22118 W DEL VALLE ST 91364
Certificate Information: 22118 W DEL VALLE ST 91364
- Application / Permit
- 20014-10000-01343
- Plan Check / Job No.
- B20LA05755
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) GARAGE/STORAGE TO AN ACEESSORY DWELLING UNIT PER LAMC 12.22A.33(c) and (d), ALL WORK PER ENGR'S DETAILS.
- Permit Issued
- Issued on 8/31/2020
- Issuing Office
- Current Status
- CofO Issued on 8/11/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/26/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 4/2/2020 | SAM CHANG |
| Corrections Issued | 4/17/2020 | SAM CHANG |
| Quality Review Completed | 4/21/2020 | ARMEN JIVALAGIAN |
| Building Plans Picked Up | 5/20/2020 | APPLICANT |
| Green Plans Picked Up | 7/30/2020 | APPLICANT |
| Applicant returned to address corrections | 8/11/2020 | SAM CHANG |
| Plan Check Approved | 8/25/2020 | SAM CHANG |
| Issued | 8/31/2020 | APPLICANT |
| CofO in Progress | 8/11/2021 | PETER FOLLING |
| CofO in Progress | 8/11/2021 | PETER FOLLING |
| CofO Issued | 8/11/2021 | MICHAEL SMITH |
| Permit Finaled | 8/11/2021 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 7/14/2020 | ADRIAN CASTRO |
| Eng Process Fee Ord 176,300 | Cleared | 7/14/2020 | ADRIAN CASTRO |
| Roof/Waste drainage to street | Cleared | 7/14/2020 | ADRIAN CASTRO |
| Sewer availability | Cleared | 7/15/2020 | ADRIAN CASTRO |
| CPC | Cleared | 7/20/2020 | HERMINIGILDO AGUSTIN |
| Hydrant and Access approval | Cleared | 7/20/2020 | KURT CORRAL |
| Grading Pre-Inspection | Cleared | 7/23/2020 | PATRICK MISCHLICH |
| Green Code | Cleared | 7/29/2020 | VIVIAN LAO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Miraaney,, David H; Lic. No.: C60575 | 22041 CRESPI ST WOODLAND HILLS, CA 91364 |
Inspector Information
| JOHN HAYES, (818) 774-4302 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 12/30/2020 | Not Ready for Inspection | PAUL CHOPP |
| Underground Mechanical | 12/30/2020 | Corrections Issued | PAUL CHOPP |
| Footing/Foundation/Slab | 1/4/2021 | No Access for Inspection | PAUL CHOPP |
| Underground Mechanical | 1/4/2021 | Corrections Issued | PAUL CHOPP |
| Underground Mechanical | 1/6/2021 | Corrections Issued | PAUL CHOPP |
| Footing/Foundation/Slab | 1/11/2021 | Approved | PAUL CHOPP |
| Underground Mechanical | 1/11/2021 | Partial Approval | PAUL CHOPP |
| ELECTRICAL-Final | 2/2/2021 | Not Ready for Inspection | PAUL CHOPP |
| ELECTRICAL-Rough | 2/2/2021 | Partial Inspection | PAUL CHOPP |
| Wood Frame | 2/2/2021 | Partial Inspection | PAUL CHOPP |
| ELECTRICAL-Rough | 2/3/2021 | Corrections Issued | PAUL CHOPP |
| Wood Frame | 2/3/2021 | Partial Inspection | PAUL CHOPP |
| ELECTRICAL-Rough | 2/5/2021 | Partial Inspection | PAUL CHOPP |
| Floor/Roof Diaphrgm/Shear Wall | 2/5/2021 | Partial Inspection | PAUL CHOPP |
| Rough-Elec/Plmb/HVAC | 2/5/2021 | Partial Inspection | PAUL CHOPP |
| Wood Frame | 2/5/2021 | Partial Inspection | PAUL CHOPP |
| ELECTRICAL-Rough | 2/10/2021 | Approved | PAUL CHOPP |
| HVAC-Rough | 2/10/2021 | Approved | PAUL CHOPP |
| PLUMBING-Rough | 2/10/2021 | Approved | PAUL CHOPP |
| Wood Frame | 2/10/2021 | Partial Approval | PAUL CHOPP |
| Interior/Exterior Lathing | 2/16/2021 | Not Ready for Inspection | PAUL CHOPP |
| Wood Frame | 2/16/2021 | Approved | PAUL CHOPP |
| Insulation | 2/22/2021 | Approved | PAUL CHOPP |
| Drywall Nailing | 3/11/2021 | Approved | STEVEN BACK |
| Interior/Exterior Lathing | 3/11/2021 | Approved | STEVEN BACK |
| BUILDING-Rough-Frame | 7/29/2021 | Approved | PETER FOLLING |
| Final | 7/29/2021 | Corrections Issued | PETER FOLLING |
| Green Building Final | 7/29/2021 | Approved | PETER FOLLING |
| Green Building Rough | 7/29/2021 | Approved | PETER FOLLING |
| SGSOV-Seismic Gas S/O Valve | 7/29/2021 | SGSOV Not Ready | PETER FOLLING |
| Smoke Detectors | 7/29/2021 | Not Ready for Inspection | PETER FOLLING |
| Final | 8/5/2021 | Not Ready for Inspection | PETER FOLLING |
| SGSOV-Seismic Gas S/O Valve | 8/5/2021 | SGSOV Not Ready | PETER FOLLING |
| Smoke Detectors | 8/5/2021 | Approved | PETER FOLLING |
| Final | 8/10/2021 | OK to Issue CofO | PETER FOLLING |
| SGSOV-Seismic Gas S/O Valve | 8/10/2021 | SGSOV Approved | PETER FOLLING |
| Service/Power Release | 8/10/2021 | Approved | PETER FOLLING |