3012 W FANITA ST 90026
Certificate Information: 3012 W FANITA ST 90026
- Application / Permit
- 20014-10000-01447
- Plan Check / Job No.
- B20LA06164
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 2ND STORY ADDITION TO EXISTING 1 STORY SINGLE FAMILY RESIDENCE. INTERIOR REMODEL OF EXISTING 1ST FLOOR
- Permit Issued
- Issued on 2/5/2021
- Issuing Office
- Current Status
- CofO Issued on 10/28/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/2/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 4/23/2020 | CRYSTEL MAALOUF |
| Corrections Issued | 5/5/2020 | CRYSTEL MAALOUF |
| Quality Review Completed | 5/7/2020 | BILL STUTSMAN |
| Green Plans Picked Up | 10/14/2020 | APPLICANT |
| Applicant returned to address corrections | 10/22/2020 | CRYSTEL MAALOUF |
| Applicant returned to address corrections | 11/4/2020 | CRYSTEL MAALOUF |
| Plan Check Approved | 12/10/2020 | CRYSTEL MAALOUF |
| Issued | 2/5/2021 | APPLICANT |
| Building Plans Picked Up | 2/8/2021 | APPLICANT |
| CofO in Progress | 8/5/2022 | FREDDIE RIVERA |
| No Progress | 8/30/2022 | RUBEN SALAS |
| CofO in Progress | 10/20/2022 | RUBEN SALAS |
| Permit Finaled | 10/28/2022 | DEROLD HAUFF |
| CofO Issued | 10/28/2022 | DEROLD HAUFF |
| Permit Finaled | 10/28/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| Low Impact Development | Cleared | 8/10/2020 | JORGE MEJIA LEMUS |
| Eng Process Fee Ord 176,300 | Cleared | 8/20/2020 | ELENA LOPEZ |
| Roof/Waste drainage to street | Cleared | 8/24/2020 | ELENA LOPEZ |
| Green Code | Cleared | 10/13/2020 | KHEDER ALRAZAA |
| GPI Written Notices | Cleared | 10/22/2020 | CRYSTEL MAALOUF |
| Grading Pre-Inspection | Cleared | 10/22/2020 | CRYSTEL MAALOUF |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| FREDDIE RIVERA, (213) 202-3437 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 2/10/2021 | Corrections Issued | HAMIK HARTOUNIAN |
| Deputy Drilled-In Anchors | 3/5/2021 | No Access for Inspection | ELMER BLAND |
| Excavation/Setback/Form/Re-Bar | 3/15/2021 | Corrections Issued | RUBEN SALAS |
| Footing/Foundation/Slab | 3/17/2021 | Approved | RUBEN SALAS |
| METHANE-Barrier | 3/17/2021 | Approved | RUBEN SALAS |
| METHANE-Subgrade | 3/17/2021 | Approved | RUBEN SALAS |
| Floor/Roof Diaphrgm/Shear Wall | 3/31/2021 | Partial Approval | ROBERT VORHIS |
| BUILDING-Rough-Frame | 5/20/2021 | Not Ready for Inspection | ROBERT VORHIS |
| Floor/Roof Diaphrgm/Shear Wall | 5/20/2021 | Corrections Issued | ROBERT VORHIS |
| Green Building Rough | 5/20/2021 | Not Ready for Inspection | ROBERT VORHIS |
| METHANE-Rough | 5/20/2021 | Not Ready for Inspection | ROBERT VORHIS |
| PLUMBING-Rough | 5/26/2021 | Approved | ROBERT VORHIS |
| ELECTRICAL-Rough | 6/17/2021 | Approved | ROBERT VORHIS |
| HVAC-Rough | 6/17/2021 | Partial Inspection | ROBERT VORHIS |
| Floor/Roof Diaphrgm/Shear Wall | 7/16/2021 | Approved | ROBERT VORHIS |
| HVAC-Rough | 7/16/2021 | Approved | ROBERT VORHIS |
| BUILDING-Rough-Frame | 7/28/2021 | Not Ready for Inspection | ROBERT VORHIS |
| Green Building Rough | 7/28/2021 | Approved | ROBERT VORHIS |
| Interior/Exterior Lathing | 7/28/2021 | Partial Approval | ROBERT VORHIS |
| METHANE-Rough | 7/28/2021 | Approved | ROBERT VORHIS |
| Shower Pan | 7/28/2021 | Approved | ROBERT VORHIS |
| BUILDING-Rough-Frame | 8/2/2021 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| Insulation | 8/2/2021 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| BUILDING-Rough-Frame | 8/4/2021 | Corrections Issued | JOAQUIN GREENOUGH |
| Insulation | 8/4/2021 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| BUILDING-Rough-Frame | 8/6/2021 | Approved | CALEB MEISTER |
| Insulation | 8/6/2021 | Approved | CALEB MEISTER |
| Drywall Nailing | 8/12/2021 | Approved | RICHARD STEINBACH |
| Interior/Exterior Lathing | 8/30/2021 | Approved | ASHLEY THOMPSON |
| Final | 5/19/2022 | Corrections Issued | FREDDIE RIVERA |
| Green Building Final | 5/19/2022 | Approved | FREDDIE RIVERA |
| SGSOV-Seismic Gas S/O Valve | 5/19/2022 | SGSOV Not Ready | FREDDIE RIVERA |
| Smoke Detectors | 5/19/2022 | Approved | FREDDIE RIVERA |
| Final | 6/10/2022 | Partial Inspection | FREDDIE RIVERA |
| SGSOV-Seismic Gas S/O Valve | 6/10/2022 | SGSOV Approved | FREDDIE RIVERA |
| Final | 8/4/2022 | OK to Issue CofO | FREDDIE RIVERA |