4760 1/2 E BALTIMORE ST 90042

Certificate Information: 4760 1/2 E BALTIMORE ST 90042

Application / Permit
20014-10000-01344
Plan Check / Job No.
B20LA05757
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
PROPOSE 20'X34' ADU (479 SQFT) AT BASEMENT LEVEL ATTACHED TO (E) SFD. see comment. "COMPLY WITH DEPARTMENT ORDER effective date 02/11/2020. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE"
Permit Issued
Issued on 10/27/2021
Issuing Office
Current Status
Issued on 10/27/2021
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 3/27/2020 APPLICANT
Assigned to Plan Check Engineer 4/2/2020 CHUNG-WEN CHUANG
Corrections Issued 4/16/2020 CHUNG-WEN CHUANG
Quality Review Completed 5/7/2020 KESETE HAREGOT
Green Plans Picked Up 7/17/2020 APPLICANT
Applicant returned to address corrections 8/14/2020 CHUNG-WEN CHUANG
Plan Check Approved 10/19/2020 CHUNG-WEN CHUANG
Issued 10/27/2021 APPLICANT
Building Plans Picked Up 11/10/2021 APPLICANT

Permit Application Clearance Information

Green Code Cleared 7/15/2020 VIVIAN LAO
Address approval Cleared 7/29/2020 CELINA MORENO
Eng Process Fee Ord 176,300 Cleared 7/30/2020 CELINA MORENO
Sewer availability Cleared 7/30/2020 CELINA MORENO

Contact Information

Contractor E H R Construction; Lic. No.: 972351-B 4760 BALTIMORE STREET      LOS ANGELES, CA 90042
Engineer Morales,, Carlos A; Lic. No.: C69972 38100 SAN MATEO AVE      PALMDALE, CA 93551

Inspector Information

THOMAS WILLIS, (213) 252-3038 Office Hours: 7:00-8:00 AM MON-FRI
JEFFREY CHRISTIAN, (213) 252-3038 Office Hours: 7:00-8:00 AM MON-FRI
FERMIN RUBIO, (213) 252-3038 Office Hours: 7:00-8:00 AM MON-FRI
JACOB SEGURA, (213) 252-3038 Office Hours: 7:00-8:00 AM MON-FRI
CLAUDIO MORENO, (213) 252-3038 Office Hours: 7:00-8:00 AM MON-FRI
MARK RUDE, (213) 252-3038 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 10/21/2022 Not Ready for Inspection JAVIER RAMOS SR
Footing/Foundation/Slab 3/7/2023 Partial Approval JAVIER RAMOS SR
Footing/Foundation/Slab 12/28/2023 Partial Approval LONG LEE
Deputy Drilled-In Anchors 5/20/2024 Approved FERMIN RUBIO
Footing/Foundation/Slab 5/23/2024 Partial Approval COREY HUPP
Footing/Foundation/Slab 7/11/2024 Approved JONATHAN FRANCHINI
Excavation/Setback/Form/Re-Bar 8/19/2024 Not Ready for Inspection JACOB SEGURA
Deputy Drilled-In Anchors 4/9/2025 Corrections Issued JACOB SEGURA
Deputy Drilled-In Anchors 10/14/2025 Approved JACOB SEGURA
Deputy Drilled-In Anchors 2/20/2026 Approved FERMIN RUBIO
Excavation/Setback/Form/Re-Bar 5/26/2026 Partial Approval JACOB SEGURA
Footing/Foundation/Slab 5/26/2026 Partial Approval JACOB SEGURA