543 N FULLER AVE 90036
Certificate Information: 543 N FULLER AVE 90036
- Application / Permit
- 20014-10000-01744
- Plan Check / Job No.
- B20LA07454
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- TO ADD 162 SQ.FT. TO REAR OF PRIMARY RESIDENCE W/ MINOR INTERIOR REMODEL (SCOPE OF WORK ON PRIMARY RESIDENCE DUE TO WATER DAMAGE) 2 OF 2
- Permit Issued
- Issued on 8/20/2020
- Issuing Office
- Current Status
- CofO Issued on 2/6/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/23/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 5/14/2020 | SERGIO GUTIERREZ |
| Corrections Issued | 5/28/2020 | SERGIO GUTIERREZ |
| Quality Review Completed | 6/9/2020 | KESETE HAREGOT |
| Building Plans Picked Up | 6/16/2020 | APPLICANT |
| Green Plans Picked Up | 7/20/2020 | APPLICANT |
| Applicant returned to address corrections | 8/4/2020 | SERGIO GUTIERREZ |
| Plan Check Approved | 8/20/2020 | SERGIO GUTIERREZ |
| Issued | 8/20/2020 | APPLICANT |
| CofO in Progress | 2/1/2021 | CHRIS CHRISTENSEN |
| Permit Finaled | 2/6/2021 | DEROLD HAUFF |
| CofO Issued | 2/6/2021 | DEROLD HAUFF |
| Permit Finaled | 2/6/2021 | DEROLD HAUFF |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 6/25/2020 | RENZ SORIANO |
| Sewer availability | Cleared | 6/25/2020 | RENZ SORIANO |
| Eng Process Fee Ord 176,300 | Cleared | 6/29/2020 | RENZ SORIANO |
| Green Code | Cleared | 7/20/2020 | VIVIAN LAO |
Contact Information
| Contractor | Trinity Builders & Design Inc; Lic. No.: 988119-B | 7022 DARBY AVE UNIT A RESEDA, CA 91335 |
| Engineer | Le,, Thang Huu; Lic. No.: S4978 | 507 MAGELLAN RD ARCADIA, CA 91007 |
Inspector Information
| JOSE MACIAS, (213) 202-3125 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| ELECTRICAL-Rough | 8/26/2020 | Partial Approval | CHRIS CHRISTENSEN |
| Footing/Foundation/Slab | 8/26/2020 | Approved | CHRIS CHRISTENSEN |
| METHANE-Barrier | 8/26/2020 | Approved | CHRIS CHRISTENSEN |
| METHANE-Subgrade | 8/26/2020 | Approved | CHRIS CHRISTENSEN |
| PLUMBING-Rough | 8/26/2020 | Partial Approval | CHRIS CHRISTENSEN |
| Deputy Drilled-In Anchors | 8/27/2020 | Conditional Approval | THOMAS LOGRASSO |
| Floor/Roof Diaphrgm/Shear Wall | 8/31/2020 | Approved | CHRIS CHRISTENSEN |
| BUILDING-Rough-Frame | 10/6/2020 | Approved | CHRIS CHRISTENSEN |
| ELECTRICAL-Rough | 10/6/2020 | Approved | CHRIS CHRISTENSEN |
| Floor/Roof Diaphrgm/Shear Wall | 10/6/2020 | Approved | CHRIS CHRISTENSEN |
| Green Building Rough | 10/6/2020 | Approved | CHRIS CHRISTENSEN |
| METHANE-Rough | 10/6/2020 | Approved | CHRIS CHRISTENSEN |
| PLUMBING-Rough | 10/6/2020 | Approved | CHRIS CHRISTENSEN |
| Insulation | 10/9/2020 | Approved | CHRIS CHRISTENSEN |
| Interior/Exterior Lathing | 10/9/2020 | Partial Approval | CHRIS CHRISTENSEN |
| Drywall Nailing | 10/19/2020 | Approved | CHRIS CHRISTENSEN |
| Underground Mechanical | 10/19/2020 | Approved | CHRIS CHRISTENSEN |
| Final | 12/17/2020 | Corrections Issued | DAVID FEILER |
| Green Building Final | 12/17/2020 | Not Ready for Inspection | DAVID FEILER |
| SGSOV-Seismic Gas S/O Valve | 12/17/2020 | SGSOV Not Ready | DAVID FEILER |
| Smoke Detectors | 12/17/2020 | Not Ready for Inspection | DAVID FEILER |
| ELECTRICAL-Final | 2/1/2021 | Approved | CHRIS CHRISTENSEN |
| Final | 2/1/2021 | OK to Issue CofO | CHRIS CHRISTENSEN |
| Green Building Final | 2/1/2021 | Approved | CHRIS CHRISTENSEN |
| HVAC-Final | 2/1/2021 | Approved | CHRIS CHRISTENSEN |
| PLUMBING-Final | 2/1/2021 | Approved | CHRIS CHRISTENSEN |
| SGSOV-Seismic Gas S/O Valve | 2/1/2021 | SGSOV Approved | CHRIS CHRISTENSEN |
| Smoke Detectors | 2/1/2021 | Approved | CHRIS CHRISTENSEN |