5330 S WEST BLVD 90043
Certificate Information: 5330 S WEST BLVD 90043
- Application / Permit
- 20014-10000-01365
- Plan Check / Job No.
- B20LA05813
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW STORY ADDITION, ADD BATH AND LOFT SPACE ON THE 2ND FLOOR AND EXTEND 1ST FLOOR
- Permit Issued
- Issued on 9/24/2020
- Issuing Office
- Current Status
- Issued on 9/24/2020
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 4/1/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 4/9/2020 | CRYSTEL MAALOUF |
| Corrections Issued | 4/15/2020 | CRYSTEL MAALOUF |
| Quality Review Completed | 4/21/2020 | BILL STUTSMAN |
| Building Plans Picked Up | 4/24/2020 | APPLICANT |
| Applicant returned to address corrections | 6/26/2020 | CRYSTEL MAALOUF |
| Applicant returned to address corrections | 8/11/2020 | CRYSTEL MAALOUF |
| Green Plans Picked Up | 8/13/2020 | APPLICANT |
| Applicant returned to address corrections | 9/16/2020 | CRYSTEL MAALOUF |
| Plan Check Approved | 9/22/2020 | CRYSTEL MAALOUF |
| Issued | 9/24/2020 | APPLICANT |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 6/4/2020 | WALLIE JONG |
| Roof/Waste drainage to street | Cleared | 6/15/2020 | WALLIE JONG |
| Green Code | Cleared | 6/29/2020 | VIVIAN LAO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Guzman,, Jesus Enrique; Lic. No.: C27906 | 927 AMELUXEN AVE HACIENDA HEIGHTS, CA 91745 |
Inspector Information
| LUIS CASTRO, (213) 202-3436 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 3/1/2021 | Approved | DAVID FEILER |
| Footing/Foundation/Slab | 3/1/2021 | Approved | DAVID FEILER |
| Floor/Roof Diaphrgm/Shear Wall | 5/5/2021 | Partial Approval | DAVID FEILER |
| PLUMBING-Rough | 5/5/2021 | Partial Approval | DAVID FEILER |
| Floor/Roof Diaphrgm/Shear Wall | 5/19/2021 | Partial Approval | DAVID FEILER |
| Floor/Roof Diaphrgm/Shear Wall | 6/1/2021 | Partial Approval | DAVID FEILER |
| ELECTRICAL-Rough | 11/17/2021 | Corrections Issued | ANTHONY EGSON |
| HVAC-Rough | 11/17/2021 | Corrections Issued | ANTHONY EGSON |
| PLUMBING-Rough | 11/17/2021 | Corrections Issued | ANTHONY EGSON |
| Wood Frame | 11/17/2021 | Corrections Issued | ANTHONY EGSON |
| Wood Frame | 11/29/2021 | Partial Approval | ADAM ESCOTO |
| ELECTRICAL-Rough | 3/7/2022 | Corrections Issued | ANTHONY EGSON |
| Floor/Roof Diaphrgm/Shear Wall | 3/7/2022 | Corrections Issued | ANTHONY EGSON |
| PLUMBING-Rough | 3/7/2022 | Corrections Issued | ANTHONY EGSON |
| Interior/Exterior Lathing | 6/6/2022 | Approved | ANTHONY EGSON |
| Insulation | 6/22/2022 | Approved | ANTHONY EGSON |
| Drywall Nailing | 7/14/2022 | Approved | ANTHONY EGSON |
| Interior/Exterior Lathing | 7/14/2022 | Approved | ANTHONY EGSON |
| BUILDING-Rough-Frame | 9/15/2022 | Approved | ANTHONY EGSON |
| ELECTRICAL-Final | 9/15/2022 | Approved | ANTHONY EGSON |
| Final | 9/15/2022 | Corrections Issued | ANTHONY EGSON |
| Green Building Final | 9/15/2022 | Corrections Issued | ANTHONY EGSON |
| Green Building Rough | 9/15/2022 | Approved | ANTHONY EGSON |
| HVAC-Final | 9/15/2022 | Approved | ANTHONY EGSON |
| PLUMBING-Final | 9/15/2022 | Approved | ANTHONY EGSON |
| SGSOV-Seismic Gas S/O Valve | 9/15/2022 | SGSOV Not Required | ANTHONY EGSON |
| Smoke Detectors | 9/15/2022 | Partial Approval | ANTHONY EGSON |
| ELECTRICAL-Final | 9/29/2022 | Approved | ANTHONY EGSON |
| Final | 9/29/2022 | Conditional Approval | ANTHONY EGSON |
| Green Building Final | 9/29/2022 | Approved | ANTHONY EGSON |
| HVAC-Final | 9/29/2022 | Approved | ANTHONY EGSON |
| Smoke Detectors | 9/29/2022 | Approved | ANTHONY EGSON |