163 S SERRANO AVE 90004

Certificate Information: 163 S SERRANO AVE 90004

Application / Permit
20014-10000-01201
Plan Check / Job No.
B20LA05192
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEEW TWO STORY ADU, 18.25 FT X 35 FT, 957 SQFT, see comment.
Permit Issued
Issued on 6/4/2021
Issuing Office
Metro
Current Status
CofO Issued on 10/3/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/13/2020 APPLICANT
Assigned to Plan Check Engineer 3/20/2020 TSE MING HUANG
Corrections Issued 3/25/2020 TSE MING HUANG
Quality Review Completed 4/3/2020 STANLEY RAAP
Green Plans Picked Up 8/11/2020 APPLICANT
Applicant returned to address corrections 9/3/2020 TSE MING HUANG
Applicant returned to address corrections 9/25/2020 TSE MING HUANG
Applicant returned to address corrections 12/11/2020 TSE MING HUANG
Applicant returned to address corrections 12/21/2020 TSE MING HUANG
Applicant returned to address corrections 3/12/2021 TSE MING HUANG
Applicant returned to address corrections 4/30/2021 TSE MING HUANG
Plan Check Approved 5/10/2021 TSE MING HUANG
Issued 6/4/2021 APPLICANT
Building Plans Picked Up 8/26/2021 APPLICANT
CofO in Progress 4/21/2023 JEFFREY MEAD
No Progress 4/24/2023 SCOTT FINNILA
CofO in Progress 4/24/2023 RUBEN SALAS
CofO in Progress 9/13/2023 JEFFREY MEAD
CofO in Progress 9/13/2023 JEFFREY MEAD
Permit Finaled 10/3/2023 DEROLD HAUFF
CofO Issued 10/3/2023 DEROLD HAUFF
Permit Finaled 10/3/2023 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 5/14/2020 CECILIO NAVARRO
Sewer availability Cleared 6/10/2020 CECILIO NAVARRO
Redevelopment Project Area Cleared 6/12/2020 DAVID URITA
Green Code Cleared 6/22/2020 VIVIAN LAO
Hydrant and Access approval Cleared 7/1/2020 KURT CORRAL
Low Impact Development Cleared 8/2/2020 MARTIN FRAGOSO
Eng Process Fee Ord 176,300 Cleared 9/1/2020 CECILIO NAVARRO
Roof/Waste drainage to street Cleared 9/9/2020 ELENA LOPEZ

Contact Information

Contractor P Y Construction Inc; Lic. No.: 1006989-B 10213 FAIR GROVE AVE      TUJUNGA, CA 91042
Engineer Park,, Juntae; Lic. No.: C65104 3055 WILSHIRE BLVD 880      LOS ANGELES, CA 90010

Inspector Information

JEFFREY MEAD, (213) 202-3240 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 6/14/2021 Approved CHRIS CHRISTENSEN
PLUMBING-Rough 6/14/2021 Partial Approval CHRIS CHRISTENSEN
Floor/Roof Diaphrgm/Shear Wall 6/30/2021 Partial Approval CHRIS CHRISTENSEN
Green Building Rough 6/30/2021 Not Ready for Inspection CHRIS CHRISTENSEN
Pre-Inspection 6/30/2021 Approved CHRIS CHRISTENSEN
Verify Sprinkler Sign Off 6/30/2021 Not Ready for Inspection CHRIS CHRISTENSEN
BUILDING-Rough-Frame 8/24/2021 Corrections Issued CHRIS CHRISTENSEN
ELECTRICAL-Rough 8/24/2021 Approved CHRIS CHRISTENSEN
Gas Test 8/24/2021 Partial Approval CHRIS CHRISTENSEN
Green Building Rough 8/24/2021 Not Ready for Inspection CHRIS CHRISTENSEN
PLUMBING-Rough 8/24/2021 Approved CHRIS CHRISTENSEN
Verify Sprinkler Sign Off 8/24/2021 Not Ready for Inspection CHRIS CHRISTENSEN
Deputy Wood Construction 8/30/2021 Approved CHRIS CHRISTENSEN
Floor/Roof Diaphrgm/Shear Wall 8/30/2021 Partial Approval CHRIS CHRISTENSEN
Wood Frame 8/30/2021 Partial Approval CHRIS CHRISTENSEN
Interior/Exterior Lathing 9/16/2021 Partial Approval CHRIS CHRISTENSEN
HVAC-Rough 10/5/2021 Approved CHRIS CHRISTENSEN
BUILDING-Rough-Frame 10/7/2021 Approved CHRIS CHRISTENSEN
Green Building Rough 10/7/2021 Approved CHRIS CHRISTENSEN
Verify Sprinkler Sign Off 10/7/2021 Approved CHRIS CHRISTENSEN
Insulation 12/7/2021 Approved ALEJANDRO DE ARTOLA
Drywall Nailing 12/17/2021 Conditional Approval JOSEPH MCGARRY
Shower Pan 2/18/2022 Corrections Issued SHAVONNE ESPINOZA
Shower Pan 3/7/2022 Corrections Issued SHAVONNE ESPINOZA
Shower Pan 3/14/2022 Corrections Issued SHAVONNE ESPINOZA
Shower Pan 3/17/2022 Corrections Issued SHAVONNE ESPINOZA
Interior/Exterior Lathing 4/1/2022 Approved ADAM ESCOTO
Shower Pan 4/1/2022 Approved ADAM ESCOTO
PLUMBING-Final 6/29/2022 Approved JEFFREY MEAD
Drywall Nailing 7/12/2022 Partial Inspection JEFFREY MEAD
Final 7/12/2022 Not Ready for Inspection JEFFREY MEAD
Green Building Final 7/12/2022 Approved JEFFREY MEAD
SGSOV-Seismic Gas S/O Valve 7/12/2022 SGSOV Approved JEFFREY MEAD
Service/Power Release 7/12/2022 Partial Approval JEFFREY MEAD
Smoke Detectors 7/12/2022 Approved JEFFREY MEAD
Drywall Nailing 8/3/2022 Approved JEFFREY MEAD
Final 8/3/2022 Corrections Issued JEFFREY MEAD
Service/Power Release 8/3/2022 Not Ready for Inspection JEFFREY MEAD
Final 8/25/2022 Not Ready for Inspection JEFFREY MEAD
Service/Power Release 8/25/2022 Not Ready for Inspection JEFFREY MEAD
Final 3/16/2023 Corrections Issued JEFFREY MEAD
Service/Power Release 3/16/2023 Not Ready for Inspection JEFFREY MEAD
Final 3/22/2023 Corrections Issued JEFFREY MEAD
Service/Power Release 3/22/2023 Not Ready for Inspection JEFFREY MEAD
ELECTRICAL-Final 4/21/2023 Approved JEFFREY MEAD
Final 4/21/2023 OK to Issue CofO JEFFREY MEAD
HVAC-Final 4/21/2023 Approved JEFFREY MEAD
Service/Power Release 4/21/2023 Approved JEFFREY MEAD
Final 4/25/2023 Corrections Issued JEFFREY MEAD
Special/Order Compliance 9/27/2023 Approved BRIAN SULLIVAN