned to address corrections 8/11/2021 MICHAEL LOPEZ
Plan Check Approved 9/21/2021 MICHAEL LOPEZ
Issued 9/21/2021 APPLICANT
CofO in Progress 3/21/2023 THOMAS LOGRASSO
Permit Finaled 3/28/2023 DEROLD HAUFF
CofO Issued 3/28/2023 DEROLD HAUFF
Permit Finaled 3/28/2023 DEROLD HAUFF

Permit Application Clearance Information

Sewer availability Cleared 7/17/2020 CECILIO NAVARRO
Address approval Cleared 7/21/2020 CECILIO NAVARRO
Eng Process Fee Ord 176,300 Cleared 7/22/2020 CECILIO NAVARRO
Low Impact Development Cleared 7/30/2020 MITESH PATEL
Demo/Removal of Rental Units Cleared 5/18/2021 SUSAN LIM
Roof/Waste drainage to street Cleared 5/24/2021 WALLIE JONG
Grading Pre-Inspection Cleared 6/30/2021 ALEXANDER HELFER
Green Code Cleared 6/30/2021 MICHAEL LOPEZ

Contact Information

Architect Garrison,, Catherine; Lic. No.: C31638 5109 MONTEZUMA      LOS ANGELES, CA 90042
Contractor Fanello Construction; Lic. No.: 308170-B 216 15TH PLACE      MANHATTAN BEACH, CA 90266
Engineer Phillips,, Craig Richard; Lic. No.: C69673 2123 VESTAL AVE      LOS ANGELES, CA 90026

Inspector Information

HAMIK HARTOUNIAN, (213) 202-3275 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 9/30/2021 Corrections Issued THOMAS LOGRASSO
Footing/Foundation/Slab 10/12/2021 Partial Inspection THOMAS LOGRASSO
Footing/Foundation/Slab 11/9/2021 Corrections Issued THOMAS LOGRASSO
Floor/Roof Diaphrgm/Shear Wall 11/22/2021 Corrections Issued THOMAS LOGRASSO
Floor/Roof Diaphrgm/Shear Wall 12/28/2021 Corrections Issued THOMAS LOGRASSO
ELECTRICAL-Rough 1/27/2022 Corrections Issued LILIANA PORTILLO
HVAC-Rough 1/27/2022 Corrections Issued LILIANA PORTILLO
PLUMBING-Rough 1/27/2022 Conditional Approval LILIANA PORTILLO
BUILDING-Rough-Frame 2/1/2022 Corrections Issued THOMAS LOGRASSO
Green Building Rough 2/1/2022 Not Ready for Inspection THOMAS LOGRASSO
Interior/Exterior Lathing 3/2/2022 Partial Approval THOMAS LOGRASSO
BUILDING-Rough-Frame 4/28/2022 Not Ready for Inspection THOMAS LOGRASSO
BUILDING-Rough-Frame 5/23/2022 Corrections Issued THOMAS LOGRASSO
Drywall Nailing 6/8/2022 Conditional Approval THOMAS LOGRASSO
Interior/Exterior Lathing 6/8/2022 Conditional Approval THOMAS LOGRASSO
BUILDING-Rough-Frame 9/14/2022 Approved THOMAS LOGRASSO
Final 9/14/2022 Corrections Issued THOMAS LOGRASSO
Footing/Foundation/Slab 9/14/2022 Approved THOMAS LOGRASSO
Green Building Final 9/14/2022 Approved THOMAS LOGRASSO
Green Building Rough 9/14/2022 Approved THOMAS LOGRASSO
SGSOV-Seismic Gas S/O Valve 9/14/2022 SGSOV Approved THOMAS LOGRASSO
Smoke Detectors 9/14/2022 Approved THOMAS LOGRASSO
Final 10/14/2022 Corrections Issued THOMAS LOGRASSO
Final 3/21/2023 OK to Issue CofO THOMAS LOGRASSO