1227 W G ST 90744

Certificate Information: 1227 W G ST 90744

Application / Permit
20014-10000-01223
Plan Check / Job No.
B20LA05266
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ADDITION (18'-0" X 17'-9") TO THE REAR OF (E) SFD TO ADD A NEW BEDROOM.
Permit Issued
Issued on 3/16/2020
Issuing Office
Metro
Current Status
CofO Issued on 5/1/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/16/2020 APPLICANT
Assigned to Plan Check Engineer 3/16/2020 FARSHAD ALIMOHAMADI
Plan Check Approved 3/16/2020 SHANGQIN XIE
Issued 3/16/2020 LADBS
CofO in Progress 8/10/2020 JOHN KLARIN
Permit Finaled 5/1/2021 DEROLD HAUFF
CofO Issued 5/1/2021 DEROLD HAUFF
Permit Finaled 5/1/2021 DEROLD HAUFF

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 3/16/2020 PAMELA TENEZA
Roof/Waste drainage to street Cleared 3/16/2020 JEANIE LAM
Sewer availability Cleared 3/16/2020 JEANIE LAM

Contact Information

Contractor 3000 Construction; Lic. No.: 994421-B 11955 MANOR DR APT 1      HAWTHORNE, CA 90250

Inspector Information

EUGENE CASSIDY, (310) 548-2508 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 3/26/2020 Approved JOHN KLARIN
Excavation/Setback/Form/Re-Bar 3/26/2020 Corrections Issued JOHN KLARIN
Footing/Foundation/Slab 4/3/2020 Approved JOHN KLARIN
METHANE-Barrier 4/3/2020 Approved JOHN KLARIN
METHANE-Subgrade 4/3/2020 Approved JOHN KLARIN
Floor/Roof Diaphrgm/Shear Wall 4/8/2020 Not Ready for Inspection JOHN KLARIN
PLUMBING-Rough 4/8/2020 Partial Inspection JOHN KLARIN
Drywall Nailing 4/10/2020 Not Ready for Inspection JOHN KLARIN
Floor/Roof Diaphrgm/Shear Wall 4/10/2020 Partial Inspection JOHN KLARIN
Insulation 4/10/2020 Partial Inspection JOHN KLARIN
BUILDING-Rough-Frame 5/1/2020 Approved JOHN KLARIN
ELECTRICAL-Rough 5/1/2020 Approved JOHN KLARIN
Green Building Rough 5/1/2020 Approved JOHN KLARIN
MERV13>=Rough 5/1/2020 Approved JOHN KLARIN
METHANE-Rough 5/1/2020 Approved JOHN KLARIN
PLUMBING-Rough 5/1/2020 Approved JOHN KLARIN
HVAC-Rough 5/5/2020 Approved JOHN KLARIN
Insulation 5/5/2020 Approved JOHN KLARIN
Interior/Exterior Lathing 5/5/2020 Approved JOHN KLARIN
Drywall Nailing 5/7/2020 Approved JOHN KLARIN
Interior/Exterior Lathing 5/15/2020 Approved JOHN KLARIN
ELECTRICAL-Final 6/26/2020 Approved JOHN KLARIN
Final 6/26/2020 Corrections Issued JOHN KLARIN
Green Building Final 6/26/2020 Corrections Issued JOHN KLARIN
HVAC-Final 6/26/2020 Corrections Issued JOHN KLARIN
MERV13>=Final 6/26/2020 Approved JOHN KLARIN
PLUMBING-Final 6/26/2020 Approved JOHN KLARIN
SGSOV-Seismic Gas S/O Valve 6/26/2020 SGSOV Approved JOHN KLARIN
Smoke Detectors 6/26/2020 Approved JOHN KLARIN
ELECTRICAL-Final 7/10/2020 Approved JOHN KLARIN
Final 7/10/2020 Not Ready for Inspection JOHN KLARIN
Green Building Final 7/10/2020 Not Ready for Inspection JOHN KLARIN
HVAC-Final 7/10/2020 Conditional Approval JOHN KLARIN
PLUMBING-Final 7/10/2020 Approved JOHN KLARIN
ELECTRICAL-Final 7/22/2020 Approved JOHN KLARIN
Final 7/22/2020 Corrections Issued JOHN KLARIN
Green Building Final 7/22/2020 Approved JOHN KLARIN
PLUMBING-Final 7/22/2020 Approved JOHN KLARIN
Final 8/7/2020 OK to Issue CofO JOHN KLARIN