11916 N LAUGHTON WAY 91326
Certificate Information: 11916 N LAUGHTON WAY 91326
- Application / Permit
- 20014-10000-01362
- Plan Check / Job No.
- B20LA05793
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ADDITION TO EXISTING SINGLE FAMILY DWELLING NFPA 13D THRUOUT (FIRE DAMAGE MORE THAN 75% OF STRUCTURE)
- Permit Issued
- Issued on 9/29/2020
- Issuing Office
- Current Status
- CofO Issued on 3/23/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/27/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 4/2/2020 | AUNG SOE |
| Corrections Issued | 4/8/2020 | AUNG SOE |
| Quality Review Completed | 4/10/2020 | QUAN NGHIEM |
| Green Plans Picked Up | 7/2/2020 | APPLICANT |
| Applicant returned to address corrections | 7/29/2020 | AUNG SOE |
| Building Plans Picked Up | 8/31/2020 | APPLICANT |
| Applicant returned to address corrections | 9/14/2020 | AUNG SOE |
| Plan Check Approved | 9/15/2020 | AUNG SOE |
| Issued | 9/29/2020 | APPLICANT |
| CofO in Progress | 12/17/2021 | DAVID SCANTLIN |
| Permit Finaled | 3/23/2022 | JOHN JANSON |
| CofO Issued | 3/23/2022 | JOHN JANSON |
| Permit Finaled | 3/23/2022 | JOHN JANSON |
Permit Application Clearance Information
| BHO/Hillside ordinance | Cleared | 6/10/2020 | GABRIEL ROBLES |
| BHO/Hillside ordinance | Cleared | 6/10/2020 | GABRIEL ROBLES |
| BHO/Hillside ordinance | Cleared | 6/10/2020 | GABRIEL ROBLES |
| Highway dedication | Cleared | 6/10/2020 | GABRIEL ROBLES |
| Grading Pre-Inspection | Cleared | 6/22/2020 | PATRICK MISCHLICH |
| Green Code | Cleared | 6/26/2020 | KHEDER ALRAZAA |
| Eng Process Fee Ord 176,300 | Cleared | 7/8/2020 | GABRIEL ROBLES |
| Sewer availability | Cleared | 7/8/2020 | GABRIEL ROBLES |
| Miscellaneous | Cleared | 7/15/2020 | TERRI OSBORNE |
| Tract Map conditions | Cleared | 7/15/2020 | TERRI OSBORNE |
| Hydrant and Access approval | Cleared | 7/16/2020 | MATTHEW CRAIG |
| GPI Written Notices | Cleared | 8/3/2020 | AUNG SOE |
| Low Impact Development | Cleared | 8/12/2020 | MARTIN FRAGOSO |
| Distance to fire station | Cleared | 8/20/2020 | MATTHEW CRAIG |
| Roof/Waste drainage to street | Cleared | 8/20/2020 | GABRIEL ROBLES |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Oruncakciel,, Sayat; Lic. No.: C77182 | 15445 VENTURA BLVD 25 SHERMAN OAKS, CA 91403 |
Inspector Information
| JEFFREY PARD, (818) 774-4312 | Office Hours: 7:00-8:00 AM MON-FRI |
| STEVEN BACK, (818) 774-4312 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 10/15/2020 | Partial Approval | DAVID SCANTLIN |
| Deputy Drilled-In Anchors | 10/16/2020 | Approved | DAVID SCANTLIN |
| Sewer | 10/16/2020 | Not Ready for Inspection | DAVID SCANTLIN |
| Underground Mechanical | 10/16/2020 | Approved | DAVID SCANTLIN |
| Footing/Foundation/Slab | 10/21/2020 | Approved | DAVID SCANTLIN |
| METHANE-Barrier | 10/21/2020 | Approved | DAVID SCANTLIN |
| METHANE-Subgrade | 10/21/2020 | Approved | DAVID SCANTLIN |
| Deputy Steel/Welding | 11/5/2020 | Partial Approval | DAVID SCANTLIN |
| Wood Frame | 12/1/2020 | Partial Approval | DAVID SCANTLIN |
| Floor/Roof Diaphrgm/Shear Wall | 3/8/2021 | Not Ready for Inspection | DAVID SCANTLIN |
| ELECTRICAL-Rough | 3/19/2021 | Approved | DAVID SCANTLIN |
| Floor/Roof Diaphrgm/Shear Wall | 3/19/2021 | Approved | DAVID SCANTLIN |
| HVAC-Rough | 3/19/2021 | Approved | DAVID SCANTLIN |
| PLUMBING-Rough | 3/19/2021 | Approved | DAVID SCANTLIN |
| BUILDING-Rough-Frame | 3/23/2021 | Not Ready for Inspection | DAVID SCANTLIN |
| Green Building Rough | 3/23/2021 | Not Ready for Inspection | DAVID SCANTLIN |
| METHANE-Rough | 3/23/2021 | Approved | DAVID SCANTLIN |
| Verify Sprinkler Sign Off | 3/23/2021 | Approved | DAVID SCANTLIN |
| Sewer | 6/1/2021 | Approved | DAVID SCANTLIN |
| Insulation | 7/14/2021 | Not Ready for Inspection | LILIANA PORTILLO |
| Interior/Exterior Lathing | 7/14/2021 | Not Ready for Inspection | LILIANA PORTILLO |
| Insulation | 7/23/2021 | Corrections Issued | ALIZAH MAYAGOITIA |
| Interior/Exterior Lathing | 7/23/2021 | Approved | ALIZAH MAYAGOITIA |
| Drywall Nailing | 8/3/2021 | Conditional Approval | LILIANA PORTILLO |
| Green Building Rough | 8/3/2021 | Approved | LILIANA PORTILLO |
| Shower Pan | 8/3/2021 | Partial Approval | LILIANA PORTILLO |
| Interior/Exterior Lathing | 8/23/2021 | Approved | DAVID SCANTLIN |
| Service/Power Release | 8/23/2021 | Approved | DAVID SCANTLIN |
| Gas Test | 8/31/2021 | Not Ready for Inspection | DAVID SCANTLIN |
| Gas Test | 9/3/2021 | Approved | DAVID SCANTLIN |
| Pre-Inspection | 10/22/2021 | Approved | DAVID SCANTLIN |
| Pre-Inspection | 11/9/2021 | Approved | DAVID SCANTLIN |
| BUILDING-Rough-Frame | 12/16/2021 | Approved | DAVID SCANTLIN |
| Drywall Nailing | 12/16/2021 | Approved | DAVID SCANTLIN |
| Final | 12/16/2021 | OK to Issue CofO | DAVID SCANTLIN |
| Green Building Final | 12/16/2021 | Approved | DAVID SCANTLIN |
| SGSOV-Seismic Gas S/O Valve | 12/16/2021 | SGSOV Approved | DAVID SCANTLIN |
| Smoke Detectors | 12/16/2021 | Approved | DAVID SCANTLIN |
| Special/Order Compliance | 3/18/2022 | Approved | DAVID SCANTLIN |