6214 E STRICKLAND AVE 90042
Certificate Information: 6214 E STRICKLAND AVE 90042
- Application / Permit
- 20014-10000-01527
- Plan Check / Job No.
- B20LA06537
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- PROPOSED 1 STORY ADDITION (25'0" X 19'6") TO THE REAR OF AN EXISTING SINGLE FAMILY DWELLING TO CREATE 1 NEW BEDROOM, RELOCATE EXISTING KITCHEN, AND 1 NEW BATHROOM. SCOPE WILL ALSO INCLUDE AN (7'3" X 25'0") UNCOVERED DECK AT THE REAR. ALL WORK TO BE DONE PER ENGINEER OF RECORD. ***SPRINKLERS REQUIRED PER NFPA 13D***
- Permit Issued
- Issued on 10/13/2022
- Issuing Office
- Metro
- Current Status
- CofO Issued on 6/4/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/9/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 4/23/2020 | MICHAEL LOPEZ |
| Corrections Issued | 4/30/2020 | MICHAEL LOPEZ |
| Quality Review Completed | 5/12/2020 | QUAN NGHIEM |
| Building Plans Picked Up | 5/15/2020 | APPLICANT |
| Green Plans Picked Up | 6/16/2020 | APPLICANT |
| Applicant returned to address corrections | 10/14/2021 | MICHAEL LOPEZ |
| Applicant returned to address corrections | 4/20/2022 | MICHAEL LOPEZ |
| Plan Check Approved | 6/3/2022 | MICHAEL LOPEZ |
| Issued | 10/13/2022 | APPLICANT |
| CofO in Progress | 6/1/2024 | ALIZAH MAYAGOITIA |
| Permit Finaled | 6/4/2024 | DEROLD HAUFF |
| CofO Issued | 6/4/2024 | DEROLD HAUFF |
| Permit Finaled | 6/4/2024 | DEROLD HAUFF |
Permit Application Clearance Information
| Green Code | Cleared | 6/15/2020 | KHEDER ALRAZAA |
| BHO/Hillside ordinance | Cleared | 7/17/2020 | CECILIO NAVARRO |
| BHO/Hillside ordinance | Cleared | 7/17/2020 | CECILIO NAVARRO |
| BHO/Hillside ordinance | Cleared | 7/17/2020 | CECILIO NAVARRO |
| Eng Process Fee Ord 176,300 | Cleared | 7/26/2020 | CECILIO NAVARRO |
| Low Impact Development | Cleared | 5/19/2021 | JORGE MEJIA LEMUS |
| Roof/Waste drainage to street | Cleared | 8/10/2021 | WALLIE JONG |
| Grading Pre-Inspection | Cleared | 10/14/2021 | ROBERT HUGHES |
| Hydrant and Access approval | Cleared | 2/11/2022 | JOHN CONNEALLY |
Contact Information
| Contractor | Refinish Plus Inc; Lic. No.: 1050293-B | 8133 PURITAN ST DOWNEY, CA 90242 |
| Engineer | Cooke,, Conway Cecil; Lic. No.: S5524 | 34658 LINDA ROSEA RD TEMECULA, CA 92592 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 12/12/2022 | Conditional Approval | HAMIK HARTOUNIAN |
| Excavation/Setback/Form/Re-Bar | 12/15/2022 | Partial Approval | AMY COLIN |
| Footing/Foundation/Slab | 12/15/2022 | Corrections Issued | AMY COLIN |
| Deputy Drilled-In Anchors | 3/9/2023 | Conditional Approval | AMY COLIN |
| Floor/Roof Diaphrgm/Shear Wall | 4/6/2023 | Partial Approval | AMY COLIN |
| Wood Frame | 4/6/2023 | Partial Approval | AMY COLIN |
| Floor/Roof Diaphrgm/Shear Wall | 5/16/2023 | Partial Approval | AMY COLIN |
| ELECTRICAL-Rough | 7/31/2023 | Not Ready for Inspection | AMY COLIN |
| Floor/Roof Diaphrgm/Shear Wall | 7/31/2023 | Partial Approval | AMY COLIN |
| Footing/Foundation/Slab | 7/31/2023 | Approved | AMY COLIN |
| PLUMBING-Rough | 7/31/2023 | Corrections Issued | AMY COLIN |
| Underground Mechanical | 7/31/2023 | Approved | AMY COLIN |
| Wood Frame | 7/31/2023 | Partial Approval | AMY COLIN |
| ELECTRICAL-Rough | 8/24/2023 | Corrections Issued | AMY COLIN |
| HVAC-Rough | 8/24/2023 | Partial Approval | AMY COLIN |
| Interior/Exterior Lathing | 8/24/2023 | Partial Approval | AMY COLIN |
| Insulation | 9/11/2023 | Approved | AMY COLIN |
| Deck | 9/25/2023 | Approved | AMY COLIN |
| Drywall Nailing | 9/25/2023 | Approved | AMY COLIN |
| Interior/Exterior Lathing | 9/25/2023 | Approved | AMY COLIN |
| Shower Pan | 9/25/2023 | Approved | AMY COLIN |
| BUILDING-Rough-Frame | 3/8/2024 | Approved | ALIZAH MAYAGOITIA |
| ELECTRICAL-Final | 3/8/2024 | Approved | ALIZAH MAYAGOITIA |
| Final | 3/8/2024 | Corrections Issued | ALIZAH MAYAGOITIA |
| Green Building Final | 3/8/2024 | Approved | ALIZAH MAYAGOITIA |
| Green Building Rough | 3/8/2024 | Approved | ALIZAH MAYAGOITIA |
| HVAC-Final | 3/8/2024 | Approved | ALIZAH MAYAGOITIA |
| PLUMBING-Final | 3/8/2024 | Approved | ALIZAH MAYAGOITIA |
| SGSOV-Seismic Gas S/O Valve | 3/8/2024 | SGSOV Approved | ALIZAH MAYAGOITIA |
| Smoke Detectors | 3/8/2024 | Corrections Issued | ALIZAH MAYAGOITIA |
| Verify Sprinkler Sign Off | 3/8/2024 | Approved | ALIZAH MAYAGOITIA |
| Final | 5/31/2024 | OK to Issue CofO | ALIZAH MAYAGOITIA |
| Smoke Detectors | 5/31/2024 | Approved | ALIZAH MAYAGOITIA |