1520 S CARDIFF AVE 90035
Certificate Information: 1520 S CARDIFF AVE 90035
- Application / Permit
- 20014-10000-01299
- Plan Check / Job No.
- B20LA05541
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW BASEMENT, FIRST, AND SECOND FLOOR ADDITION AND MAJOR REMODEL TO (E) SINGLE FAMILY DWELLING. NEW ATTACHED GARAGE. NFPA-13D FIRE SPRINKLERS REQUIRED.
- Permit Issued
- Issued on 1/22/2021
- Issuing Office
- Metro
- Current Status
- CofO Issued on 10/14/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/19/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 3/27/2020 | KEVIN MORALES |
| Corrections Issued | 4/3/2020 | KEVIN MORALES |
| Quality Review Completed | 4/8/2020 | STANLEY RAAP |
| Applicant returned to address corrections | 10/23/2020 | KEVIN MORALES |
| Green Plans Picked Up | 12/2/2020 | APPLICANT |
| Applicant returned to address corrections | 1/8/2021 | KEVIN MORALES |
| Plan Check Approved | 1/20/2021 | KEVIN MORALES |
| Building Plans Picked Up | 1/21/2021 | APPLICANT |
| Issued | 1/22/2021 | APPLICANT |
| CofO in Progress | 9/29/2022 | OGANES TARAKHCHYAN |
| Permit Finaled | 10/14/2022 | DANIEL ORRANTE |
| CofO Issued | 10/14/2022 | DANIEL ORRANTE |
| Permit Finaled | 10/14/2022 | DANIEL ORRANTE |
Permit Application Clearance Information
| Hydrant and Access approval | Cleared | 7/17/2020 | KURT CORRAL |
| Eng Process Fee Ord 176,300 | Cleared | 7/24/2020 | DINAH GARIN |
| Sewer availability | Cleared | 7/24/2020 | DINAH GARIN |
| Low Impact Development | Cleared | 7/27/2020 | JORGE MEJIA LEMUS |
| Roof/Waste drainage to street | Cleared | 8/28/2020 | DINAH GARIN |
| Green Code | Cleared | 9/24/2020 | DONALD CRICHLOW |
| GPI Written Notices | Cleared | 10/26/2020 | KEVIN MORALES |
| Grading Pre-Inspection | Cleared | 10/26/2020 | KEVIN MORALES |
Contact Information
| Contractor | Drexel Construction Management Llc; Lic. No.: 1014160-B | 5168 W PICO BLVD LOS ANGELES, CA 90019 |
| Engineer | Chiu,, Ivan Wai-Kuen; Lic. No.: C44672 | 2160 PARNELL WY ALTADENA, CA 91001 |
| Engineer | Smith,, Melvin Bruce; Lic. No.: GE2673 | 2165 N MARVEL AVE SIMI VALLEY, CA 93065 |
| Engineer | Yuzon,, Benigno S; Lic. No.: S3454 | 25531 PRADO DELAS BELLOTAS CALABASAS, CA 91302 |
Inspector Information
| ASHLEY THOMPSON, (310) 914-3897 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Floor/Roof Diaphrgm/Shear Wall | 6/23/2021 | Not Ready for Inspection | KEVIN SARGSYAN |
| Insulation | 6/23/2021 | Partial Approval | KEVIN SARGSYAN |
| BUILDING-Rough-Frame | 6/28/2021 | Partial Approval | KEVIN SARGSYAN |
| Floor/Roof Diaphrgm/Shear Wall | 6/28/2021 | Partial Approval | KEVIN SARGSYAN |
| Green Building Rough | 6/28/2021 | Not Ready for Inspection | KEVIN SARGSYAN |
