2811 N MARSH ST 90039
Certificate Information: 2811 N MARSH ST 90039
- Application / Permit
- 20014-10000-01189
- Plan Check / Job No.
- B20LA05156
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- PROPOSED NEW 1 STORY 24'6"x17'0" ADDITION TO (E) SFD. ALL WORK PER WOOD FRAME PRESCRIPTIVE PROVISIONS 1 OF 2
- Permit Issued
- Issued on 11/6/2020
- Issuing Office
- Current Status
- CofO Issued on 3/25/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/13/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 3/20/2020 | GEORGE ALVAREZ |
| Corrections Issued | 3/26/2020 | GEORGE ALVAREZ |
| Green Plans Picked Up | 3/31/2020 | APPLICANT |
| Quality Review Completed | 4/3/2020 | STANLEY RAAP |
| Plan Check Approved | 11/6/2020 | GEORGE ALVAREZ |
| Issued | 11/6/2020 | APPLICANT |
| Building Plans Picked Up | 11/6/2020 | APPLICANT |
| CofO in Progress | 3/24/2021 | RUBEN SALAS |
| Permit Finaled | 3/25/2021 | DEROLD HAUFF |
| CofO Issued | 3/25/2021 | DEROLD HAUFF |
| Permit Finaled | 3/25/2021 | DEROLD HAUFF |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 4/24/2020 | THOMAS LANG |
| Sewer availability | Cleared | 4/24/2020 | THOMAS LANG |
| Eng Process Fee Ord 176,300 | