10120 N JANETTA WAY 91040
Certificate Information: 10120 N JANETTA WAY 91040
- Application / Permit
- 20014-10000-01357
- Plan Check / Job No.
- B20LA05787
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ONE-STORY [9' X 21'-8"] ADDITION TO 2-STORY SFD WITH ATTACHED GARAGE: TO EXPAND KITCHEN AND DINING AREA.
- Permit Issued
- Issued on 11/10/2021
- Issuing Office
- Current Status
- Issued on 11/10/2021
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 4/3/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 4/16/2020 | CRISTINA SALAZAR |
| Corrections Issued | 4/16/2020 | CRISTINA SALAZAR |
| Applicant returned to address corrections | 6/24/2020 | GEORGE ALVAREZ |
| Applicant returned to address corrections | 8/5/2020 | JESSE JIMENEZ |
| Plan Check Approved | 10/27/2021 | DANIEL SANJUAN |
| Building Plans Picked Up | 11/1/2021 | APPLICANT |
| Issued | 11/10/2021 | APPLICANT |
Permit Application Clearance Information
| BHO/Hillside ordinance | Cleared | 6/9/2020 | ADRIAN CASTRO |
| BHO/Hillside ordinance | Cleared | 6/9/2020 | ADRIAN CASTRO |
| BHO/Hillside ordinance | Cleared | 6/9/2020 | ADRIAN CASTRO |
| Roof/Waste drainage to street | Cleared | 6/9/2020 | ADRIAN CASTRO |
| Sewer availability | Cleared | 6/9/2020 | ADRIAN CASTRO |
| Eng Process Fee Ord 176,300 | Cleared | 6/11/2020 | ADRIAN CASTRO |
| Grading Pre-Inspection | Cleared | 7/30/2020 | PATRICK MISCHLICH |
| Specific Plan | Cleared | 10/20/2021 | ANACANY HURTADO |
Contact Information
| Architect | Volbeda,, Pete; Lic. No.: C13077 | P.O. BOX 1665 UPLAND, CA 91785 |
| Contractor | Owner-Builder | , |
Inspector Information
| DAVID ANDERSON, (818) 374-1168 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 11/16/2021 | Approved | WILLIAM KUEHN |
| Floor/Roof Diaphrgm/Shear Wall | 12/7/2021 | Partial Inspection | WILLIAM KUEHN |
| BUILDING-Rough-Frame | 12/29/2021 | Corrections Issued | JENNIFER RABUCHIN |
| ELECTRICAL-Rough | 12/29/2021 | Approved | JENNIFER RABUCHIN |
| Gas Test | 12/29/2021 | Corrections Issued | JENNIFER RABUCHIN |
| Green Building Rough | 12/29/2021 | Approved | JENNIFER RABUCHIN |
| HVAC-Rough | 12/29/2021 | Approved | JENNIFER RABUCHIN |
| Interior/Exterior Lathing | 12/29/2021 | Partial Approval | JENNIFER RABUCHIN |
| PLUMBING-Rough | 12/29/2021 | Approved | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 1/3/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Gas Test | 1/3/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Insulation | 1/10/2022 | Approved | MATTHEW NELSON |
| Drywall Nailing | 1/18/2022 | Approved | JOHN HAYES |
| Final | 12/1/2022 | Corrections Issued | GREGG CUMMINGS |
| Green Building Final | 12/1/2022 | Approved | GREGG CUMMINGS |
| SGSOV-Seismic Gas S/O Valve | 12/1/2022 | SGSOV Not Ready | GREGG CUMMINGS |
| Smoke Detectors | 12/1/2022 | Approved | GREGG CUMMINGS |