9300 W HAZEN DR 90210
Certificate Information: 9300 W HAZEN DR 90210
- Application / Permit
- 20014-10000-01436
- Plan Check / Job No.
- B20LA06075
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- PROPOSED 1ST & 2ND FLOOR ADDITIONS (200 SF) TO EXISTING SINGLE FAMILY DWELLING.
- Permit Issued
- Issued on 8/5/2020
- Issuing Office
- Current Status
- Issued on 8/5/2020
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 4/1/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 4/9/2020 | CHUNG-WEN CHUANG |
| Green Plans Picked Up | 4/13/2020 | APPLICANT |
| Corrections Issued | 4/28/2020 | CHUNG-WEN CHUANG |
| Quality Review Completed | 5/18/2020 | TIEN JEN WANG |
| Building Plans Picked Up | 5/20/2020 | APPLICANT |
| Applicant returned to address corrections | 6/30/2020 | CHUNG-WEN CHUANG |
| Plan Check Approved | 7/22/2020 | CHUNG-WEN CHUANG |
| Issued | 8/5/2020 | APPLICANT |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 5/1/2020 | DINAH GARIN |
| Roof/Waste drainage to street | Cleared | 5/1/2020 | DINAH GARIN |
| Grading Pre-Inspection | Cleared | 5/19/2020 | PATRICK MISCHLICH |
| Specific Plan | Cleared | 5/26/2020 | DOMINICK ORTIZ |
| Green Code | Cleared | 7/8/2020 | VIVIAN LAO |
| GPI Written Notices | Cleared | 7/9/2020 | CHUNG-WEN CHUANG |
Contact Information
| Contractor | E N S Builders Inc; Lic. No.: 1022358-B | 1212 WESTCHESTER PLACE LOS ANGELES, CA 90019 |
| Engineer | Soliman,, John; Lic. No.: C80833 | 13785 PELICAN DR RANCHO CUCAMONGA, CA 91739 |
Inspector Information
| BRENDAN MORELLI, (213) 202-3412 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 8/11/2020 | Conditional Approval | CHRISTOPHER DELLEFIELD |
| Footing/Foundation/Slab | 8/14/2020 | Corrections Issued | RAUL BARAJAS |
| Footing/Foundation/Slab | 8/24/2020 | Partial Approval | RAUL BARAJAS |
| Deputy Reinf. Concrete | 8/27/2020 | Conditional Approval | CHRISTOPHER DELLEFIELD |
| Floor/Roof Diaphrgm/Shear Wall | 9/10/2020 | Partial Approval | RAUL BARAJAS |
| Floor/Roof Diaphrgm/Shear Wall | 9/24/2020 | Conditional Approval | RAUL BARAJAS |
| Deputy Wood Construction | 10/14/2020 | No Access for Inspection | ELMER BLAND |
| BUILDING-Rough-Frame | 10/15/2020 | Not Ready for Inspection | RAUL BARAJAS |
| ELECTRICAL-Rough | 10/15/2020 | Approved | RAUL BARAJAS |
| Green Building Rough | 10/15/2020 | Approved | RAUL BARAJAS |
| HVAC-Rough | 10/15/2020 | Approved | RAUL BARAJAS |
| PLUMBING-Rough | 10/15/2020 | Approved | RAUL BARAJAS |
| Insulation | 10/30/2020 | Approved | RAUL BARAJAS |
| Interior/Exterior Lathing | 10/30/2020 | Approved | RAUL BARAJAS |
| Drywall Nailing | 11/5/2020 | Approved | RAUL BARAJAS |
| BUILDING-Rough-Frame | 12/9/2020 | Approved | RAUL BARAJAS |
| Final | 12/9/2020 | Corrections Issued | RAUL BARAJAS |
| Footing/Foundation/Slab | 12/9/2020 | Approved | RAUL BARAJAS |
| Green Building Final | 12/9/2020 | Approved | RAUL BARAJAS |
| SGSOV-Seismic Gas S/O Valve | 12/9/2020 | SGSOV Approved | RAUL BARAJAS |
| Smoke Detectors | 12/9/2020 | Approved | RAUL BARAJAS |