1268 W 37TH PL 90007
Certificate Information: 1268 W 37TH PL 90007
- Application / Permit
- 20014-10000-01428
- Plan Check / Job No.
- B20LA06019
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- ADDITIONS AT THE REAR FOR A 3RD BEDROOM AND LAUNDRY ON (E) 3 UNIT APARTMENT. ALL WORK PER ENGINEERING.
- Permit Issued
- Issued on 6/9/2021
- Issuing Office
- Current Status
- CofO Issued on 12/30/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/7/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 4/7/2020 | LUKE GONZALES |
| Corrections Issued | 4/7/2020 | LUKE GONZALES |
| Applicant returned to address corrections | 6/23/2020 | LUKE GONZALES |
| Applicant returned to address corrections | 5/6/2021 | OMAR GARNICA |
| Plan Check Approved | 6/8/2021 | OMAR GARNICA |
| Issued | 6/9/2021 | APPLICANT |
| Building Plans Picked Up | 6/11/2021 | APPLICANT |
| CofO in Progress | 12/30/2022 | TED RIES |
| CofO Issued | 12/30/2022 | TED RIES |
| Permit Finaled | 12/30/2022 | TED RIES |
Permit Application Clearance Information
| Address approval | Cleared | 3/23/2021 | JEANIE LAM |
| Miscellaneous | Cleared | 3/23/2021 | DENZEL HENDERSON |
| Roof/Waste drainage to street | Cleared | 3/23/2021 | JEANIE LAM |
| ZI | Cleared | 3/23/2021 | DENZEL HENDERSON |
| Eng Process Fee Ord 176,300 | Cleared | 3/24/2021 | JEANIE LAM |
| Community Plan Implem. Overlay | Cleared | 4/26/2021 | RAFAEL FONTES |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Crook,, Barrett Cameron; Lic. No.: C57196 | 2036 CREEK RD KITTY HAWK, NC 27949 |
Inspector Information
| PAUL BAZERKANIAN, (213) 482-0353 | Office Hours: 7:00-8:00 AM MON-FRI |
| LUIS CCAMACHO, (213) 482-0353 | Office Hours: 7:00-8:00 AM MON-FRI |
| ALAN MORELOS, (213) 482-0353 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Green Building Rough | 6/21/2021 | Not Ready for Inspection | LEOPOLDO MENDOZA |
| Pre-Inspection | 6/21/2021 | Partial Inspection | LEOPOLDO MENDOZA |
| Wood Frame | 6/21/2021 | Not Ready for Inspection | LEOPOLDO MENDOZA |
| Pre-Inspection | 2/25/2022 | Conditional Approval | BRUCE CAMPBELL |
| Pre-Inspection | 4/26/2022 | Approved | RUSSELL BONVOULOIR |
| Green Building Rough | 5/16/2022 | Approved | RUSSELL BONVOULOIR |
| Wood Frame | 5/16/2022 | Approved | RUSSELL BONVOULOIR |
| Drywall Nailing | 6/1/2022 | Approved | RUSSELL BONVOULOIR |
| Final | 9/8/2022 | Not Ready for Inspection | RUSSELL BONVOULOIR |
| Footing/Foundation/Slab | 9/8/2022 | Approved | RUSSELL BONVOULOIR |
| Green Building Final | 9/8/2022 | Approved | RUSSELL BONVOULOIR |
| SGSOV-Seismic Gas S/O Valve | 9/8/2022 | SGSOV Approved | RUSSELL BONVOULOIR |
| Smoke Detectors | 9/8/2022 | Approved | RUSSELL BONVOULOIR |
| Final | 12/14/2022 | Conditional Approval | RAMAZANALI ALMASI |