2934 S SOMERSET DR 90016

Certificate Information: 2934 S SOMERSET DR 90016

Application / Permit
20014-10000-01291
Plan Check / Job No.
B20LA05504
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW 2ND STORY 26'-7"X26'-2" ADDITION TO EXISTING SINGLE FAMILY DWELLING AND ROOF TOP DECK
Permit Issued
Issued on 7/9/2020
Issuing Office
Current Status
CofO Issued on 4/24/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/18/2020 APPLICANT
Assigned to Plan Check Engineer 3/26/2020 GEORGE ALVAREZ
Corrections Issued 4/3/2020 GEORGE ALVAREZ
Green Plans Picked Up 5/1/2020 APPLICANT
Quality Review Completed 6/19/2020 STANLEY RAAP
Plan Check Approved 6/22/2020 GEORGE ALVAREZ
Building Plans Picked Up 6/22/2020 APPLICANT
Issued 7/9/2020 APPLICANT
CofO in Progress 12/19/2020 STUART CHAPMAN
No Progress 3/18/2023 MICHAEL PELHAM
CofO in Progress 4/20/2023 RICHARD STEINBACH
Permit Finaled 4/24/2023 DANIEL ORRANTE
CofO Issued 4/24/2023 DANIEL ORRANTE
Permit Finaled 4/24/2023 DANIEL ORRANTE

Permit Application Clearance Information

Green Code Cleared 4/29/2020 VIVIAN LAO
Low Impact Development Cleared 6/3/2020 JORGE MEJIA LEMUS
Eng Process Fee Ord 176,300 Cleared 6/11/2020 EMIL KYUPELYAN
Roof/Waste drainage to street Cleared 6/11/2020 EMIL KYUPELYAN
Sewer availability Cleared 6/11/2020 EMIL KYUPELYAN
Tenant Habitability Plan Cleared 6/21/2020 JORGE ALCANTAR

Contact Information

Contractor Owner-Builder       ,
Engineer Espino,, Manuel A; Lic. No.: C55526 12109 WOODRUFF AVE      DOWNEY, CA 90241

Inspector Information

JUSTIN HAWLEY, (213) 202-3432 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 7/13/2020 Corrections Issued STUART CHAPMAN
Excavation/Setback/Form/Re-Bar 7/15/2020 Approved STUART CHAPMAN
Sewer 7/21/2020 Partial Approval STUART CHAPMAN
Floor/Roof Diaphrgm/Shear Wall 8/7/2020 Partial Approval STUART CHAPMAN
BUILDING-Rough-Frame 8/21/2020 Partial Approval STUART CHAPMAN
Floor/Roof Diaphrgm/Shear Wall 8/21/2020 Partial Approval STUART CHAPMAN
Green Building Rough 8/21/2020 Not Ready for Inspection STUART CHAPMAN
Rough-Elec/Plmb/HVAC 9/23/2020 Corrections Issued STUART CHAPMAN
Smoke Detectors 9/23/2020 Not Ready for Inspection STUART CHAPMAN
BUILDING-Rough-Frame 9/24/2020 Conditional Approval STUART CHAPMAN
Green Building Rough 9/24/2020 Approved STUART CHAPMAN
Interior/Exterior Lathing 9/24/2020 Partial Approval STUART CHAPMAN
Insulation 9/30/2020 Approved STUART CHAPMAN
Drywall Nailing 10/19/2020 Approved STUART CHAPMAN
Interior/Exterior Lathing 10/19/2020 Approved STUART CHAPMAN
BUILDING-Rough-Frame 12/14/2020 Approved STUART CHAPMAN
Final 12/14/2020 Corrections Issued STUART CHAPMAN
Footing/Foundation/Slab 12/14/2020 Approved STUART CHAPMAN
Green Building Final 12/14/2020 Approved STUART CHAPMAN
SGSOV-Seismic Gas S/O Valve 12/14/2020 SGSOV Approved STUART CHAPMAN
Smoke Detectors 12/14/2020 Approved STUART CHAPMAN
ELECTRICAL-Final 12/18/2020 Approved STUART CHAPMAN
Final 12/18/2020 OK to Issue CofO STUART CHAPMAN
HVAC-Final 12/18/2020 Approved STUART CHAPMAN
PLUMBING-Final 12/18/2020 Approved STUART CHAPMAN
Special/Order Compliance 2/17/2022 Corrections Issued STUART CHAPMAN