3854 N AVENIDA DEL SOL 91604

Certificate Information: 3854 N AVENIDA DEL SOL 91604

Application / Permit
20014-10000-01612
Plan Check / Job No.
B20LA06896
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
New gorund floor addition with rooftop deck at rear of (E) 1-story SFD.(see comments)
Permit Issued
Issued on 5/6/2022
Issuing Office
Current Status
CofO Issued on 12/19/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/23/2020 APPLICANT
Assigned to Plan Check Engineer 4/30/2020 SAMUEL GONZALEZ
Corrections Issued 5/7/2020 SAMUEL GONZALEZ
Quality Review Completed 5/12/2020 LAWRENCE QUIRANTE
Green Plans Picked Up 5/14/2020 APPLICANT
Plan Check Approved 5/6/2022 SAMUEL GONZALEZ
Issued 5/6/2022 APPLICANT
Building Plans Picked Up 5/9/2022 APPLICANT
CofO in Progress 12/2/2022 CHRISTOPHE COCHRAN
CofO in Progress 12/2/2022 CHRISTOPHE COCHRAN
Permit Finaled 12/19/2022 MICHAEL SMITH
CofO Issued 12/19/2022 MICHAEL SMITH
Permit Finaled 12/19/2022 MICHAEL SMITH

Permit Application Clearance Information

BHO/Hillside ordinance Cleared 5/27/2020 LEE GUILBEAUX
BHO/Hillside ordinance Cleared 6/22/2020 LEE GUILBEAUX
Address approval Cleared 7/30/2020 GABRIEL ROBLES
Eng Process Fee Ord 176,300 Cleared 10/8/2020 GABRIEL ROBLES
BHO/Hillside ordinance Cleared 11/24/2021 CARLOS AGUILERA
Low Impact Development Cleared 1/19/2022 ANDRES COVARRUBIAS
Roof/Waste drainage to street Cleared 1/20/2022 ABDULLAH SADOZAI
Hydrant and Access approval Cleared 3/14/2022 DWIGHT SANKEY
Miscellaneous Cleared 3/21/2022 MIGUEL GAMBOA
ZA Case Cleared 3/21/2022 MIGUEL GAMBOA
Grading Pre-Inspection Cleared 3/30/2022 SAMUEL GONZALEZ
Green Code Cleared 3/30/2022 VIVIAN LAO
BHO/Hillside ordinance Cleared 4/8/2022 LEE GUILBEAUX
BHO/Hillside ordinance Cleared 4/8/2022 LEE GUILBEAUX
Sewer availability Cleared 4/8/2022 LEE GUILBEAUX

Contact Information

Architect Ko,, Michael Myungsoo; Lic. No.: C22356 3435 WILSHIRE BLVD #2905      LOS ANGELES, CA 90010
Contractor Owner-Builder       ,

Inspector Information

CHRISTOPHE COCHRAN, (818) 374-1165 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 6/22/2022 Approved CHRISTOPHE COCHRAN
Footing/Foundation/Slab 6/29/2022 Partial Approval CHRISTOPHE COCHRAN
Excavation/Setback/Form/Re-Bar 7/7/2022 Not Ready for Inspection CHRISTOPHE COCHRAN
Footing/Foundation/Slab 7/7/2022 Corrections Issued CHRISTOPHE COCHRAN
Footing/Foundation/Slab 7/8/2022 Partial Approval JOHN KIDWELL
Deputy Drilled-In Anchors 7/20/2022 Conditional Approval CHRISTOPHE COCHRAN
Deputy Drilled-In Anchors 7/21/2022 Conditional Approval CHRISTOPHE COCHRAN
Footing/Foundation/Slab 7/25/2022 Approved CHRISTOPHE COCHRAN
Masonry Wall/Backfill 7/25/2022 Partial Approval CHRISTOPHE COCHRAN
Deputy Reinf. Masonry 7/29/2022 Conditional Approval DAVID MATSON
Deputy Drilled-In Anchors 8/2/2022 Conditional Approval MATT KELLERMAN
Masonry Wall/Backfill 8/4/2022 Partial Approval CHRISTOPHE COCHRAN
Masonry Wall/Backfill 8/8/2022 Approved CHRISTOPHE COCHRAN
Deputy Reinf. Masonry 8/9/2022 Conditional Approval CHRISTOPHE COCHRAN
Floor/Roof Diaphrgm/Shear Wall 8/24/2022 Partial Approval CHRISTOPHE COCHRAN
Floor/Roof Diaphrgm/Shear Wall 8/25/2022 Partial Approval CHRISTOPHE COCHRAN
Deputy Drilled-In Anchors 8/30/2022 Conditional Approval CHRISTOPHE COCHRAN
BUILDING-Rough-Frame 8/31/2022 Approved CHRISTOPHE COCHRAN
ELECTRICAL-Rough 8/31/2022 Approved CHRISTOPHE COCHRAN
Green Building Rough 8/31/2022 Approved CHRISTOPHE COCHRAN
PLUMBING-Rough 8/31/2022 Corrections Issued CHRISTOPHE COCHRAN
PLUMBING-Rough 9/9/2022 Partial Approval JOHN HAYES
Deck 9/26/2022 Approved CALEB MEISTER
HVAC-Rough 10/3/2022 Approved CHRISTOPHE COCHRAN
Insulation 10/3/2022 Approved CHRISTOPHE COCHRAN
Shower Pan 10/3/2022 Approved CHRISTOPHE COCHRAN
Drywall Nailing 10/13/2022 Approved CHRISTOPHE COCHRAN
Interior/Exterior Lathing 10/13/2022 Approved CHRISTOPHE COCHRAN
Final 11/28/2022 Corrections Issued CHRISTOPHE COCHRAN
Green Building Final 11/28/2022 Approved CHRISTOPHE COCHRAN
SGSOV-Seismic Gas S/O Valve 11/28/2022 SGSOV Approved CHRISTOPHE COCHRAN
Smoke Detectors 11/28/2022 Approved CHRISTOPHE COCHRAN
Final 12/1/2022 OK to Issue CofO CHRISTOPHE COCHRAN