6707 S 3RD AVE 90043

Certificate Information: 6707 S 3RD AVE 90043

Application / Permit
20014-10000-01517
Plan Check / Job No.
B20LA06505
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Bathroom addition to existing single family dwelling per wfpp
Permit Issued
Issued on 9/9/2020
Issuing Office
Current Status
Issued on 9/9/2020
Certificate of Occupancy
Pending More Information

Permit Application Status History

Plan Check Approved 6/16/2020 FERNANDO FLORES
Issued 9/9/2020 APPLICANT
Building Plans Picked Up 9/14/2020 APPLICANT

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 6/2/2020 JEANIE LAM
Sewer availability Cleared 6/2/2020 JEANIE LAM
Eng Process Fee Ord 176,300 Cleared 6/8/2020 JEANIE LAM

Contact Information

Contractor Sutton Home Improvement; Lic. No.: 830509-B 914 NORTH DWIGHT AVE      COMPTON, CA 90220

Inspector Information

SALVADOR MARTINEZ, (213) 202-3479 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 10/21/2020 Conditional Approval FREDDIE RIVERA
Pre-Inspection 10/21/2020 Corrections Issued FREDDIE RIVERA
BUILDING-Rough-Frame 11/9/2020 Partial Approval FREDDIE RIVERA
Green Building Rough 11/9/2020 Not Ready for Inspection FREDDIE RIVERA
Floor/Roof Diaphrgm/Shear Wall 11/16/2020 Approved FREDDIE RIVERA
ELECTRICAL-Rough 11/17/2020 Not Ready for Inspection FREDDIE RIVERA
PLUMBING-Rough 11/17/2020 Not Ready for Inspection FREDDIE RIVERA
ELECTRICAL-Rough 11/25/2020 Not Ready for Inspection FREDDIE RIVERA
PLUMBING-Rough 11/25/2020 Conditional Approval FREDDIE RIVERA
BUILDING-Rough-Frame 12/18/2020 Approved FREDDIE RIVERA
ELECTRICAL-Rough 12/18/2020 Approved FREDDIE RIVERA
Green Building Rough 12/18/2020 Approved FREDDIE RIVERA
PLUMBING-Rough 12/18/2020 Approved FREDDIE RIVERA
Drywall Nailing 12/30/2020 Approved KATHRYN BUTTERWORTH
Insulation 12/30/2020 Approved KATHRYN BUTTERWORTH
Interior/Exterior Lathing 1/6/2021 Partial Approval ROBERT VORHIS
Final 5/17/2021 Corrections Issued RICHARD ROBLES
Footing/Foundation/Slab 5/17/2021 Not Ready for Inspection RICHARD ROBLES
Green Building Final 5/17/2021 Approved RICHARD ROBLES
SGSOV-Seismic Gas S/O Valve 5/17/2021 SGSOV Not Ready RICHARD ROBLES
Smoke Detectors 5/17/2021 Corrections Issued RICHARD ROBLES
SGSOV-Seismic Gas S/O Valve 5/24/2021 SGSOV Not Ready FREDDIE RIVERA
SGSOV-Seismic Gas S/O Valve 6/7/2021 SGSOV Not Ready EUGENE CASSIDY
Special/Order Compliance 6/14/2021 Corrections Issued FREDDIE RIVERA
SGSOV-Seismic Gas S/O Valve 7/26/2021 SGSOV Not Ready FREDDIE RIVERA
Pre-Inspection 7/30/2021 Corrections Issued FREDDIE RIVERA
Final 8/31/2021 Corrections Issued FREDDIE RIVERA
Footing/Foundation/Slab 8/31/2021 Not Ready for Inspection FREDDIE RIVERA
SGSOV-Seismic Gas S/O Valve 8/31/2021 SGSOV Approved FREDDIE RIVERA
Smoke Detectors 8/31/2021 Approved FREDDIE RIVERA