4127 S MARCASEL AVE 90066
Certificate Information: 4127 S MARCASEL AVE 90066
- Application / Permit
- 20014-10000-01615
- Plan Check / Job No.
- B20LA06898
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ADDITION TO EXISTING SFD AND CONVERT EXISTING ATTACHED GARAGE TO HABITABLE SPACE
- Permit Issued
- Issued on 11/18/2020
- Issuing Office
- Current Status
- CofO Issued on 11/9/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/15/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 4/30/2020 | STARR CHEN |
| Corrections Issued | 5/25/2020 | STARR CHEN |
| Quality Review Completed | 5/28/2020 | LAWRENCE QUIRANTE |
| Building Plans Picked Up | 6/8/2020 | APPLICANT |
| Green Plans Picked Up | 9/10/2020 | APPLICANT |
| Applicant returned to address corrections | 10/14/2020 | STARR CHEN |
| Plan Check Approved | 11/18/2020 | STARR CHEN |
| Issued | 11/18/2020 | APPLICANT |
| CofO in Progress | 11/2/2021 | ENRIQUE MIRELES |
| Permit Finaled | 11/9/2021 | DANIEL ORRANTE |
| CofO Issued | 11/9/2021 | DANIEL ORRANTE |
| Permit Finaled | 11/9/2021 | DANIEL ORRANTE |
Permit Application Clearance Information
| Sewer availability | Cleared | 7/2/2020 | DINAH GARIN |
| Eng Process Fee Ord 176,300 | Cleared | 7/7/2020 | DINAH GARIN |
| Low Impact Development | Cleared | 8/6/2020 | ANDRES COVARRUBIAS |
| Roof/Waste drainage to street | Cleared | 8/14/2020 | DINAH GARIN |
| Construction near power lines | Cleared | 8/17/2020 | RIDWAN HARDY |
| Construction within easement | Cleared | 8/17/2020 | RIDWAN HARDY |
| Specific Plan | Cleared | 8/17/2020 | FREDDY GARCIA |
| Green Code | Cleared | 9/9/2020 | STARR CHEN |
| Hydrant and Access approval | Cleared | 9/15/2020 | KURT CORRAL |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Ilasin,, John Lacebal; Lic. No.: C67469 | 1011 OARFISH LN OXNARD, CA 93035 |
Inspector Information
| DAKOTA LOW, (310) 914-3895 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 1/20/2021 | Corrections Issued | ENRIQUE MIRELES |
| PLUMBING-Rough | 1/22/2021 | Corrections Issued | ENRIQUE MIRELES |
| PLUMBING-Rough | 1/26/2021 | Partial Approval | ENRIQUE MIRELES |
| Footing/Foundation/Slab | 1/28/2021 | Corrections Issued | ENRIQUE MIRELES |
| Footing/Foundation/Slab | 2/2/2021 | Approved | ENRIQUE MIRELES |
| Wood Frame | 3/25/2021 | Approved | ENRIQUE MIRELES |
| Interior/Exterior Lathing | 4/7/2021 | Approved | ENRIQUE MIRELES |
| Rough-Elec/Plmb/HVAC | 4/13/2021 | Approved | ENRIQUE MIRELES |
| Insulation | 4/20/2021 | Approved | ENRIQUE MIRELES |
| Drywall Nailing | 4/23/2021 | Approved | ENRIQUE MIRELES |
| Interior/Exterior Lathing | 5/7/2021 | Approved | ENRIQUE MIRELES |
| BUILDING-Rough-Frame | 10/13/2021 | Approved | ENRIQUE MIRELES |
| Final | 10/13/2021 | Corrections Issued | ENRIQUE MIRELES |
| Gas Test | 10/13/2021 | Approved | ENRIQUE MIRELES |
| Green Building Final | 10/13/2021 | Approved | ENRIQUE MIRELES |
| Green Building Rough | 10/13/2021 | Approved | ENRIQUE MIRELES |
| SGSOV-Seismic Gas S/O Valve | 10/13/2021 | SGSOV Approved | ENRIQUE MIRELES |
| Smoke Detectors | 10/13/2021 | Approved | ENRIQUE MIRELES |
| Final | 11/2/2021 | OK to Issue CofO | ENRIQUE MIRELES |