3072 N FRANKLIN CANYON DR 90210
Certificate Information: 3072 N FRANKLIN CANYON DR 90210
- Application / Permit
- 20014-10000-01504
- Plan Check / Job No.
- B20LA06449
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ADDITION (N) A.D.U. TO (E) 3-CAR GARAGE
- Permit Issued
- Issued on 12/10/2020
- Issuing Office
- Metro
- Current Status
- CofO Issued on 10/1/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/20/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 5/6/2020 | JESSE ARELLANO |
| Corrections Issued | 5/13/2020 | JESSE ARELLANO |
| Quality Review Completed | 5/18/2020 | BILL STUTSMAN |
| Building Plans Picked Up | 5/21/2020 | APPLICANT |
| Green Plans Picked Up | 9/24/2020 | APPLICANT |
| Applicant returned to address corrections | 11/4/2020 | JESSE ARELLANO |
| Plan Check Approved | 12/2/2020 | JESSE ARELLANO |
| Issued | 12/10/2020 | APPLICANT |
| CofO in Progress | 9/7/2022 | RAUL BARAJAS |
| Permit Finaled | 10/1/2022 | DEROLD HAUFF |
| CofO Issued | 10/1/2022 | DEROLD HAUFF |
| Permit Finaled | 10/1/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| BHO/Hillside ordinance | Cleared | 6/3/2020 | DINAH GARIN |
| BHO/Hillside ordinance | Cleared | 6/4/2020 | DINAH GARIN |
| BHO/Hillside ordinance | Cleared | 6/4/2020 | DINAH GARIN |
| BHO/Hillside ordinance | Cleared | 6/4/2020 | DINAH GARIN |
| Address approval | Cleared | 6/11/2020 | DINAH GARIN |
| Eng Process Fee Ord 176,300 | Cleared | 6/18/2020 | DINAH GARIN |
| Grading Pre-Inspection | Cleared | 6/23/2020 | PATRICK MISCHLICH |
| Specific Plan | Cleared | 6/23/2020 | DOMINICK ORTIZ |
| Low Impact Development | Cleared | 8/21/2020 | ORVAL HERNANDEZ-MARCI |
| Roof/Waste drainage to street | Cleared | 9/8/2020 | DINAH GARIN |
| Hydrant and Access approval | Cleared | 9/9/2020 | MATTHEW CRAIG |
| Green Code | Cleared | 9/23/2020 | DONALD CRICHLOW |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Ha,, Seungil; Lic. No.: S4164 | 3454 W 1ST ST LOS ANGELES, CA 90004 |
Inspector Information
| BRENDAN MORELLI, (213) 202-3412 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 2/24/2021 | Conditional Approval | RAUL BARAJAS |
| Footing/Foundation/Slab | 3/9/2021 | Partial Approval | RAUL BARAJAS |
| Footing/Foundation/Slab | 3/25/2021 | Approved | RAUL BARAJAS |
| Special/Order Compliance | 5/26/2021 | Approved | BRAD BESCOS |
| Floor/Roof Diaphrgm/Shear Wall | 6/16/2021 | Approved | RAUL BARAJAS |
| BUILDING-Rough-Frame | 7/22/2021 | Partial Approval | RICHARD STEINBACH |
| ELECTRICAL-Rough | 7/22/2021 | Approved | RICHARD STEINBACH |
| Green Building Rough | 7/22/2021 | Approved | RICHARD STEINBACH |
| HVAC-Rough | 7/22/2021 | Approved | RICHARD STEINBACH |
| PLUMBING-Rough | 7/22/2021 | Approved | RICHARD STEINBACH |
| Verify Sprinkler Sign Off | 7/22/2021 | Approved | RICHARD STEINBACH |
| Insulation | 8/16/2021 | Approved | RAUL BARAJAS |
| Drywall Nailing | 9/15/2021 | Corrections Issued | RICHARD STEINBACH |
| Interior/Exterior Lathing | 9/15/2021 | Not Ready for Inspection | RICHARD STEINBACH |
| ELECTRICAL-Final | 3/7/2022 | Corrections Issued | RAUL BARAJAS |
| PLUMBING-Final | 3/7/2022 | Corrections Issued | RAUL BARAJAS |
| ELECTRICAL-Final | 3/21/2022 | Approved | RAUL BARAJAS |
| PLUMBING-Final | 3/21/2022 | Approved | RAUL BARAJAS |
| BUILDING-Rough-Frame | 5/4/2022 | Approved | RAUL BARAJAS |
| Drywall Nailing | 5/4/2022 | Approved | RAUL BARAJAS |
| Final | 5/4/2022 | Corrections Issued | RAUL BARAJAS |
| Green Building Final | 5/4/2022 | Approved | RAUL BARAJAS |
| SGSOV-Seismic Gas S/O Valve | 5/4/2022 | SGSOV Approved | RAUL BARAJAS |
| Smoke Detectors | 5/4/2022 | Approved | RAUL BARAJAS |
| ELECTRICAL-Final | 8/9/2022 | Approved | RAUL BARAJAS |
| Final | 9/7/2022 | OK to Issue CofO | RAUL BARAJAS |
| Service/Power Release | 9/7/2022 | Approved | RAUL BARAJAS |