948 W 74TH ST 1-4 90044
Certificate Information: 948 W 74TH ST 1-4 90044
- Application / Permit
- 20014-10000-01374
- Plan Check / Job No.
- B20LA05850
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- (TOC) 55'X36' (N) 2-STORY BUILDING (2,262 SQFT), INCLUDING ONE 18'-8"X32' (N) ACCESSORY DWELLING UNIT (548 SF) & STORAGE ROOM (63 SF) ON 1ST FLOOR AND THREE (N) UNITS ON 2ND FLOOR, ATTACHED TO (E) COMMERCIAL BLDG. PARKING DESIGN PURSUANT TO THE TOC PROGRAM PER LAMC 12.22 A.31 AND APPLYING BASE INCETIVES. PROJECTS IS UNDER TIER 2.
- Permit Issued
- Issued on 1/17/2022
- Issuing Office
- Current Status
- Issued on 1/17/2022
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 4/3/2020 | APPLICANT |
| Application Withdrawn | 4/3/2020 | APPLICANT |
| Re-Activate Applicaton | 4/8/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 4/23/2020 | CHUNG-WEN CHUANG |
| Corrections Issued | 5/12/2020 | CHUNG-WEN CHUANG |
| Disabled Access Plans Picked Up | 5/19/2020 | APPLICANT |
| Quality Review Completed | 6/9/2020 | KESETE HAREGOT |
| Applicant returned to address corrections | 8/25/2020 | CHUNG-WEN CHUANG |
| Applicant returned to address corrections | 1/14/2021 | CHUNG-WEN CHUANG |
| Green Plans Picked Up | 3/10/2021 | APPLICANT |
| Applicant returned to address corrections | 4/29/2021 | CHUNG-WEN CHUANG |
| Applicant returned to address corrections | 12/13/2021 | CHUNG-WEN CHUANG |
| Plan Check Approved | 12/15/2021 | CHUNG-WEN CHUANG |
| Issued | 1/17/2022 | APPLICANT |
| Building Plans Picked Up | 1/27/2022 | APPLICANT |
Permit Application Clearance Information
| Specific Plan | Cleared | 6/19/2020 | TERRI OSBORNE |
| Historic Resource Verification | Cleared | 6/22/2020 | MICAELA TORRES-GIL |
| Address approval | Cleared | 6/23/2020 | CECILIO NAVARRO |
| Address approval | Cleared | 6/23/2020 | CECILIO NAVARRO |
| Permit | Cleared | 6/23/2020 | CECILIO NAVARRO |
| Eng Process Fee Ord 176,300 | Cleared | 7/7/2020 | CECILIO NAVARRO |
| Sewer availability | Cleared | 8/6/2020 | CECILIO NAVARRO |
| DAS Clearance | Cleared | 2/18/2021 | CHUNG-WEN CHUANG |
| Redevelopment Project Area | Cleared | 2/26/2021 | GRACIELA ACOSTA |
| Green Code | Cleared | 3/5/2021 | KHEDER ALRAZAA |
| Community Plan Implem. Overlay | Cleared | 3/15/2021 | RAFAEL FONTES |
| ZI | Cleared | 3/15/2021 | RAFAEL FONTES |
| ZI | Cleared | 3/15/2021 | RAFAEL FONTES |
| ZA Case | Cleared | 4/7/2021 | ANNA VIDAL |
| Low Impact Development | Cleared | 6/9/2021 | ORVAL HERNANDEZ-MARCI |
| Roof/Waste drainage to street | Cleared | 6/14/2021 | CECILIO NAVARRO |
| Density Bonus 12.22.A.31 | Cleared | 11/5/2021 | JAMES MCCARTHY |
Contact Information
| Architect | Salcedo,, Glen Charles; Lic. No.: C33143 | P O BOX 14202 VAN NUYS, CA 91409 |
| Contractor | C G S Home Improvement Inc; Lic. No.: 1037939-B | 7189 N FIGUEROA ST LOS ANGELES, CA 90042 |
