5800 W SUNSET BLVD 90028

Certificate Information: 5800 W SUNSET BLVD 90028

Application / Permit
20014-10000-01698
Plan Check / Job No.
B20LA07277
Group
Building
Type
Bldg-Addition
Sub-Type
Commercial
Primary Use
(13) Office
Work Description
PROPOSED ENTRY CANOPY (7'-7 1/2" X 17'-3 1/2"), RAMP, AND HANDRAILS/GUARDRAILS IN ENTRANCE OF BUILDING.
Permit Issued
Issued on 3/11/2021
Issuing Office
Current Status
Issued on 3/11/2021
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 4/24/2020 APPLICANT
Assigned to Plan Check Engineer 5/14/2020 MICHAEL LOPEZ
Building Plans Picked Up 5/20/2020 APPLICANT
Green Plans Picked Up 5/20/2020 APPLICANT
Corrections Issued 5/21/2020 MICHAEL LOPEZ
Quality Review Completed 6/2/2020 QUAN NGHIEM
Plan Check Approved 10/8/2020 MICHAEL LOPEZ
Issued 3/11/2021 APPLICANT

Permit Application Clearance Information

Green Code Cleared 5/13/2020 VIVIAN LAO
CPC Cleared 6/18/2020 KENTON TRINH
CPC Cleared 6/18/2020 KENTON TRINH
CPC Cleared 6/18/2020 KENTON TRINH
CPC Cleared 6/18/2020 KENTON TRINH
ZA Case Cleared 6/18/2020 KENTON TRINH
Roof/Waste drainage to street Cleared 6/24/2020 JUAN ASHTON
Eng Process Fee Ord 176,300 Cleared 6/26/2020 RENZ SORIANO
City Hist. Cultural Monument Cleared 7/6/2020 LAMBERT GIESSINGER
Historic monument Cleared 7/6/2020 LAMBERT GIESSINGER
Redevelopment Project Area Cleared 7/14/2020 DAVID URITA
Low Impact Development Cleared 7/16/2020 ORVAL HERNANDEZ-MARCI
DAS Clearance Cleared 9/15/2020 EDDIE GARIN

Contact Information

Architect Kamus,, John Howard; Lic. No.: C20397 5364 EVENING SKY DRIVE      SIMI VALLEY, CA 93063
Contractor Nelson E D Construction; Lic. No.: 701259-B 22115 PLACERITOS BOULEVARD      SANTA CLARITA, CA 91321
Engineer Castillo,, Margarito; Lic. No.: S4808 1205 PINE AVENUE      LONG BEACH, CA 90813

Inspector Information

TIMOTHY POWELL, (213) 482-0360 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 3/15/2021 Approved EDWIN GREGORYONA
Green Building Rough 3/23/2021 Approved EDWIN GREGORYONA
Wood Frame 3/23/2021 Approved EDWIN GREGORYONA
Interior/Exterior Lathing 4/12/2021 Approved EDWIN GREGORYONA
Final 7/14/2021 Conditional Approval JONATHAN QUACH
Green Building Final 7/14/2021 Approved JONATHAN QUACH
SGSOV-Seismic Gas S/O Valve 7/14/2021 SGSOV Approved JONATHAN QUACH
Smoke Detectors 7/14/2021 Approved JONATHAN QUACH