5635 E BERKSHIRE DR 90032
Certificate Information: 5635 E BERKSHIRE DR 90032
- Application / Permit
- 20014-10000-01516
- Plan Check / Job No.
- B20LA06488
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT PORTION OF EXISTING GARAGE PLUS ADDITION INTO ACCESSORY DWELLING UNIT PER CITY ORDIANANCE
- Permit Issued
- Issued on 8/5/2020
- Issuing Office
- Current Status
- CofO Issued on 9/16/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/20/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 4/20/2020 | FERNANDO FLORES |
| Corrections Issued | 5/5/2020 | FERNANDO FLORES |
| Applicant returned to address corrections | 5/12/2020 | FERNANDO FLORES |
| Applicant returned to address corrections | 6/2/2020 | SINA KHOSRAVI |
| Plan Check Approved | 7/30/2020 | SERGIO GUTIERREZ |
| Issued | 8/5/2020 | APPLICANT |
| Building Plans Picked Up | 8/5/2020 | APPLICANT |
| CofO in Progress | 8/9/2021 | COREY HUPP |
| CofO in Progress | 8/9/2021 | COREY HUPP |
| Permit Finaled | 9/16/2021 | DEROLD HAUFF |
| CofO Issued | 9/16/2021 | DEROLD HAUFF |
| Permit Finaled | 9/16/2021 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 4/20/2020 | CECILIO NAVARRO |
| Eng Process Fee Ord 176,300 | Cleared | 4/20/2020 | CECILIO NAVARRO |
| Sewer availability | Cleared | 4/20/2020 | CECILIO NAVARRO |
| Roof/Waste drainage to street | Cleared | 4/21/2020 | CECILIO NAVARRO |
| Grading Pre-Inspection | Cleared | 5/4/2020 | PATRICK MISCHLICH |
| HPOZ | Cleared | 5/18/2020 | JONATHAN KAPLAN |
Contact Information
| Architect | Dahl,, Steven Phillip; Lic. No.: C18545 | 1134 EL CENTRO STREET SOUTH PASADENA, CA 91030 |
| Contractor | Owner-Builder | , |
| Engineer | Mani,, Dev; Lic. No.: C62778 | P O BOX 1451 DUARTE, CA 91009 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 8/10/2020 | Approved | ENRIQUE MIRELES |
| Excavation/Setback/Form/Re-Bar | 9/2/2020 | Not Ready for Inspection | ENRIQUE MIRELES |
| Footing/Foundation/Slab | 9/2/2020 | Partial Approval | ENRIQUE MIRELES |
| Footing/Foundation/Slab | 9/28/2020 | Corrections Issued | COREY HUPP |
| PLUMBING-Rough | 9/28/2020 | Corrections Issued | COREY HUPP |
| Footing/Foundation/Slab | 10/5/2020 | Approved | COREY HUPP |
| PLUMBING-Rough | 10/5/2020 | Partial Approval | COREY HUPP |
| Excavation/Setback/Form/Re-Bar | 10/8/2020 | Partial Inspection | RUBEN SALAS |
| PLUMBING-Rough | 10/8/2020 | Partial Inspection | RUBEN SALAS |
| Sewer | 10/8/2020 | Partial Inspection | RUBEN SALAS |
| Green Building Rough | 10/23/2020 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Pre-Inspection | 10/23/2020 | Partial Inspection | HAMIK HARTOUNIAN |
| BUILDING-Rough-Frame | 12/1/2020 | No Access for Inspection | COREY HUPP |
| Green Building Rough | 12/1/2020 | No Access for Inspection | COREY HUPP |
| BUILDING-Rough-Frame | 12/7/2020 | Partial Approval | COREY HUPP |
| ELECTRICAL-Rough | 12/8/2020 | Partial Inspection | COREY HUPP |
| BUILDING-Rough-Frame | 12/24/2020 | Not Ready for Inspection | COREY HUPP |
| ELECTRICAL-Rough | 12/24/2020 | Not Ready for Inspection | COREY HUPP |
| ELECTRICAL-Rough | 12/28/2020 | Approved | RUBEN SALAS |
| Gas Test | 12/28/2020 | Partial Approval | RUBEN SALAS |
| PLUMBING-Rough | 12/28/2020 | Approved | RUBEN SALAS |
| Insulation | 1/5/2021 | Not Ready for Inspection | COREY HUPP |
| Insulation | 1/11/2021 | Approved | COREY HUPP |
| Interior/Exterior Lathing | 1/11/2021 | Partial Approval | COREY HUPP |
| Underground Mechanical | 1/14/2021 | Approved | COREY HUPP |
| Drywall Nailing | 2/1/2021 | Approved | COREY HUPP |
| ELECTRICAL-Final | 6/2/2021 | Corrections Issued | CRAIG VAUGHAN |
| Green Building Final | 6/2/2021 | Corrections Issued | CRAIG VAUGHAN |
| PLUMBING-Final | 6/2/2021 | Corrections Issued | CRAIG VAUGHAN |
| Green Building Final | 6/21/2021 | Approved | COREY HUPP |
| PLUMBING-Final | 6/21/2021 | Approved | COREY HUPP |
| BUILDING-Rough-Frame | 6/25/2021 | Approved | COREY HUPP |
| Final | 6/25/2021 | Partial Inspection | COREY HUPP |
| Green Building Rough | 6/25/2021 | Approved | COREY HUPP |
| SGSOV-Seismic Gas S/O Valve | 6/25/2021 | SGSOV Approved | COREY HUPP |
| Smoke Detectors | 6/25/2021 | Approved | COREY HUPP |
| Final | 8/2/2021 | OK to Issue CofO | COREY HUPP |