Inspector Information
| PAUL BAZERKANIAN, (213) 482-0353 | Office Hours: 7:00-8:00 AM MON-FRI |
| LUIS CCAMACHO, (213) 482-0353 | Office Hours: 7:00-8:00 AM MON-FRI |
| ALAN MORELOS, (213) 482-0353 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 4/13/2022 | Corrections Issued | RUSSELL BONVOULOIR |
| Pre-Inspection | 4/14/2022 | Corrections Issued | RUSSELL BONVOULOIR |
| Deputy Drilled-In Anchors | 4/29/2022 | Conditional Approval | RUSSELL BONVOULOIR |
| Footing/Foundation/Slab | 7/7/2022 | Partial Approval | RUSSELL BONVOULOIR |
| Deputy Steel/Welding | 8/11/2022 | Conditional Approval | RUSSELL BONVOULOIR |
| Green Building Rough | 8/29/2022 | Partial Inspection | RUSSELL BONVOULOIR |
| Pre-Inspection | 8/29/2022 | Partial Inspection | RUSSELL BONVOULOIR |
| Structural Steel Frame | 8/29/2022 | Partial Inspection | RUSSELL BONVOULOIR |
| Deputy Steel/Welding | 9/19/2022 | Conditional Approval | RUSSELL BONVOULOIR |
| Floor/Roof Diaphrgm/Shear Wall | 10/18/2022 | Partial Approval | RUSSELL BONVOULOIR |
| Floor/Roof Diaphrgm/Shear Wall | 11/21/2022 | Approved | RONALD JIMENEZ |
| Floor/Roof Diaphrgm/Shear Wall | 1/6/2023 | Not Ready for Inspection | ALAN MORELOS |
| Green Building Rough | 1/6/2023 | Not Ready for Inspection | ALAN MORELOS |
| Wood Frame | 1/6/2023 | Not Ready for Inspection | ALAN MORELOS |
| Pre-Inspection | 2/27/2023 | No Access for Inspection | ALAN MORELOS |
| Floor/Roof Diaphrgm/Shear Wall | 3/1/2023 | Not Ready for Inspection | ALAN MORELOS |
| Green Building Rough | 3/1/2023 | Not Ready for Inspection | ALAN MORELOS |
| Pre-Inspection | 3/1/2023 | Partial Inspection | ALAN MORELOS |
| Wood Frame | 3/1/2023 | Not Ready for Inspection | ALAN MORELOS |
| Deputy Wood Construction | 3/2/2023 | Conditional Approval | MICHAEL ROSENBERG |
| Green Building Rough | 5/3/2023 | Approved | ALAN MORELOS |
| Wood Frame | 5/3/2023 | Partial Approval | ALAN MORELOS |
| Insulation | 5/24/2023 | Conditional Approval | DARRYL ARNOLD |
| Interior/Exterior Lathing | 5/24/2023 | Conditional Approval | DARRYL ARNOLD |
| Interior/Exterior Lathing | 5/25/2023 | Conditional Approval | DARRYL ARNOLD |
| Drywall Nailing | 8/23/2023 | Approved | RAFAEL CORTES |
| Interior/Exterior Lathing | 8/23/2023 | Partial Approval | RAFAEL CORTES |
| Final | 2/9/2026 | Not Ready for Inspection | ALFREDO LOPEZ |
| Footing/Foundation/Slab | 2/9/2026 | Partial Inspection | ALFREDO LOPEZ |
| Green Building Final | 2/9/2026 | Approved | ALFREDO LOPEZ |
| SGSOV-Seismic Gas S/O Valve | 2/9/2026 | SGSOV Not Ready | ALFREDO LOPEZ |
| Smoke Detectors | 2/9/2026 | Not Ready for Inspection | ALFREDO LOPEZ |
| Structural Steel Frame | 2/9/2026 | Not Ready for Inspection | ALFREDO LOPEZ |
| Wood Frame | 2/9/2026 | Partial Inspection | ALFREDO LOPEZ |