6295 W IVARENE AVE 90068
Certificate Information: 6295 W IVARENE AVE 90068
- Application / Permit
- 20014-10000-01791
- Plan Check / Job No.
- B20LA07623
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- GROUND FLOOR ADDITION TO THE (E) BEDROOM TO CONVERT IT TO MASTER BEDROOM COMPLY WITH DEPARTMENT ORDER effective date 06/30/2017. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE *** see comments
- Permit Issued
- Issued on 2/19/2021
- Issuing Office
- Current Status
- CofO Issued on 8/25/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/28/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 4/29/2020 | AMIR DANAI |
| Corrections Issued | 4/29/2020 | AMIR DANAI |
| Applicant returned to address corrections | 6/9/2020 | FERNANDO FLORES |
| Applicant returned to address corrections | 7/7/2020 | RICARDO RAMIREZ |
| Applicant returned to address corrections | 7/23/2020 | RACHEL BEYENE |
| Building Plans Picked Up | 7/24/2020 | APPLICANT |
| Applicant returned to address corrections | 8/21/2020 | LUKE GONZALES |
| Plan Check Approved | 2/1/2021 | ADAM HEGAZI |
| Issued | 2/19/2021 | APPLICANT |
| CofO in Progress | 8/9/2022 | JOEL WILLIAMS |
| Permit Finaled | 8/25/2022 | DANIEL SANCHEZ |
| CofO Issued | 8/25/2022 | DANIEL SANCHEZ |
| Permit Finaled | 8/25/2022 | DANIEL SANCHEZ |
Permit Application Clearance Information
| BHO/Hillside ordinance | Cleared | 5/5/2020 | EMIL KYUPELYAN |
| BHO/Hillside ordinance | Cleared | 5/5/2020 | EMIL KYUPELYAN |
| BHO/Hillside ordinance | Cleared | 5/5/2020 | EMIL KYUPELYAN |
| Roof/Waste drainage to street | Cleared | 5/5/2020 | EMIL KYUPELYAN |
| GPI Written Notices | Cleared | 6/8/2020 | FERNANDO FLORES |
| Grading Pre-Inspection | Cleared | 6/8/2020 | AMIR DANAI |
| Green Code | Cleared | 6/8/2020 | AMIR DANAI |
| Low Impact Development | Cleared | 6/23/2020 | ROBIN YAMADA |
| Eng Process Fee Ord 176,300 | Cleared | 6/25/2020 | EMIL KYUPELYAN |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JOEL ORDAZ, (213) 252-3049 | Office Hours: 7:00-8:00 AM MON-FRI |
| PTOLEMY HILL, (213) 252-3049 | Office Hours: 7:00-8:00 AM MON-FRI |
| ARAM AVAKIAN, (213) 252-3049 | Office Hours: 7:00-8:00 AM MON-FRI |
| EDMOND DECKERT, (213) 252-3049 | Office Hours: 7:00-8:00 AM MON-FRI |
| TIMOTHY KEY, (213) 252-3049 | Office Hours: 7:00-8:00 AM MON-FRI |
| ROBERT CHAVEZ, (213) 252-3049 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| BUILDING-Rough-Frame | 6/23/2021 | Partial Approval | JOHN TCHANG |
| ELECTRICAL-Rough | 6/23/2021 | Not Ready for Inspection | JOHN TCHANG |
| Footing/Foundation/Slab | 6/23/2021 | Corrections Issued | JOHN TCHANG |
| Green Building Rough | 6/23/2021 | Not Ready for Inspection | JOHN TCHANG |
| PLUMBING-Rough | 6/23/2021 | Not Ready for Inspection | JOHN TCHANG |
| BUILDING-Rough-Frame | 7/7/2021 | Approved | JOHN TCHANG |
| ELECTRICAL-Rough | 7/7/2021 | Approved | JOHN TCHANG |
| Footing/Foundation/Slab | 7/7/2021 | Approved | JOHN TCHANG |
| Green Building Rough | 7/7/2021 | Approved | JOHN TCHANG |
| PLUMBING-Rough | 7/7/2021 | Approved | JOHN TCHANG |
| Final | 8/31/2021 | Conditional Approval | JOHN TCHANG |
| Green Building Final | 8/31/2021 | Approved | JOHN TCHANG |
| SGSOV-Seismic Gas S/O Valve | 8/31/2021 | SGSOV Approved | JOHN TCHANG |
| Smoke Detectors | 8/31/2021 | Approved | JOHN TCHANG |
| Final | 6/21/2022 | Partial Approval | JOHN TCHANG |