3074 N ST GEORGE ST 90027
Certificate Information: 3074 N ST GEORGE ST 90027
- Application / Permit
- 20014-10000-01464
- Plan Check / Job No.
- B20LA06270
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 2ND STORY DETACHED ACCESSORY DWELLING UNIT OVER EXISTING GROUND FLOOR GARAGE PER LAMC 12.22 A.33(c) AND(d)
- Permit Issued
- Issued on 5/5/2021
- Issuing Office
- Current Status
- CofO Issued on 10/13/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/4/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 4/23/2020 | CRYSTEL MAALOUF |
| Green Plans Picked Up | 4/28/2020 | APPLICANT |
| Corrections Issued | 5/1/2020 | CRYSTEL MAALOUF |
| Quality Review Completed | 5/4/2020 | BILL STUTSMAN |
| Building Plans Picked Up | 5/7/2020 | APPLICANT |
| Applicant returned to address corrections | 10/27/2020 | CRYSTEL MAALOUF |
| Applicant returned to address corrections | 12/28/2020 | CRYSTEL MAALOUF |
| Plan Check Approved | 1/29/2021 | CRYSTEL MAALOUF |
| Issued | 5/5/2021 | APPLICANT |
| CofO in Progress | 9/27/2022 | JOSEPH MCGARRY |
| Permit Finaled | 10/13/2022 | DEROLD HAUFF |
| CofO Issued | 10/13/2022 | DEROLD HAUFF |
| Permit Finaled | 10/13/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 5/22/2020 | CECILIO NAVARRO |
| Roof/Waste drainage to street | Cleared | 5/22/2020 | CECILIO NAVARRO |
| Grading Pre-Inspection | Cleared | 5/27/2020 | VASIL MIHALEV |
| Eng Process Fee Ord 176,300 | Cleared | 6/11/2020 | CECILIO NAVARRO |
| Sewer availability | Cleared | 6/11/2020 | CECILIO NAVARRO |
| GPI Written Notices | Cleared | 8/5/2020 | CRYSTEL MAALOUF |
| Construction near power lines | Cleared | 11/13/2020 | RIDWAN HARDY |
| Green Code | Cleared | 1/29/2021 | CRYSTEL MAALOUF |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Manlangit,, Vicente Balingasa; Lic. No.: C75499 | 20626 HAYNES ST WINNETKA, CA 91306 |
Inspector Information
| ENRIQUE MIRELES, (213) 202-3438 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 5/24/2021 | Corrections Issued | HAMIK HARTOUNIAN |
| Footing/Foundation/Slab | 5/24/2021 | Partial Inspection | HAMIK HARTOUNIAN |
| Footing/Foundation/Slab | 7/12/2021 | Conditional Approval | JOSEPH MCGARRY |
| PLUMBING-Rough | 7/13/2021 | No Access for Inspection | CHARLES BOGHOSKHAN |
| Footing/Foundation/Slab | 7/22/2021 | Conditional Approval | HAMIK HARTOUNIAN |
| PLUMBING-Rough | 7/22/2021 | Partial Approval | HAMIK HARTOUNIAN |
| Floor/Roof Diaphrgm/Shear Wall | 9/30/2021 | Partial Approval | JOSEPH MCGARRY |
| Green Building Rough | 9/30/2021 | Not Ready for Inspection | JOSEPH MCGARRY |
| Verify Sprinkler Sign Off | 9/30/2021 | Not Ready for Inspection | JOSEPH MCGARRY |
| BUILDING-Rough-Frame | 12/14/2021 | Partial Inspection | ARTHUR SARGSYAN |
| ELECTRICAL-Rough | 12/14/2021 | Approved | ARTHUR SARGSYAN |
| Green Building Rough | 12/14/2021 | Approved | ARTHUR SARGSYAN |
| HVAC-Rough | 12/14/2021 | Approved | ARTHUR SARGSYAN |
| PLUMBING-Rough | 12/14/2021 | Approved | ARTHUR SARGSYAN |
| Verify Sprinkler Sign Off | 12/14/2021 | Not Ready for Inspection | ARTHUR SARGSYAN |
| Wood Frame | 12/14/2021 | Corrections Issued | ARTHUR SARGSYAN |
| BUILDING-Rough-Frame | 3/4/2022 | Conditional Approval | JOSEPH MCGARRY |
| Insulation | 3/4/2022 | Corrections Issued | JOSEPH MCGARRY |
| Interior/Exterior Lathing | 3/4/2022 | Partial Approval | JOSEPH MCGARRY |
| Verify Sprinkler Sign Off | 3/4/2022 | Approved | JOSEPH MCGARRY |
| BUILDING-Rough-Frame | 3/22/2022 | Approved | JOSEPH MCGARRY |
| Drywall Nailing | 3/22/2022 | Approved | JOSEPH MCGARRY |
| Insulation | 3/22/2022 | Approved | JOSEPH MCGARRY |
| Underground Mechanical | 3/22/2022 | Approved | JOSEPH MCGARRY |
| Interior/Exterior Lathing | 4/12/2022 | Approved | CRAIG DAVIS |
| Shower Pan | 4/12/2022 | Approved | CRAIG DAVIS |
| ELECTRICAL-Final | 6/28/2022 | Approved | JOSEPH MCGARRY |
| Service/Power Release | 6/28/2022 | Not Required | JOSEPH MCGARRY |
| Final | 7/6/2022 | Corrections Issued | JOSEPH MCGARRY |
| Footing/Foundation/Slab | 7/6/2022 | Approved | JOSEPH MCGARRY |
| Green Building Final | 7/6/2022 | Approved | JOSEPH MCGARRY |
| HVAC-Final | 7/6/2022 | Approved | JOSEPH MCGARRY |
| PLUMBING-Final | 7/6/2022 | Approved | JOSEPH MCGARRY |
| SGSOV-Seismic Gas S/O Valve | 7/6/2022 | SGSOV Approved | JOSEPH MCGARRY |
| Smoke Detectors | 7/6/2022 | Approved | JOSEPH MCGARRY |
| Final | 9/20/2022 | Corrections Issued | JOSEPH MCGARRY |
| Final | 9/21/2022 | Conditional Approval | JOSEPH MCGARRY |
| Final | 9/26/2022 | OK to Issue CofO | JOSEPH MCGARRY |