2825-2827 W 15TH ST 90006

Certificate Information: 2825-2827 W 15TH ST 90006

Application / Permit
20014-10000-01449
Plan Check / Job No.
B20LA06170
Group
Building
Type
Bldg-Addition
Sub-Type
Apartment
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT PORTION OF EXISTING GARAGE TO (2) ADU UNITS PER CA Govt. Code 65852.2(e)(1)(D AND AN ADDITION.
Permit Issued
Issued on 8/17/2021
Issuing Office
Current Status
CofO Issued on 8/8/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/3/2020 APPLICANT
Assigned to Plan Check Engineer 4/23/2020 SAMUEL GONZALEZ
Corrections Issued 4/28/2020 SAMUEL GONZALEZ
Quality Review Completed 5/4/2020 LAWRENCE QUIRANTE
Disabled Access Plans Picked Up 5/6/2020 APPLICANT
Green Plans Picked Up 7/27/2020 APPLICANT
Plan Check Approved 7/29/2021 SAMUEL GONZALEZ
Issued 8/17/2021 APPLICANT
Building Plans Picked Up 8/20/2021 APPLICANT
CofO in Progress 8/8/2022 TIMOTHY BUXTON
CofO Issued 8/8/2022 ERNESTO CORRAL
Permit Finaled 8/8/2022 ERNESTO CORRAL

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 6/10/2020 RENZ SORIANO
Roof/Waste drainage to street Cleared 6/10/2020 RENZ SORIANO
Address approval Cleared 6/11/2020 RENZ SORIANO
Sewer availability Cleared 6/11/2020 RENZ SORIANO
HPOZ Cleared 6/15/2020 DEEPEAKA DHALIWAL
Construction near power lines Cleared 9/23/2020 RIDWAN HARDY
DAS Clearance Cleared 10/15/2020 SAMUEL GONZALEZ
Hydrant and Access approval Cleared 11/2/2020 MATTHEW CRAIG
Green Code Cleared 4/28/2021 SAMUEL GONZALEZ

Contact Information

Contractor Ben Porat Moshe M; Lic. No.: 963181-B P O BOX 48603      LOS ANGELES, CA 90048
Engineer Mourad,, Daniel; Lic. No.: C83387 542 N FULLER AVE      LOS ANGELES, CA 90036

Inspector Information

JEROME BLACKWOOD, (213) 213-5353 Office Hours: 7:00-8:00 AM MON-FRI
REGINA MENDEZ, (213) 213-5353 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 11/9/2021 Approved DANIEL COLLINS
Green Building Rough 12/8/2021 Approved TIMOTHY BUXTON
Wood Frame 12/8/2021 Approved TIMOTHY BUXTON
Drywall Nailing 12/20/2021 Corrections Issued DARRYL ARNOLD
Insulation 12/20/2021 Conditional Approval DARRYL ARNOLD
Interior/Exterior Lathing 12/20/2021 Conditional Approval DARRYL ARNOLD
Drywall Nailing 3/1/2022 Approved TIMOTHY BUXTON
Final 3/1/2022 Conditional Approval TIMOTHY BUXTON
Green Building Final 3/1/2022 Approved TIMOTHY BUXTON
SGSOV-Seismic Gas S/O Valve 3/1/2022 SGSOV No Gas TIMOTHY BUXTON
Smoke Detectors 3/1/2022 Approved TIMOTHY BUXTON
Final 8/5/2022 Partial Inspection EDWIN GREGORYONA