3711 S RUTHELEN ST 90018

Certificate Information: 3711 S RUTHELEN ST 90018

Application / Permit
20014-10000-01481
Plan Check / Job No.
B20LA06351
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
2 Story Addition to existing SFD
Permit Issued
Issued on 7/20/2020
Issuing Office
Current Status
CofO Issued on 10/16/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/6/2020 APPLICANT
Assigned to Plan Check Engineer 4/23/2020 SAMUEL GONZALEZ
Corrections Issued 5/1/2020 SAMUEL GONZALEZ
Quality Review Completed 5/4/2020 LAWRENCE QUIRANTE
Green Plans Picked Up 6/23/2020 APPLICANT
Plan Check Approved 7/20/2020 SAMUEL GONZALEZ
Issued 7/20/2020 APPLICANT
Building Plans Picked Up 7/20/2020 APPLICANT
CofO in Progress 2/17/2021 ROBERT MCDOWELL
CofO in Progress 10/13/2021 SABAS ALONSO
Permit Finaled 10/16/2021 DEROLD HAUFF
Permit Finaled 10/16/2021 DEROLD HAUFF
CofO Issued 10/16/2021 DEROLD HAUFF

Permit Application Clearance Information

Green Code Cleared 6/14/2020 KHEDER ALRAZAA
Community Plan Implem. Overlay Cleared 6/24/2020 RICHARD REASER
Eng Process Fee Ord 176,300 Cleared 7/2/2020 WALLIE JONG
Roof/Waste drainage to street Cleared 7/2/2020 WALLIE JONG

Contact Information

Contractor Owner-Builder       ,
Engineer Lashkevich,, Dmitriy Leonidovich; Lic. No.: C87250 3 MARSH RD      TIBURON, CA 94920

Inspector Information

SABAS ALONSO, (213) 202-3468 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 7/29/2020 Conditional Approval ROBERT MCDOWELL
Excavation/Setback/Form/Re-Bar 7/29/2020 Corrections Issued ROBERT MCDOWELL
Insulation 8/11/2020 Not Ready for Inspection SABAS ALONSO
Insulation 8/18/2020 Partial Approval ROBERT MCDOWELL
Floor/Roof Diaphrgm/Shear Wall 8/27/2020 Partial Approval ROBERT MCDOWELL
Floor/Roof Diaphrgm/Shear Wall 9/11/2020 Not Ready for Inspection DAVID FEILER
Floor/Roof Diaphrgm/Shear Wall 9/14/2020 Corrections Issued DAVID FEILER
Floor/Roof Diaphrgm/Shear Wall 9/25/2020 Conditional Approval ROBERT MCDOWELL
ELECTRICAL-Rough 10/1/2020 No Access for Inspection FREDDIE RIVERA
Floor/Roof Diaphrgm/Shear Wall 10/1/2020 No Access for Inspection FREDDIE RIVERA
ELECTRICAL-Rough 10/2/2020 Corrections Issued ROBERT MCDOWELL
Interior/Exterior Lathing 10/2/2020 Approved ROBERT MCDOWELL
ELECTRICAL-Rough 10/8/2020 Approved ROBERT MCDOWELL
Drywall Nailing 10/20/2020 Approved ROBERT MCDOWELL
Green Building Rough 10/20/2020 Approved ROBERT MCDOWELL
BUILDING-Rough-Frame 11/30/2020 Approved ROBERT MCDOWELL
ELECTRICAL-Final 11/30/2020 Approved ROBERT MCDOWELL
Final 11/30/2020 Corrections Issued ROBERT MCDOWELL
Footing/Foundation/Slab 11/30/2020 Approved ROBERT MCDOWELL
Green Building Final 11/30/2020 Approved ROBERT MCDOWELL
SGSOV-Seismic Gas S/O Valve 11/30/2020 SGSOV Approved ROBERT MCDOWELL
Smoke Detectors 11/30/2020 Approved ROBERT MCDOWELL
Final 1/26/2021 Conditional Approval ROBERT MCDOWELL
HVAC-Final 1/26/2021 Approved ROBERT MCDOWELL
Special/Order Compliance 3/19/2021 Corrections Issued SABAS ALONSO
Final 7/28/2021 No Access for Inspection SABAS ALONSO
Final 10/12/2021 OK to Issue CofO SABAS ALONSO