16510 W CHATTANOOGA PL 90272
Certificate Information: 16510 W CHATTANOOGA PL 90272
- Application / Permit
- 20014-10000-01287
- Plan Check / Job No.
- B20LA05495
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- (N) Rec Roomn as a basement level addition with (N) Roof Deck to the rear of the (E) one story SFD. "COMPLY WITH DEPARTMENT ORDER effective date 10/23/2019. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE".
- Permit Issued
- Issued on 11/3/2021
- Issuing Office
- Current Status
- CofO Issued on 10/24/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/18/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 3/31/2020 | TEODORO DIAZ RODRIGUEZ |
| Corrections Issued | 4/27/2020 | TEODORO DIAZ RODRIGUEZ |
| Quality Review Completed | 4/30/2020 | QUAN NGHIEM |
| Green Plans Picked Up | 9/9/2020 | APPLICANT |
| Plan Check Approved | 8/18/2021 | TEODORO DIAZ RODRIGUEZ |
| Issued | 11/3/2021 | APPLICANT |
| Building Plans Picked Up | 11/8/2021 | APPLICANT |
| Permit Finaled | 10/24/2024 | CLAUDIO MORENO |
| CofO Issued | 10/24/2024 | CLAUDIO MORENO |
| Permit Finaled | 10/24/2024 | CLAUDIO MORENO |
Permit Application Clearance Information
| GPI Written Notices | Cleared | 8/25/2020 | TEODORO DIAZ RODRIGUEZ |
| Grading Pre-Inspection | Cleared | 8/25/2020 | TEODORO DIAZ RODRIGUEZ |
| Coastal Zone | Cleared | 8/26/2020 | RUBEN VASQUEZ |
| BHO/Hillside ordinance | Cleared | 8/31/2020 | ANTHONY MAINEZ |
| BHO/Hillside ordinance | Cleared | 8/31/2020 | ANTHONY MAINEZ |
| BHO/Hillside ordinance | Cleared | 8/31/2020 | ANTHONY MAINEZ |
| Sewer availability | Cleared | 8/31/2020 | ANTHONY MAINEZ |
| Green Code | Cleared | 9/8/2020 | DONALD CRICHLOW |
| Eng Process Fee Ord 176,300 | Cleared | 9/30/2020 | ANTHONY MAINEZ |
| Hydrant and Access approval | Cleared | 12/7/2020 | MATTHEW CRAIG |
| Low Impact Development | Cleared | 7/21/2021 | ORVAL HERNANDEZ-MARCI |
| Roof/Waste drainage to street | Cleared | 8/18/2021 | ANTHONY MAINEZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Pineda,, Salvador Antonio; Lic. No.: S5233 | PO BOX 7313 ALHAMBRA, CA 91802 |
Inspector Information
| ROBERT GARTH, (213) 978-4498 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOHN MATTILLO, (213) 978-4498 | Office Hours: 7:00-8:00 AM MON-FRI |
| PEDRO RIVERA, (213) 978-4498 | Office Hours: 7:00-8:00 AM MON-FRI |
| EUSEBIO GUZMAN, (213) 978-4498 | Office Hours: 7:00-8:00 AM MON-FRI |
| PAUL REECE, (213) 978-4498 | Office Hours: 7:00-8:00 AM MON-FRI |
| ANDREW BEELI, (213) 978-4498 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 11/15/2021 | Approved | MARIAN PODPORA |
| Excavation/Setback/Form/Re-Bar | 12/15/2021 | Conditional Approval | MARIAN PODPORA |
| Excavation/Setback/Form/Re-Bar | 2/8/2022 | Partial Approval | RYAN BARNES |
| Excavation/Setback/Form/Re-Bar | 2/17/2022 | Partial Approval | RYAN BARNES |
| Footing/Foundation/Slab | 2/17/2022 | Partial Approval | RYAN BARNES |
| Masonry Wall/Backfill | 2/17/2022 | Partial Approval | RYAN BARNES |
| Excavation/Setback/Form/Re-Bar | 2/23/2022 | Partial Approval | RYAN BARNES |
| Masonry Wall/Backfill | 2/23/2022 | Partial Approval | RYAN BARNES |
| Excavation/Setback/Form/Re-Bar | 3/29/2022 | Partial Approval | RYAN BARNES |
