2940 S 11TH AVE 90018

Certificate Information: 2940 S 11TH AVE 90018

Application / Permit
20014-10000-01505
Plan Check / Job No.
B20LA06450
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ONE STORY REAR ADDITION WITH BEDROOM AND BATHROOM TO SINGLE FAMILY DWELLING.
Permit Issued
Issued on 7/23/2020
Issuing Office
Current Status
CofO Issued on 2/25/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/22/2020 APPLICANT
Assigned to Plan Check Engineer 4/22/2020 GEORGE ALVAREZ
Corrections Issued 4/22/2020 GEORGE ALVAREZ
Plan Check Approved 7/20/2020 RICARDO RAMIREZ
Issued 7/23/2020 APPLICANT
Building Plans Picked Up 7/27/2020 APPLICANT
CofO in Progress 2/2/2021 STUART CHAPMAN
Permit Finaled 2/25/2021 DEROLD HAUFF
CofO Issued 2/25/2021 DEROLD HAUFF
Permit Finaled 2/25/2021 DEROLD HAUFF

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 6/1/2020 JUAN ASHTON
Sewer availability Cleared 6/1/2020 JUAN ASHTON
Eng Process Fee Ord 176,300 Cleared 6/2/2020 JUAN ASHTON

Contact Information

Contractor Valencia Construction Company; Lic. No.: 1015167-B 12069 SMALLWOOD AVE      DOWNEY, CA 90242
Engineer Salto,, Alvaro; Lic. No.: C83859 7366 W MANCHESTER AVE #B      LOS ANGELES, CA 90045

Inspector Information

JUSTIN HAWLEY, (213) 202-3432 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 8/7/2020 Conditional Approval STUART CHAPMAN
Footing/Foundation/Slab 8/26/2020 Approved STUART CHAPMAN
PLUMBING-Rough 8/26/2020 Partial Approval STUART CHAPMAN
Underground Mechanical 8/26/2020 Not Ready for Inspection STUART CHAPMAN
Insulation 9/1/2020 Partial Approval STUART CHAPMAN
BUILDING-Rough-Frame 9/25/2020 Corrections Issued STUART CHAPMAN
ELECTRICAL-Rough 9/25/2020 Approved STUART CHAPMAN
Green Building Rough 9/25/2020 Corrections Issued STUART CHAPMAN
HVAC-Rough 9/25/2020 Not Ready for Inspection STUART CHAPMAN
PLUMBING-Rough 9/25/2020 Approved STUART CHAPMAN
Interior/Exterior Lathing 10/7/2020 Partial Approval STUART CHAPMAN
Floor/Roof Diaphrgm/Shear Wall 10/26/2020 Approved STUART CHAPMAN
Drywall Nailing 10/27/2020 Not Ready for Inspection STUART CHAPMAN
Insulation 10/27/2020 Approved STUART CHAPMAN
Drywall Nailing 11/6/2020 Approved STUART CHAPMAN
Interior/Exterior Lathing 11/6/2020 Partial Approval STUART CHAPMAN
BUILDING-Rough-Frame 1/6/2021 Approved STUART CHAPMAN
Final 1/6/2021 Corrections Issued STUART CHAPMAN
Green Building Final 1/6/2021 Not Ready for Inspection STUART CHAPMAN
Green Building Rough 1/6/2021 Approved STUART CHAPMAN
SGSOV-Seismic Gas S/O Valve 1/6/2021 SGSOV Approved STUART CHAPMAN
Smoke Detectors 1/6/2021 Approved STUART CHAPMAN
ELECTRICAL-Final 2/1/2021 Approved STUART CHAPMAN
Final 2/1/2021 OK to Issue CofO STUART CHAPMAN
Green Building Final 2/1/2021 Approved STUART CHAPMAN
HVAC-Final 2/1/2021 Approved STUART CHAPMAN
PLUMBING-Final 2/1/2021 Approved STUART CHAPMAN
Service/Power Release 2/9/2021 Approved STUART CHAPMAN