3012 W FANITA ST 90026

Certificate Information: 3012 W FANITA ST 90026

Application / Permit
20014-10000-01447
Plan Check / Job No.
B20LA06164
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
2ND STORY ADDITION TO EXISTING 1 STORY SINGLE FAMILY RESIDENCE. INTERIOR REMODEL OF EXISTING 1ST FLOOR
Permit Issued
Issued on 2/5/2021
Issuing Office
Current Status
CofO Issued on 10/28/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/2/2020 APPLICANT
Assigned to Plan Check Engineer 4/23/2020 CRYSTEL MAALOUF
Corrections Issued 5/5/2020 CRYSTEL MAALOUF
Quality Review Completed 5/7/2020 BILL STUTSMAN
Green Plans Picked Up 10/14/2020 APPLICANT
Applicant returned to address corrections 10/22/2020 CRYSTEL MAALOUF
Applicant returned to address corrections 11/4/2020 CRYSTEL MAALOUF
Plan Check Approved 12/10/2020 CRYSTEL MAALOUF
Issued 2/5/2021 APPLICANT
Building Plans Picked Up 2/8/2021 APPLICANT
CofO in Progress 8/5/2022 FREDDIE RIVERA
No Progress 8/30/2022 RUBEN SALAS
CofO in Progress 10/20/2022 RUBEN SALAS
Permit Finaled 10/28/2022 DEROLD HAUFF
CofO Issued 10/28/2022 DEROLD HAUFF
Permit Finaled 10/28/2022 DEROLD HAUFF

Permit Application Clearance Information

Low Impact Development Cleared 8/10/2020 JORGE MEJIA LEMUS
Eng Process Fee Ord 176,300 Cleared 8/20/2020 ELENA LOPEZ
Roof/Waste drainage to street Cleared 8/24/2020 ELENA LOPEZ
Green Code Cleared 10/13/2020 KHEDER ALRAZAA
GPI Written Notices Cleared 10/22/2020 CRYSTEL MAALOUF
Grading Pre-Inspection Cleared 10/22/2020 CRYSTEL MAALOUF

Contact Information

Contractor Owner-Builder       ,

Inspector Information

FREDDIE RIVERA, (213) 202-3437 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 2/10/2021 Corrections Issued HAMIK HARTOUNIAN
Deputy Drilled-In Anchors 3/5/2021 No Access for Inspection ELMER BLAND
Excavation/Setback/Form/Re-Bar 3/15/2021 Corrections Issued RUBEN SALAS
Footing/Foundation/Slab 3/17/2021 Approved RUBEN SALAS
METHANE-Barrier 3/17/2021 Approved RUBEN SALAS
METHANE-Subgrade 3/17/2021 Approved RUBEN SALAS
Floor/Roof Diaphrgm/Shear Wall 3/31/2021 Partial Approval ROBERT VORHIS
BUILDING-Rough-Frame 5/20/2021 Not Ready for Inspection ROBERT VORHIS
Floor/Roof Diaphrgm/Shear Wall 5/20/2021 Corrections Issued ROBERT VORHIS
Green Building Rough 5/20/2021 Not Ready for Inspection ROBERT VORHIS
METHANE-Rough 5/20/2021 Not Ready for Inspection ROBERT VORHIS
PLUMBING-Rough 5/26/2021 Approved ROBERT VORHIS
ELECTRICAL-Rough 6/17/2021 Approved ROBERT VORHIS
HVAC-Rough 6/17/2021 Partial Inspection ROBERT VORHIS
Floor/Roof Diaphrgm/Shear Wall 7/16/2021 Approved ROBERT VORHIS
HVAC-Rough 7/16/2021 Approved ROBERT VORHIS
BUILDING-Rough-Frame 7/28/2021 Not Ready for Inspection ROBERT VORHIS
Green Building Rough 7/28/2021 Approved ROBERT VORHIS
Interior/Exterior Lathing 7/28/2021 Partial Approval ROBERT VORHIS
METHANE-Rough 7/28/2021 Approved ROBERT VORHIS
Shower Pan 7/28/2021 Approved ROBERT VORHIS
BUILDING-Rough-Frame 8/2/2021 Not Ready for Inspection KATHRYN BUTTERWORTH
Insulation 8/2/2021 Not Ready for Inspection KATHRYN BUTTERWORTH
BUILDING-Rough-Frame 8/4/2021 Corrections Issued JOAQUIN GREENOUGH
Insulation 8/4/2021 Not Ready for Inspection JOAQUIN GREENOUGH
BUILDING-Rough-Frame 8/6/2021 Approved CALEB MEISTER
Insulation 8/6/2021 Approved CALEB MEISTER
Drywall Nailing 8/12/2021 Approved RICHARD STEINBACH
Interior/Exterior Lathing 8/30/2021 Approved ASHLEY THOMPSON
Final 5/19/2022 Corrections Issued FREDDIE RIVERA
Green Building Final 5/19/2022 Approved FREDDIE RIVERA
SGSOV-Seismic Gas S/O Valve 5/19/2022 SGSOV Not Ready FREDDIE RIVERA
Smoke Detectors 5/19/2022 Approved FREDDIE RIVERA
Final 6/10/2022 Partial Inspection FREDDIE RIVERA
SGSOV-Seismic Gas S/O Valve 6/10/2022 SGSOV Approved FREDDIE RIVERA
Final 8/4/2022 OK to Issue CofO FREDDIE RIVERA