5635 E BERKSHIRE DR 90032

Certificate Information: 5635 E BERKSHIRE DR 90032

Application / Permit
20014-10000-01516
Plan Check / Job No.
B20LA06488
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT PORTION OF EXISTING GARAGE PLUS ADDITION INTO ACCESSORY DWELLING UNIT PER CITY ORDIANANCE
Permit Issued
Issued on 8/5/2020
Issuing Office
Current Status
CofO Issued on 9/16/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/20/2020 APPLICANT
Assigned to Plan Check Engineer 4/20/2020 FERNANDO FLORES
Corrections Issued 5/5/2020 FERNANDO FLORES
Applicant returned to address corrections 5/12/2020 FERNANDO FLORES
Applicant returned to address corrections 6/2/2020 SINA KHOSRAVI
Plan Check Approved 7/30/2020 SERGIO GUTIERREZ
Issued 8/5/2020 APPLICANT
Building Plans Picked Up 8/5/2020 APPLICANT
CofO in Progress 8/9/2021 COREY HUPP
CofO in Progress 8/9/2021 COREY HUPP
Permit Finaled 9/16/2021 DEROLD HAUFF
CofO Issued 9/16/2021 DEROLD HAUFF
Permit Finaled 9/16/2021 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 4/20/2020 CECILIO NAVARRO
Eng Process Fee Ord 176,300 Cleared 4/20/2020 CECILIO NAVARRO
Sewer availability Cleared 4/20/2020 CECILIO NAVARRO
Roof/Waste drainage to street Cleared 4/21/2020 CECILIO NAVARRO
Grading Pre-Inspection Cleared 5/4/2020 PATRICK MISCHLICH
HPOZ Cleared 5/18/2020 JONATHAN KAPLAN

Contact Information

Architect Dahl,, Steven Phillip; Lic. No.: C18545 1134 EL CENTRO STREET      SOUTH PASADENA, CA 91030
Contractor Owner-Builder       ,
Engineer Mani,, Dev; Lic. No.: C62778 P O BOX 1451      DUARTE, CA 91009

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 8/10/2020 Approved ENRIQUE MIRELES
Excavation/Setback/Form/Re-Bar 9/2/2020 Not Ready for Inspection ENRIQUE MIRELES
Footing/Foundation/Slab 9/2/2020 Partial Approval ENRIQUE MIRELES
Footing/Foundation/Slab 9/28/2020 Corrections Issued COREY HUPP
PLUMBING-Rough 9/28/2020 Corrections Issued COREY HUPP
Footing/Foundation/Slab 10/5/2020 Approved COREY HUPP
PLUMBING-Rough 10/5/2020 Partial Approval COREY HUPP
Excavation/Setback/Form/Re-Bar 10/8/2020 Partial Inspection RUBEN SALAS
PLUMBING-Rough 10/8/2020 Partial Inspection RUBEN SALAS
Sewer 10/8/2020 Partial Inspection RUBEN SALAS
Green Building Rough 10/23/2020 Not Ready for Inspection HAMIK HARTOUNIAN
Pre-Inspection 10/23/2020 Partial Inspection HAMIK HARTOUNIAN
BUILDING-Rough-Frame 12/1/2020 No Access for Inspection COREY HUPP
Green Building Rough 12/1/2020 No Access for Inspection COREY HUPP
BUILDING-Rough-Frame 12/7/2020 Partial Approval COREY HUPP
ELECTRICAL-Rough 12/8/2020 Partial Inspection COREY HUPP
BUILDING-Rough-Frame 12/24/2020 Not Ready for Inspection COREY HUPP
ELECTRICAL-Rough 12/24/2020 Not Ready for Inspection COREY HUPP
ELECTRICAL-Rough 12/28/2020 Approved RUBEN SALAS
Gas Test 12/28/2020 Partial Approval RUBEN SALAS
PLUMBING-Rough 12/28/2020 Approved RUBEN SALAS
Insulation 1/5/2021 Not Ready for Inspection COREY HUPP
Insulation 1/11/2021 Approved COREY HUPP
Interior/Exterior Lathing 1/11/2021 Partial Approval COREY HUPP
Underground Mechanical 1/14/2021 Approved COREY HUPP
Drywall Nailing 2/1/2021 Approved COREY HUPP
ELECTRICAL-Final 6/2/2021 Corrections Issued CRAIG VAUGHAN
Green Building Final 6/2/2021 Corrections Issued CRAIG VAUGHAN
PLUMBING-Final 6/2/2021 Corrections Issued CRAIG VAUGHAN
Green Building Final 6/21/2021 Approved COREY HUPP
PLUMBING-Final 6/21/2021 Approved COREY HUPP
BUILDING-Rough-Frame 6/25/2021 Approved COREY HUPP
Final 6/25/2021 Partial Inspection COREY HUPP
Green Building Rough 6/25/2021 Approved COREY HUPP
SGSOV-Seismic Gas S/O Valve 6/25/2021 SGSOV Approved COREY HUPP
Smoke Detectors 6/25/2021 Approved COREY HUPP
Final 8/2/2021 OK to Issue CofO COREY HUPP