3933 S SOMERSET DR 90008
Certificate Information: 3933 S SOMERSET DR 90008
- Application / Permit
- 20014-10000-01315
- Plan Check / Job No.
- B20LA05641
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) DETACHED GARAGE TO ACCESSORY DWELING UNIT PER GCS 65852.2(e)(1)(A).
- Permit Issued
- Issued on 6/30/2023
- Issuing Office
- Current Status
- CofO Issued on 6/14/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/20/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 3/25/2020 | RAHEL BEYENE |
| Corrections Issued | 5/27/2020 | RAHEL BEYENE |
| Applicant returned to address corrections | 7/1/2020 | RAHEL BEYENE |
| Plan Check Approved | 8/10/2021 | RAHEL BEYENE |
| Plan Check Approved | 8/10/2021 | GIOVANNY CHAVEZ |
| Building Plans Picked Up | 8/11/2021 | APPLICANT |
| Issued | 6/30/2023 | APPLICANT |
| CofO in Progress | 6/12/2024 | ANTHONY EGSON |
| CofO Issued | 6/14/2024 | DEROLD HAUFF |
| Permit Finaled | 6/14/2024 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 4/7/2020 | JEANIE LAM |
| Roof/Waste drainage to street | Cleared | 4/7/2020 | JEANIE LAM |
| Eng Process Fee Ord 176,300 | Cleared | 4/16/2020 | JEANIE LAM |
| Sewer availability | Cleared | 4/16/2020 | JEANIE LAM |
| Low Impact Development | Cleared | 7/6/2021 | MARTIN FRAGOSO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Melchor,, Oscar Elias; Lic. No.: C76828 | 21243 VENTURA BLVD SUITE 119 WOODLAND HILLS, CA 91364 |
Inspector Information
| LUIS CASTRO, (213) 202-3436 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 8/14/2023 | Not Ready for Inspection | ANTHONY EGSON |
| Sewer | 8/14/2023 | Corrections Issued | ANTHONY EGSON |
| PLUMBING-Rough | 8/17/2023 | Approved | ANTHONY EGSON |
| Sewer | 8/17/2023 | Approved | ANTHONY EGSON |
| Excavation/Setback/Form/Re-Bar | 8/30/2023 | Not Ready for Inspection | ANTHONY EGSON |
| Footing/Foundation/Slab | 8/30/2023 | Corrections Issued | ANTHONY EGSON |
| Excavation/Setback/Form/Re-Bar | 9/6/2023 | Approved | ANTHONY EGSON |
| Footing/Foundation/Slab | 9/6/2023 | Approved | ANTHONY EGSON |
| BUILDING-Rough-Frame | 11/2/2023 | Not Ready for Inspection | ANTHONY EGSON |
| ELECTRICAL-Rough | 11/2/2023 | Corrections Issued | ANTHONY EGSON |
| Floor/Roof Diaphrgm/Shear Wall | 11/2/2023 | Approved | ANTHONY EGSON |
| Green Building Rough | 11/2/2023 | Not Ready for Inspection | ANTHONY EGSON |
| HVAC-Rough | 11/2/2023 | Corrections Issued | ANTHONY EGSON |
| PLUMBING-Rough | 11/2/2023 | Corrections Issued | ANTHONY EGSON |
| Wood Frame | 11/2/2023 | Not Ready for Inspection | ANTHONY EGSON |
| Floor/Roof Diaphrgm/Shear Wall | 11/17/2023 | Corrections Issued | ANTHONY EGSON |
| Interior/Exterior Lathing | 11/17/2023 | Not Ready for Inspection | ANTHONY EGSON |
| ELECTRICAL-Rough | 11/27/2023 | Not Ready for Inspection | ANTHONY EGSON |
| Floor/Roof Diaphrgm/Shear Wall | 11/27/2023 | Corrections Issued | ANTHONY EGSON |
| Gas Test | 11/27/2023 | Approved | ANTHONY EGSON |
| HVAC-Rough | 11/27/2023 | Approved | ANTHONY EGSON |
| Interior/Exterior Lathing | 11/27/2023 | Not Ready for Inspection | ANTHONY EGSON |
| PLUMBING-Rough | 11/27/2023 | Approved | ANTHONY EGSON |
| Wood Frame | 11/27/2023 | Not Ready for Inspection | ANTHONY EGSON |
| Floor/Roof Diaphrgm/Shear Wall | 11/30/2023 | Partial Approval | ANTHONY EGSON |
| Interior/Exterior Lathing | 11/30/2023 | Not Ready for Inspection | ANTHONY EGSON |
| Wood Frame | 11/30/2023 | Corrections Issued | ANTHONY EGSON |
| Floor/Roof Diaphrgm/Shear Wall | 12/4/2023 | Partial Approval | ANTHONY EGSON |
| HVAC-Rough | 12/4/2023 | Approved | ANTHONY EGSON |
| Interior/Exterior Lathing | 12/7/2023 | Approved | ANTHONY EGSON |
| Underground Mechanical | 12/7/2023 | Approved | ANTHONY EGSON |
| Insulation | 12/11/2023 | Approved | ANTHONY EGSON |
| Drywall Nailing | 12/15/2023 | Approved | BRENDAN MORELLI |
| Green Building Rough | 12/15/2023 | Approved | BRENDAN MORELLI |
| Shower Pan | 1/17/2024 | Corrections Issued | ANTHONY EGSON |
| Shower Pan | 1/22/2024 | Approved | AMIR NAZARIAN |
| Interior/Exterior Lathing | 1/25/2024 | Approved | BRENDAN MORELLI |
| Service/Power Release | 3/8/2024 | Corrections Issued | ANTHONY EGSON |
| BUILDING-Rough-Frame | 3/20/2024 | Approved | ANTHONY EGSON |
| ELECTRICAL-Final | 3/20/2024 | Corrections Issued | ANTHONY EGSON |
| Final | 3/20/2024 | Corrections Issued | ANTHONY EGSON |
| Green Building Final | 3/20/2024 | Not Ready for Inspection | ANTHONY EGSON |
| HVAC-Final | 3/20/2024 | Corrections Issued | ANTHONY EGSON |
| PLUMBING-Final | 3/20/2024 | Not Ready for Inspection | ANTHONY EGSON |
| SGSOV-Seismic Gas S/O Valve | 3/20/2024 | SGSOV Approved | ANTHONY EGSON |
| Service/Power Release | 3/20/2024 | Not Ready for Inspection | ANTHONY EGSON |
| Smoke Detectors | 3/20/2024 | Not Ready for Inspection | ANTHONY EGSON |
| ELECTRICAL-Final | 4/11/2024 | Corrections Issued | ANTHONY EGSON |
| HVAC-Final | 4/11/2024 | Corrections Issued | ANTHONY EGSON |
| PLUMBING-Final | 4/11/2024 | Corrections Issued | ANTHONY EGSON |
| SGSOV-Seismic Gas S/O Valve | 4/11/2024 | SGSOV Approved | ANTHONY EGSON |
| Service/Power Release | 4/11/2024 | Approved | ANTHONY EGSON |
| Final | 4/29/2024 | Not Ready for Inspection | ANTHONY EGSON |
| Final | 6/12/2024 | OK to Issue CofO | ANTHONY EGSON |
| Green Building Final | 6/12/2024 | Approved | ANTHONY EGSON |
| Smoke Detectors | 6/12/2024 | Approved | ANTHONY EGSON |