4960 N GENEVIEVE AVE 90041

Certificate Information: 4960 N GENEVIEVE AVE 90041

Application / Permit
20014-10000-01240
Plan Check / Job No.
B20LA05306
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
HOUSE REMODEL AND ADDITION
Permit Issued
Issued on 8/21/2020
Issuing Office
Current Status
CofO Issued on 2/8/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/16/2020 APPLICANT
Assigned to Plan Check Engineer 3/26/2020 SAMUEL GONZALEZ
Corrections Issued 3/31/2020 SAMUEL GONZALEZ
Quality Review Completed 4/2/2020 LAWRENCE QUIRANTE
Green Plans Picked Up 4/24/2020 APPLICANT
Plan Check Approved 8/5/2020 SAMUEL GONZALEZ
Issued 8/21/2020 APPLICANT
Building Plans Picked Up 8/25/2020 APPLICANT
CofO in Progress 11/29/2021 MARK VAN SLOOTEN
Permit Finaled 2/8/2022 DANIEL SANCHEZ
CofO Issued 2/8/2022 DANIEL SANCHEZ
Permit Finaled 2/8/2022 DANIEL SANCHEZ

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 4/15/2020 JEANIE LAM
Sewer availability Cleared 4/15/2020 JEANIE LAM
Green Code Cleared 4/16/2020 KHEDER ALRAZAA
Roof/Waste drainage to street Cleared 4/21/2020 JEANIE LAM
Grading Pre-Inspection Cleared 8/4/2020 SAMUEL GONZALEZ

Contact Information

Contractor Emmental Construction Group Inc; Lic. No.: 1011107-B 9668 MILLIKEN AVE   STE 104-284    RANCHO CUCAMONGA, CA 91730
Engineer Moreno,, Hector M; Lic. No.: C66015 1430 E COOLEY DR SUITE 120      COLTON, CA 92324

Inspector Information

DANIEL DELACRUZ, (323) 526-9348 Office Hours: 7:00-8:00 AM MON-FRI
PEDRO SIERRA, (323) 526-9348 Office Hours: 7:00-8:00 AM MON-FRI
ROBERT MINASSIANS, (323) 526-9348 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 9/3/2020 Approved DAVID LEE
Floor/Roof Diaphrgm/Shear Wall 10/15/2020 Partial Approval DAVID LEE
Insulation 10/15/2020 Partial Approval DAVID LEE
PLUMBING-Rough 10/15/2020 Partial Approval DAVID LEE
Deputy Wood Construction 12/16/2020 Conditional Approval DAVID LEE
ELECTRICAL-Rough 12/28/2020 Not Ready for Inspection DAVID LEE
HVAC-Rough 12/28/2020 Not Ready for Inspection DAVID LEE
PLUMBING-Rough 12/28/2020 Not Ready for Inspection DAVID LEE
ELECTRICAL-Rough 1/4/2021 Approved DAVID LEE
Floor/Roof Diaphrgm/Shear Wall 1/4/2021 Partial Approval DAVID LEE
HVAC-Rough 1/4/2021 Corrections Issued DAVID LEE
PLUMBING-Rough 1/4/2021 Approved DAVID LEE
Special/Order Compliance 1/4/2021 Corrections Issued DAVID LEE
HVAC-Rough 1/19/2021 Not Ready for Inspection DAVID LEE
Insulation 1/19/2021 Not Ready for Inspection DAVID LEE
Wood Frame 1/19/2021 Not Ready for Inspection DAVID LEE
HVAC-Rough 1/25/2021 Approved DAVID LEE
Insulation 1/25/2021 Not Ready for Inspection DAVID LEE
Wood Frame 1/25/2021 Not Ready for Inspection DAVID LEE
BUILDING-Rough-Frame 1/27/2021 Approved DAVID LEE
Green Building Rough 1/27/2021 Approved DAVID LEE
MERV13>=Rough 1/27/2021 Approved DAVID LEE
Insulation 1/28/2021 Approved DAVID LEE
Drywall Nailing 2/1/2021 Approved DAVID LEE
Gas Test 2/8/2021 Not Ready for Inspection DAVID LEE
Interior/Exterior Lathing 2/8/2021 Not Ready for Inspection DAVID LEE
Gas Test 2/10/2021 Approved DAVID LEE
Interior/Exterior Lathing 2/10/2021 Approved DAVID LEE
Shower Pan 2/10/2021 Approved DAVID LEE
Final 11/3/2021 Corrections Issued MARK VAN SLOOTEN
Green Building Final 11/3/2021 Approved MARK VAN SLOOTEN
MERV13>=Final 11/3/2021 Conditional Approval MARK VAN SLOOTEN
SGSOV-Seismic Gas S/O Valve 11/3/2021 SGSOV Approved MARK VAN SLOOTEN
Smoke Detectors 11/3/2021 Approved MARK VAN SLOOTEN
Final 11/22/2021 Conditional Approval MARK VAN SLOOTEN
MERV13>=Final 11/22/2021 Approved MARK VAN SLOOTEN