4850 W DOCKWEILER ST 90019

Certificate Information: 4850 W DOCKWEILER ST 90019

Application / Permit
20014-10000-01445
Plan Check / Job No.
B20LA06161
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ADDITION TO 1ST AND 2ND FLOOR OF (E) ONE STORY TWO CAR GARAGE AND CONVERT TO TWO STORY ADU WITH STORAGE ROOM.
Permit Issued
Issued on 7/28/2020
Issuing Office
Current Status
CofO Issued on 2/12/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/23/2020 APPLICANT
Assigned to Plan Check Engineer 4/30/2020 SAMUEL GONZALEZ
Corrections Issued 5/8/2020 SAMUEL GONZALEZ
Quality Review Completed 5/20/2020 LAWRENCE QUIRANTE
Green Plans Picked Up 6/29/2020 APPLICANT
Applicant returned to address corrections 7/21/2020 SAMUEL GONZALEZ
Plan Check Approved 7/28/2020 SAMUEL GONZALEZ
Issued 7/28/2020 APPLICANT
Building Plans Picked Up 7/30/2020 APPLICANT
CofO in Progress 10/4/2021 STUART CHAPMAN
No Progress 12/2/2021 STUART CHAPMAN
CofO in Progress 2/9/2024 SCOTT FINNILA
CofO Issued 2/12/2024 DEROLD HAUFF
Permit Finaled 2/12/2024 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 5/28/2020 EMIL KYUPELYAN
Eng Process Fee Ord 176,300 Cleared 6/1/2020 EMIL KYUPELYAN
Sewer availability Cleared 6/1/2020 EMIL KYUPELYAN
Roof/Waste drainage to street Cleared 6/9/2020 EMIL KYUPELYAN
Green Code Cleared 6/25/2020 VIVIAN LAO

Contact Information

Contractor E G N Builders Group; Lic. No.: 1051430-B 5000 PARKWAY CALABASAS   SUITE 308    CALABASAS, CA 91302
Engineer Landers,, Jesse Eugene; Lic. No.: C83060 2101 BENECIA AVE      LOS ANGELES, CA 90025

Inspector Information

JUSTIN HAWLEY, (213) 202-3432 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 8/28/2020 Partial Approval STUART CHAPMAN
Excavation/Setback/Form/Re-Bar 9/1/2020 Not Ready for Inspection STUART CHAPMAN
Deputy Drilled-In Anchors 9/2/2020 Approved STUART CHAPMAN
Footing/Foundation/Slab 9/2/2020 Approved STUART CHAPMAN
METHANE-Barrier 9/2/2020 Approved STUART CHAPMAN
METHANE-Subgrade 9/2/2020 Approved STUART CHAPMAN
Sewer 9/9/2020 Corrections Issued STUART CHAPMAN
Underground Mechanical 9/9/2020 Partial Approval STUART CHAPMAN
Underground Mechanical 9/18/2020 Partial Approval STUART CHAPMAN
Underground Mechanical 9/24/2020 Partial Approval STUART CHAPMAN
BUILDING-Rough-Frame 12/21/2020 Corrections Issued STUART CHAPMAN
Green Building Rough 12/21/2020 Not Ready for Inspection STUART CHAPMAN
METHANE-Rough 12/21/2020 Approved STUART CHAPMAN
Floor/Roof Diaphrgm/Shear Wall 12/22/2020 Partial Approval STUART CHAPMAN
BUILDING-Rough-Frame 1/8/2021 Not Ready for Inspection STUART CHAPMAN
Floor/Roof Diaphrgm/Shear Wall 1/8/2021 Partial Approval STUART CHAPMAN
Green Building Rough 1/8/2021 Not Ready for Inspection STUART CHAPMAN
Wood Frame 1/8/2021 Partial Approval STUART CHAPMAN
Floor/Roof Diaphrgm/Shear Wall 1/15/2021 Partial Approval STUART CHAPMAN
Wood Frame 1/15/2021 Partial Approval STUART CHAPMAN
Rough-Elec/Plmb/HVAC 1/21/2021 Corrections Issued STUART CHAPMAN
Deputy Wood Construction 1/25/2021 Approved STUART CHAPMAN
ELECTRICAL-Rough 1/26/2021 Not Ready for Inspection STUART CHAPMAN
HVAC-Rough 1/26/2021 Not Ready for Inspection STUART CHAPMAN
PLUMBING-Rough 1/26/2021 Not Ready for Inspection STUART CHAPMAN
Rough-Elec/Plmb/HVAC 1/29/2021 Approved STUART CHAPMAN
Insulation 2/8/2021 Corrections Issued STUART CHAPMAN
Interior/Exterior Lathing 2/8/2021 Partial Approval STUART CHAPMAN
Insulation 2/16/2021 Approved STUART CHAPMAN
Drywall Nailing 3/10/2021 Not Ready for Inspection STUART CHAPMAN
Green Building Rough 3/10/2021 Approved STUART CHAPMAN
Sewer 3/22/2021 Corrections Issued STUART CHAPMAN
Sewer 3/30/2021 Corrections Issued STUART CHAPMAN
Sewer 4/13/2021 Corrections Issued STUART CHAPMAN
Sewer 4/22/2021 Not Ready for Inspection STUART CHAPMAN
Sewer 6/17/2021 Not Ready for Inspection STUART CHAPMAN
SGSOV-Seismic Gas S/O Valve 7/29/2021 SGSOV Not Ready KATHRYN BUTTERWORTH
Sewer 8/31/2021 Approved STUART CHAPMAN
Service/Power Release 9/21/2021 Not Ready for Inspection STUART CHAPMAN
BUILDING-Rough-Frame 9/22/2021 Approved STUART CHAPMAN
Drywall Nailing 9/22/2021 Approved STUART CHAPMAN
ELECTRICAL-Final 9/22/2021 Corrections Issued STUART CHAPMAN
Final 9/22/2021 Not Ready for Inspection STUART CHAPMAN
Green Building Final 9/22/2021 Approved STUART CHAPMAN
HVAC-Final 9/22/2021 Corrections Issued STUART CHAPMAN
PLUMBING-Final 9/22/2021 Corrections Issued STUART CHAPMAN
SGSOV-Seismic Gas S/O Valve 9/22/2021 SGSOV Approved STUART CHAPMAN
Smoke Detectors 9/22/2021 Approved STUART CHAPMAN
ELECTRICAL-Final 9/30/2021 Approved STUART CHAPMAN
Final 9/30/2021 OK to Issue CofO STUART CHAPMAN
HVAC-Final 9/30/2021 Approved STUART CHAPMAN
PLUMBING-Final 9/30/2021 Approved STUART CHAPMAN