12867 N NORRIS AVE 91342
Certificate Information: 12867 N NORRIS AVE 91342
- Application / Permit
- 20014-10000-01298
- Plan Check / Job No.
- B20LA05534
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- (N) ADDITION TO A SINGLE FAMILY RESIDENCE PER WOOD FRAME PERSCRIPTIVE PROVISIONS.
- Permit Issued
- Issued on 12/19/2020
- Issuing Office
- Current Status
- CofO Issued on 4/2/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/19/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 3/19/2020 | FERNANDO FLORES |
| Corrections Issued | 3/19/2020 | FERNANDO FLORES |
| Applicant returned to address corrections | 4/22/2020 | RAHEL BEYENE |
| Applicant returned to address corrections | 7/14/2020 | CRISTINA SALAZAR |
| Applicant returned to address corrections | 7/30/2020 | STARR CHEN |
| Applicant returned to address corrections | 11/11/2020 | TSE MING HUANG |
| Plan Check Approved | 12/7/2020 | TSE MING HUANG |
| Issued | 12/19/2020 | APPLICANT |
| Building Plans Picked Up | 12/28/2020 | APPLICANT |
| CofO in Progress | 2/7/2022 | JOHN HAYES |
| No Progress | 2/12/2022 | MICHAEL TEMPLE |
| CofO in Progress | 4/2/2022 | DEROLD HAUFF |
| Permit Finaled | 4/2/2022 | DEROLD HAUFF |
| CofO Issued | 4/2/2022 | DEROLD HAUFF |
| Permit Finaled | 4/2/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 4/6/2020 | ROSE MARIE SMITH |
| Sewer availability | Cleared | 4/6/2020 | ADRIAN CASTRO |
| Low Impact Development | Cleared | 6/29/2020 | ANDRES COVARRUBIAS |
| Roof/Waste drainage to street | Cleared | 7/7/2020 | ADRIAN CASTRO |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| KEVIN BERBERYAN, (818) 374-9931 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 8/12/2021 | Partial Approval | MISAEL ESPARZA |
| Footing/Foundation/Slab | 8/27/2021 | Approved | MISAEL ESPARZA |
| BUILDING-Rough-Frame | 10/5/2021 | Approved | JOHN HAYES |
| ELECTRICAL-Rough | 10/5/2021 | Approved | JOHN HAYES |
| Floor/Roof Diaphrgm/Shear Wall | 10/5/2021 | Partial Approval | JOHN HAYES |
| Green Building Rough | 10/5/2021 | Approved | JOHN HAYES |
| HVAC-Rough | 10/5/2021 | Partial Approval | JOHN HAYES |
| PLUMBING-Rough | 10/5/2021 | Approved | JOHN HAYES |
| Insulation | 10/12/2021 | Not Ready for Inspection | JOHN HAYES |
| Interior/Exterior Lathing | 10/12/2021 | Partial Approval | JOHN HAYES |
| Insulation | 10/19/2021 | Approved | JOHN HAYES |
| Drywall Nailing | 10/25/2021 | No Access for Inspection | JESUS RODRIGUEZ |
| Interior/Exterior Lathing | 10/25/2021 | No Access for Inspection | JESUS RODRIGUEZ |
| Special/Order Compliance | 10/25/2021 | Partial Inspection | ALAN MORELOS |
| Drywall Nailing | 10/28/2021 | Approved | JOHN HAYES |
| Interior/Exterior Lathing | 10/28/2021 | Approved | JOHN HAYES |
| Final | 12/10/2021 | Corrections Issued | JOHN HAYES |
| Green Building Final | 12/10/2021 | Not Ready for Inspection | JOHN HAYES |
| SGSOV-Seismic Gas S/O Valve | 12/10/2021 | SGSOV Not Ready | JOHN HAYES |
| Smoke Detectors | 12/10/2021 | Not Ready for Inspection | JOHN HAYES |
| Final | 2/7/2022 | OK to Issue CofO | JOHN HAYES |
| Green Building Final | 2/7/2022 | Approved | JOHN HAYES |
| SGSOV-Seismic Gas S/O Valve | 2/7/2022 | SGSOV Approved | JOHN HAYES |
| Smoke Detectors | 2/7/2022 | Approved | JOHN HAYES |