| Excavation/Setback/Form/Re-Bar | 4/4/2022 | Partial Approval | RYAN BARNES |
| Masonry Wall/Backfill | 4/8/2022 | Partial Approval | JOHN MATTILLO |
| Masonry Wall/Backfill | 4/12/2022 | Partial Approval | JOHN MATTILLO |
| Excavation/Setback/Form/Re-Bar | 4/29/2022 | Partial Approval | RYAN BARNES |
| Masonry Wall/Backfill | 5/2/2022 | Partial Approval | RYAN BARNES |
| Masonry Wall/Backfill | 5/5/2022 | Partial Approval | RYAN BARNES |
| Excavation/Setback/Form/Re-Bar | 5/16/2022 | Partial Approval | JOHN MATTILLO |
| Masonry Wall/Backfill | 5/19/2022 | Partial Approval | MARIAN PODPORA |
| Masonry Wall/Backfill | 5/23/2022 | Partial Approval | RYAN BARNES |
| Sewer | 6/29/2022 | Approved | RYAN BARNES |
| Excavation/Setback/Form/Re-Bar | 7/6/2022 | Approved | RYAN BARNES |
| Footing/Foundation/Slab | 7/6/2022 | Approved | RYAN BARNES |
| Deputy Drilled-In Anchors | 7/27/2022 | Approved | RYAN BARNES |
| Deputy Wood Construction | 8/9/2022 | Approved | RYAN BARNES |
| BUILDING-Rough-Frame | 8/10/2022 | Partial Approval | JOHN MATTILLO |
| Green Building Rough | 8/10/2022 | Approved | JOHN MATTILLO |
| Deputy Drilled-In Anchors | 8/22/2022 | Approved | RYAN BARNES |
| BUILDING-Rough-Frame | 11/1/2022 | Approved | RYAN BARNES |
| ELECTRICAL-Rough | 11/1/2022 | Approved | RYAN BARNES |
| HVAC-Rough | 11/1/2022 | Not Ready for Inspection | RYAN BARNES |
| PLUMBING-Rough | 11/1/2022 | Corrections Issued | RYAN BARNES |
| BUILDING-Rough-Frame | 11/3/2022 | Approved | RYAN BARNES |
| ELECTRICAL-Rough | 11/3/2022 | Approved | RYAN BARNES |
| HVAC-Rough | 11/3/2022 | Approved | RYAN BARNES |
| PLUMBING-Rough | 11/3/2022 | Approved | RYAN BARNES |
| Insulation | 11/8/2022 | Approved | RYAN BARNES |
| Interior/Exterior Lathing | 2/14/2023 | Partial Approval | RYAN BARNES |
| Pre-Inspection | 2/14/2023 | Not Ready for Inspection | RYAN BARNES |
| Pre-Inspection | 2/22/2023 | Approved | RYAN BARNES |
| Drywall Nailing | 3/24/2023 | Approved | ANDREW BEELI |
| Deputy Drilled-In Anchors | 9/21/2023 | Partial Approval | ANDREW BEELI |
| Deputy Reinf. Concrete | 12/5/2023 | Approved | RYAN BARNES |
| Deputy Drilled-In Anchors | 12/15/2023 | Conditional Approval | JOHN MATTILLO |
| Excavation/Setback/Form/Re-Bar | 12/21/2023 | Approved | RYAN BARNES |
| Deputy Reinf. Concrete | 12/22/2023 | Partial Approval | ANDREW BEELI |
| ELECTRICAL-Rough | 1/29/2024 | Partial Approval | RYAN BARNES |
| Insulation | 2/2/2024 | Approved | RYAN BARNES |
| Drywall Nailing | 2/23/2024 | Approved | JOHN MATTILLO |
| Interior/Exterior Lathing | 3/20/2024 | Approved | RYAN BARNES |
| ELECTRICAL-Final | 6/4/2024 | Approved | RYAN BARNES |
| Final | 6/4/2024 | Not Ready for Inspection | RYAN BARNES |
| Green Building Final | 6/4/2024 | Approved | RYAN BARNES |
| HVAC-Final | 6/4/2024 | Approved | RYAN BARNES |
| PLUMBING-Final | 6/4/2024 | Approved | RYAN BARNES |
| SGSOV-Seismic Gas S/O Valve | 6/4/2024 | SGSOV Not Ready | RYAN BARNES |
| Smoke Detectors | 6/4/2024 | Not Ready for Inspection | RYAN BARNES |
| Final | 9/5/2024 | Conditional Approval | RYAN BARNES |
| SGSOV-Seismic Gas S/O Valve | 9/5/2024 | SGSOV Approved | RYAN BARNES |
| Smoke Detectors | 9/5/2024 | Approved | RYAN BARNES |