1527 W 66TH ST 90047
Certificate Information: 1527 W 66TH ST 90047
- Application / Permit
- 20014-10000-01352
- Plan Check / Job No.
- B20LA05780
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- (N) 1-STORY ADDITION TO THE REAR OF (E) SFD PER ENGINEER OF RECORD.
- Permit Issued
- Issued on 7/21/2020
- Issuing Office
- Current Status
- CofO Issued on 2/11/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/5/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 5/5/2020 | LUKE GONZALES |
| Corrections Issued | 5/28/2020 | LUKE GONZALES |
| Applicant returned to address corrections | 6/12/2020 | RAHEL BEYENE |
| Plan Check Approved | 7/16/2020 | CRISTINA SALAZAR |
| Issued | 7/21/2020 | APPLICANT |
| Building Plans Picked Up | 7/23/2020 | APPLICANT |
| CofO in Progress | 1/28/2021 | FREDDIE RIVERA |
| Permit Finaled | 2/11/2021 | DEROLD HAUFF |
| CofO Issued | 2/11/2021 | DEROLD HAUFF |
| Permit Finaled | 2/11/2021 | DEROLD HAUFF |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 4/15/2020 | EMIL KYUPELYAN |
| Eng Process Fee Ord 176,300 | Cleared | 4/22/2020 | CECILIO NAVARRO |
| Sewer availability | Cleared | 6/23/2020 | CECILIO NAVARRO |
Contact Information
| Contractor | Frost Construction; Lic. No.: 580847-B | 1041 WEST 105TH STREET LOS ANGELES, CA 90044 |
| Engineer | Tamu,, O C; Lic. No.: C29787 | P O BOX 17083 LONG BEACH, CA 90807 |
Inspector Information
| BARRY HACHE, (213) 202-9851 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 7/28/2020 | Not Ready for Inspection | COREY HUPP |
| Footing/Foundation/Slab | 8/3/2020 | Conditional Approval | FREDDIE RIVERA |
| Insulation | 8/27/2020 | Partial Approval | FREDDIE RIVERA |
| Floor/Roof Diaphrgm/Shear Wall | 9/2/2020 | Approved | FREDDIE RIVERA |
| Special/Order Compliance | 9/2/2020 | Corrections Issued | FREDDIE RIVERA |
| Floor/Roof Diaphrgm/Shear Wall | 9/24/2020 | Approved | FREDDIE RIVERA |
| BUILDING-Rough-Frame | 9/29/2020 | Approved | FREDDIE RIVERA |
| ELECTRICAL-Rough | 9/29/2020 | Approved | FREDDIE RIVERA |
| Green Building Rough | 9/29/2020 | Approved | FREDDIE RIVERA |
| HVAC-Rough | 9/29/2020 | Conditional Approval | FREDDIE RIVERA |
| PLUMBING-Rough | 9/29/2020 | Approved | FREDDIE RIVERA |
| Pre-Inspection | 9/29/2020 | Corrections Issued | FREDDIE RIVERA |
| Insulation | 10/7/2020 | Approved | FREDDIE RIVERA |
| Interior/Exterior Lathing | 10/7/2020 | Approved | FREDDIE RIVERA |
| Drywall Nailing | 10/16/2020 | Approved | DONALD CRICHLOW |
| Interior/Exterior Lathing | 10/16/2020 | Partial Approval | DONALD CRICHLOW |
| Final | 12/21/2020 | Corrections Issued | FREDDIE RIVERA |
| Footing/Foundation/Slab | 12/21/2020 | No Access for Inspection | FREDDIE RIVERA |
| Green Building Final | 12/21/2020 | No Access for Inspection | FREDDIE RIVERA |
| SGSOV-Seismic Gas S/O Valve | 12/21/2020 | SGSOV Not Ready | FREDDIE RIVERA |
| Smoke Detectors | 12/21/2020 | No Access for Inspection | FREDDIE RIVERA |
| ELECTRICAL-Final | 12/29/2020 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| Final | 12/29/2020 | Corrections Issued | KATHRYN BUTTERWORTH |
| HVAC-Final | 12/29/2020 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| PLUMBING-Final | 12/29/2020 | Approved | KATHRYN BUTTERWORTH |
| ELECTRICAL-Final | 1/4/2021 | Corrections Issued | JOSEPH MCGARRY |
| Final | 1/4/2021 | Corrections Issued | JOSEPH MCGARRY |
| Footing/Foundation/Slab | 1/4/2021 | Approved | JOSEPH MCGARRY |
| Green Building Final | 1/4/2021 | Approved | JOSEPH MCGARRY |
| HVAC-Final | 1/4/2021 | Corrections Issued | JOSEPH MCGARRY |
| PLUMBING-Final | 1/4/2021 | Corrections Issued | JOSEPH MCGARRY |
| SGSOV-Seismic Gas S/O Valve | 1/4/2021 | SGSOV Not Ready | JOSEPH MCGARRY |
| Smoke Detectors | 1/4/2021 | Approved | JOSEPH MCGARRY |
| Final | 1/27/2021 | Not Ready for Inspection | FREDDIE RIVERA |
| SGSOV-Seismic Gas S/O Valve | 1/27/2021 | SGSOV Approved | FREDDIE RIVERA |
| Final | 1/28/2021 | OK to Issue CofO | FREDDIE RIVERA |