| METHANE-Rough | 6/28/2021 | Not Ready for Inspection | KEVIN SARGSYAN |
| Floor/Roof Diaphrgm/Shear Wall | 7/16/2021 | Partial Approval | KEVIN SARGSYAN |
| Floor/Roof Diaphrgm/Shear Wall | 8/16/2021 | Not Ready for Inspection | KEVIN SARGSYAN |
| Sewer | 8/16/2021 | Corrections Issued | KEVIN SARGSYAN |
| PLUMBING-Rough | 8/26/2021 | Corrections Issued | KEVIN SARGSYAN |
| PLUMBING-Rough | 8/27/2021 | Approved | KEVIN SARGSYAN |
| Sewer | 8/27/2021 | Approved | KEVIN SARGSYAN |
| Floor/Roof Diaphrgm/Shear Wall | 9/20/2021 | Partial Approval | KEVIN SARGSYAN |
| Floor/Roof Diaphrgm/Shear Wall | 10/8/2021 | Approved | KEVIN SARGSYAN |
| Shower Pan | 10/15/2021 | Not Ready for Inspection | KEVIN SARGSYAN |
| ELECTRICAL-Rough | 10/19/2021 | Not Ready for Inspection | KEVIN SARGSYAN |
| HVAC-Rough | 10/19/2021 | Approved | KEVIN SARGSYAN |
| Shower Pan | 10/19/2021 | Approved | KEVIN SARGSYAN |
| ELECTRICAL-Rough | 10/22/2021 | Approved | KEVIN SARGSYAN |
| Interior/Exterior Lathing | 10/22/2021 | Partial Approval | KEVIN SARGSYAN |
| BUILDING-Rough-Frame | 11/8/2021 | Approved | KEVIN SARGSYAN |
| Green Building Rough | 11/8/2021 | Approved | KEVIN SARGSYAN |
| Interior/Exterior Lathing | 11/8/2021 | Partial Approval | KEVIN SARGSYAN |
| METHANE-Rough | 11/8/2021 | Approved | KEVIN SARGSYAN |
| Insulation | 11/17/2021 | Approved | STEPHANIE SWANSON |
| Drywall Nailing | 12/6/2021 | Approved | KEVIN SARGSYAN |
| ELECTRICAL-Final | 7/7/2022 | Corrections Issued | KEVIN SARGSYAN |
| PLUMBING-Final | 7/7/2022 | Corrections Issued | KEVIN SARGSYAN |
| ELECTRICAL-Final | 7/12/2022 | No Access for Inspection | KEVIN SARGSYAN |
| HVAC-Final | 7/12/2022 | No Access for Inspection | KEVIN SARGSYAN |
| PLUMBING-Final | 7/12/2022 | No Access for Inspection | KEVIN SARGSYAN |
| ELECTRICAL-Final | 7/13/2022 | Not Ready for Inspection | KEVIN SARGSYAN |
| Gas Test | 7/13/2022 | Approved | KEVIN SARGSYAN |
| PLUMBING-Final | 7/13/2022 | Approved | KEVIN SARGSYAN |
| HVAC-Final | 7/14/2022 | Corrections Issued | KEVIN SARGSYAN |
| ELECTRICAL-Final | 7/19/2022 | Partial Approval | STEPHANIE SWANSON |
| HVAC-Final | 7/19/2022 | Approved | STEPHANIE SWANSON |
| Smoke Detectors | 7/19/2022 | Approved | STEPHANIE SWANSON |
| Final | 8/25/2022 | Corrections Issued | OGANES TARAKHCHYAN |
| Footing/Foundation/Slab | 8/25/2022 | Approved | OGANES TARAKHCHYAN |
| Green Building Final | 8/25/2022 | Approved | OGANES TARAKHCHYAN |
| METHANE-Barrier | 8/25/2022 | Approved | OGANES TARAKHCHYAN |
| METHANE-Subgrade | 8/25/2022 | Approved | OGANES TARAKHCHYAN |
| SGSOV-Seismic Gas S/O Valve | 8/25/2022 | SGSOV Approved | OGANES TARAKHCHYAN |
| Service/Power Release | 8/25/2022 | Approved | OGANES TARAKHCHYAN |
| Final | 9/28/2022 | OK to Issue CofO | OGANES TARAKHCHYAN |