406 E 83RD ST 90003

Certificate Information: 406 E 83RD ST 90003

Application / Permit
20014-10000-01725
Plan Check / Job No.
B20LA07354
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
PROPOSED ADDITION TO REAR OF SINGLE FAMILY DEWELLING TO CREATE MASTR BEDROOM WITH FULL BATH "COMPLY WITH DEPARTMENT ORDER effective date 04/10/2020. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE"
Permit Issued
Issued on 6/30/2020
Issuing Office
Current Status
CofO Issued on 5/19/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/27/2020 APPLICANT
Assigned to Plan Check Engineer 4/27/2020 SINA KHOSRAVI
Corrections Issued 5/14/2020 SINA KHOSRAVI
Applicant returned to address corrections 6/16/2020 JESSE JIMENEZ
Plan Check Approved 6/18/2020 JESSE JIMENEZ
Issued 6/30/2020 APPLICANT
Building Plans Picked Up 7/6/2020 APPLICANT
CofO in Progress 5/18/2021 MARIO CUEVAS
Permit Finaled 5/19/2021 BRUCE TODD
Permit Finaled 5/19/2021 BRUCE TODD
CofO Issued 5/19/2021 BRUCE TODD

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 6/8/2020 WALLIE JONG
Roof/Waste drainage to street Cleared 6/8/2020 WALLIE JONG
Sewer availability Cleared 6/8/2020 WALLIE JONG
Tenant Habitability Plan Cleared 6/9/2020 MICHAEL SOTO

Contact Information

Contractor Owner-Builder       ,
Engineer Vega,, Cayetano Gonzalez; Lic. No.: C43117 9234 STAMPS AVE      DOWNEY, CA 90240

Inspector Information

JEREMY TODD, (213) 978-4495 Office Hours: 7:00-8:00 AM MON-FRI
MARVIN FONSECA, (213) 978-4495 Office Hours: 7:00-8:00 AM MON-FRI
DANIEL GUEVARA, (213) 978-4495 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

BUILDING-Rough-Frame 7/15/2020 Not Ready for Inspection MARIO CUEVAS
Green Building Rough 7/15/2020 Not Ready for Inspection MARIO CUEVAS
Pre-Inspection 7/15/2020 Approved MARIO CUEVAS
Footing/Foundation/Slab 7/20/2020 Approved HECTOR RODRIGUEZ
ELECTRICAL-Rough 10/9/2020 Not Ready for Inspection MARIO CUEVAS
Floor/Roof Diaphrgm/Shear Wall 10/9/2020 Corrections Issued MARIO CUEVAS
PLUMBING-Rough 10/9/2020 Corrections Issued MARIO CUEVAS
BUILDING-Rough-Frame 1/27/2021 Corrections Issued MEL KHACHATOURIAN
Drywall Nailing 1/27/2021 Not Ready for Inspection MEL KHACHATOURIAN
Final 1/27/2021 Not Ready for Inspection MEL KHACHATOURIAN
Green Building Final 1/27/2021 Not Ready for Inspection MEL KHACHATOURIAN
Green Building Rough 1/27/2021 Corrections Issued MEL KHACHATOURIAN
SGSOV-Seismic Gas S/O Valve 1/27/2021 SGSOV Not Ready MEL KHACHATOURIAN
Smoke Detectors 1/27/2021 Not Ready for Inspection MEL KHACHATOURIAN
BUILDING-Rough-Frame 2/16/2021 Approved MARIO CUEVAS
Drywall Nailing 2/16/2021 Not Ready for Inspection MARIO CUEVAS
ELECTRICAL-Rough 2/16/2021 Corrections Issued MARIO CUEVAS
Floor/Roof Diaphrgm/Shear Wall 2/16/2021 Approved MARIO CUEVAS
Green Building Rough 2/16/2021 Approved MARIO CUEVAS
PLUMBING-Rough 2/16/2021 Corrections Issued MARIO CUEVAS
SGSOV-Seismic Gas S/O Valve 2/16/2021 SGSOV Not Ready MARIO CUEVAS
Smoke Detectors 2/16/2021 Not Ready for Inspection MARIO CUEVAS
Rough-Elec/Plmb/HVAC 2/23/2021 Corrections Issued MARIO CUEVAS
Insulation 3/5/2021 Approved MARIO CUEVAS
Rough-Elec/Plmb/HVAC 3/5/2021 Approved MARIO CUEVAS
Drywall Nailing 3/26/2021 Approved MARIO CUEVAS
Interior/Exterior Lathing 3/26/2021 Approved MARIO CUEVAS
Final 4/14/2021 Conditional Approval MARIO CUEVAS
Green Building Final 4/14/2021 Approved MARIO CUEVAS
SGSOV-Seismic Gas S/O Valve 4/14/2021 SGSOV Approved MARIO CUEVAS
Smoke Detectors 4/14/2021 Approved MARIO CUEVAS