1461 W 80TH ST 90047

Certificate Information: 1461 W 80TH ST 90047

Application / Permit
20014-10000-01570
Plan Check / Job No.
B20LA06714
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
One story addition to exisitng one story duplex and complete remodel.. New kitchens and bathrooms, replace all windows.
Permit Issued
Issued on 8/6/2020
Issuing Office
Current Status
CofO Issued on 7/3/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/10/2020 APPLICANT
Assigned to Plan Check Engineer 7/16/2020 RICARDO RAMIREZ
Corrections Issued 7/16/2020 RICARDO RAMIREZ
Issued 8/6/2020 APPLICANT
Building Plans Picked Up 8/7/2020 APPLICANT
CofO in Progress 5/26/2021 DAVID FEILER
Permit Finaled 7/3/2021 DEROLD HAUFF
CofO Issued 7/3/2021 DEROLD HAUFF
Permit Finaled 7/3/2021 DEROLD HAUFF

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 5/19/2020 EMIL KYUPELYAN
Sewer availability Cleared 5/19/2020 EMIL KYUPELYAN
Community Plan Implem. Overlay Cleared 6/1/2020 TERRI OSBORNE
ZI Cleared 6/1/2020 TERRI OSBORNE
Low Impact Development Cleared 6/30/2020 ROBIN YAMADA
Roof/Waste drainage to street Cleared 6/30/2020 EMIL KYUPELYAN

Contact Information

Contractor K N Consulting Inc; Lic. No.: 993102-B P O BOX 410      SUNSET BEACH, CA 90742
Engineer Madero,, Fidencio; Lic. No.: C81695 10002 PANGBORN AVE      DOWNEY, CA 90240

Inspector Information

JOHN QUINTANILLA, (213) 792-6055 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 10/7/2020 Approved ALEJANDRO DE ARTOLA
Insulation 10/22/2020 Corrections Issued ALEJANDRO DE ARTOLA
Underground Mechanical 10/22/2020 Approved ALEJANDRO DE ARTOLA
Wood Frame 10/22/2020 Partial Approval ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 10/28/2020 Corrections Issued ALEJANDRO DE ARTOLA
Insulation 10/28/2020 Partial Approval ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 10/29/2020 Partial Approval ALEJANDRO DE ARTOLA
Verify Rec and Parks Fee Memo 11/6/2020 Approved ALEJANDRO DE ARTOLA
BUILDING-Rough-Frame 12/4/2020 Corrections Issued ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 12/4/2020 Partial Approval ALEJANDRO DE ARTOLA
BUILDING-Rough-Frame 1/5/2021 Partial Approval JOSEPH MCGARRY
ELECTRICAL-Rough 1/5/2021 Approved JOSEPH MCGARRY
Floor/Roof Diaphrgm/Shear Wall 1/5/2021 Approved JOSEPH MCGARRY
Green Building Rough 1/5/2021 Not Ready for Inspection JOSEPH MCGARRY
HVAC-Rough 1/5/2021 Approved JOSEPH MCGARRY
PLUMBING-Rough 1/5/2021 Approved JOSEPH MCGARRY
Insulation 1/8/2021 Approved ALEJANDRO DE ARTOLA
Drywall Nailing 1/15/2021 Approved DAVID FEILER
Green Building Rough 1/15/2021 Approved DAVID FEILER
Interior/Exterior Lathing 1/15/2021 Approved DAVID FEILER
BUILDING-Rough-Frame 4/8/2021 Approved RUBEN SALAS
ELECTRICAL-Final 4/8/2021 Approved RUBEN SALAS
Final 4/8/2021 Corrections Issued RUBEN SALAS
Green Building Final 4/8/2021 Approved RUBEN SALAS
HVAC-Final 4/8/2021 Approved RUBEN SALAS
PLUMBING-Final 4/8/2021 Approved RUBEN SALAS
SGSOV-Seismic Gas S/O Valve 4/8/2021 SGSOV Approved RUBEN SALAS
Smoke Detectors 4/8/2021 Approved RUBEN SALAS
Final 4/29/2021 Corrections Issued EUGENE CASSIDY
Service/Power Release 4/29/2021 Not Ready for Inspection EUGENE CASSIDY
Final 5/26/2021 OK to Issue CofO DAVID FEILER
Service/Power Release 5/29/2021 Approved DAVID FEILER