1549 S RIDGELEY DR 90019

Certificate Information: 1549 S RIDGELEY DR 90019

Application / Permit
20014-10000-01641
Plan Check / Job No.
B20LA07013
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
PARTIAL DEMOLITION AND RENOVATION OF THE EXISTING RESIDENCE. ADDING NEW 310 S.F. TO THE EXISTING FIRST FLOOR. ADDING A NEW 1046 S.F. SECOND FLOOR. 1 OF 2
Permit Issued
Issued on 9/21/2020
Issuing Office
Current Status
CofO Issued on 4/6/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/23/2020 APPLICANT
Assigned to Plan Check Engineer 5/14/2020 JESSE ARELLANO
Corrections Issued 5/21/2020 JESSE ARELLANO
Quality Review Completed 5/28/2020 BILL STUTSMAN
Building Plans Picked Up 6/1/2020 APPLICANT
Applicant returned to address corrections 7/24/2020 JESSE ARELLANO
Applicant returned to address corrections 7/28/2020 JESSE ARELLANO
Green Plans Picked Up 8/5/2020 APPLICANT
Plan Check Approved 8/23/2020 JESSE ARELLANO
Issued 9/21/2020 APPLICANT
CofO in Progress 3/11/2022 JOSE AVILA
Permit Finaled 4/6/2022 RONALD MYRICK
CofO Issued 4/6/2022 RONALD MYRICK
Permit Finaled 4/6/2022 RONALD MYRICK

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 6/16/2020 RENZ SORIANO
Sewer availability Cleared 6/16/2020 RENZ SORIANO
Green Code Cleared 7/20/2020 DONALD CRICHLOW
Hydrant and Access approval Cleared 7/20/2020 KURT CORRAL
Low Impact Development Cleared 7/21/2020 MARTIN FRAGOSO
Roof/Waste drainage to street Cleared 7/21/2020 RENZ SORIANO

Contact Information

Contractor J M E Construction; Lic. No.: 921816-B 1450 RONAN AVENUE      WILMINGTON, CA 90744
Engineer Espino,, Manuel A; Lic. No.: C55526 12109 WOODRUFF AVE      DOWNEY, CA 90241

Inspector Information

DAVID WILLIAMS, (213) 202-3126 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 10/30/2020 Approved DAVID CHAN
Footing/Foundation/Slab 10/30/2020 Approved DAVID CHAN
METHANE-Barrier 10/30/2020 Approved DAVID CHAN
METHANE-Subgrade 10/30/2020 Approved DAVID CHAN
Floor/Roof Diaphrgm/Shear Wall 11/16/2020 Partial Approval DAVID CHAN
PLUMBING-Rough 11/16/2020 Partial Approval DAVID CHAN
Floor/Roof Diaphrgm/Shear Wall 12/14/2020 Partial Approval DAVID CHAN
Insulation 12/14/2020 Partial Approval DAVID CHAN
Floor/Roof Diaphrgm/Shear Wall 1/21/2021 Corrections Issued JOSEPH MCGARRY
Floor/Roof Diaphrgm/Shear Wall 2/18/2021 Not Ready for Inspection KATHRYN BUTTERWORTH
BUILDING-Rough-Frame 5/12/2021 Corrections Issued STUART CHAPMAN
ELECTRICAL-Rough 5/12/2021 Approved STUART CHAPMAN
Green Building Rough 5/12/2021 Not Ready for Inspection STUART CHAPMAN
HVAC-Rough 5/12/2021 Approved STUART CHAPMAN
METHANE-Rough 5/12/2021 Approved STUART CHAPMAN
PLUMBING-Rough 5/12/2021 Approved STUART CHAPMAN
BUILDING-Rough-Frame 6/8/2021 Approved STUART CHAPMAN
Deputy Wood Construction 6/9/2021 No Access for Inspection ELMER BLAND
Insulation 6/16/2021 Corrections Issued SCOTT FINNILA
Interior/Exterior Lathing 6/16/2021 Corrections Issued SCOTT FINNILA
Green Building Rough 6/22/2021 Conditional Approval CHRIS CHRISTENSEN
Insulation 6/22/2021 Conditional Approval CHRIS CHRISTENSEN
Interior/Exterior Lathing 6/23/2021 Partial Approval BENEVA JACKSON
Shower Pan 6/23/2021 Approved BENEVA JACKSON
Drywall Nailing 7/9/2021 Approved STUART CHAPMAN
Green Building Rough 7/9/2021 Approved STUART CHAPMAN
Interior/Exterior Lathing 7/9/2021 Approved STUART CHAPMAN
Green Building Final 1/20/2022 Approved JOSE AVILA
PLUMBING-Rough 1/20/2022 Corrections Issued JOSE AVILA
SGSOV-Seismic Gas S/O Valve 1/20/2022 SGSOV Not Ready JOSE AVILA
Smoke Detectors 1/20/2022 Approved JOSE AVILA
Final 2/1/2022 Corrections Issued JOSE AVILA
SGSOV-Seismic Gas S/O Valve 2/1/2022 SGSOV Not Ready JOSE AVILA
Final 2/9/2022 Corrections Issued JOSE AVILA
SGSOV-Seismic Gas S/O Valve 2/9/2022 SGSOV Approved JOSE AVILA
Final 3/10/2022 OK to Issue CofO JOSE AVILA
Service/Power Release 3/31/2022 Approved JOSE AVILA