10949 N HAYVENHURST AVE 91344

Certificate Information: 10949 N HAYVENHURST AVE 91344

Application / Permit
20014-10000-01685
Plan Check / Job No.
B20LA07257
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ADDITION TO EXISTING 1 STORY SINGLE FAMILY DWELLING AND INTERIOR REMODEL PER ENGINEER DESIGN
Permit Issued
Issued on 1/27/2021
Issuing Office
Current Status
CofO Issued on 1/6/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/18/2020 APPLICANT
Assigned to Plan Check Engineer 6/11/2020 AUNG SOE
Corrections Issued 6/17/2020 AUNG SOE
Quality Review Completed 7/1/2020 QUAN NGHIEM
Building Plans Picked Up 7/13/2020 APPLICANT
Applicant returned to address corrections 11/19/2020 AUNG SOE
Applicant returned to address corrections 12/9/2020 AUNG SOE
Plan Check Approved 12/16/2020 AUNG SOE
Issued 1/27/2021 APPLICANT
CofO in Progress 12/1/2021 MARK JOHNSON
Permit Finaled 1/6/2022 MICHAEL SMITH
CofO Issued 1/6/2022 MICHAEL SMITH
Permit Finaled 1/6/2022 MICHAEL SMITH

Permit Application Clearance Information

Sewer availability Cleared 8/26/2020 GABRIEL ROBLES
Eng Process Fee Ord 176,300 Cleared 8/27/2020 GABRIEL ROBLES
Hydrant and Access approval Cleared 9/10/2020 MATTHEW CRAIG
Low Impact Development Cleared 10/22/2020 ORVAL HERNANDEZ-MARCI
Roof/Waste drainage to street Cleared 11/30/2020 JOHN TRIANTAFYLLOS
Green Code Cleared 12/2/2020 AUNG SOE

Contact Information

Contractor Owner-Builder       ,
Engineer Espino,, Manuel A; Lic. No.: C55526 12109 WOODRUFF AVE      DOWNEY, CA 90241

Inspector Information

CHRISTOPHER ROJAS, (818) 374-1160 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 2/25/2021 Corrections Issued MARK JOHNSON
BUILDING-Rough-Frame 3/5/2021 Partial Approval MARK JOHNSON
Footing/Foundation/Slab 3/5/2021 Approved MARK JOHNSON
Green Building Rough 3/5/2021 Not Ready for Inspection MARK JOHNSON
Insulation 3/5/2021 Partial Approval MARK JOHNSON
Floor/Roof Diaphrgm/Shear Wall 3/12/2021 Corrections Issued MARK JOHNSON
Floor/Roof Diaphrgm/Shear Wall 4/1/2021 Approved MARK JOHNSON
PLUMBING-Rough 4/5/2021 Approved MARK JOHNSON
Floor/Roof Diaphrgm/Shear Wall 4/16/2021 Partial Approval MARK JOHNSON
Interior/Exterior Lathing 5/4/2021 Approved MARK JOHNSON
ELECTRICAL-Rough 6/7/2021 Approved MARK JOHNSON
Drywall Nailing 6/18/2021 Not Ready for Inspection JUSTIN HAWLEY
Green Building Rough 6/18/2021 Approved JUSTIN HAWLEY
Insulation 6/18/2021 Approved JUSTIN HAWLEY
Drywall Nailing 6/21/2021 Not Ready for Inspection JUSTIN HAWLEY
Drywall Nailing 6/29/2021 Approved MORRIS JACKSON
SGSOV-Seismic Gas S/O Valve 10/26/2021 SGSOV Not Ready MARK JOHNSON
BUILDING-Rough-Frame 11/4/2021 Approved MARK JOHNSON
Final 11/4/2021 Corrections Issued MARK JOHNSON
Green Building Final 11/4/2021 Approved MARK JOHNSON
SGSOV-Seismic Gas S/O Valve 11/4/2021 SGSOV Approved MARK JOHNSON
Smoke Detectors 11/4/2021 Approved MARK JOHNSON
Final 11/18/2021 Corrections Issued CHRISTOPHER DELLEFIELD
Final 11/30/2021 OK to Issue CofO MARK JOHNSON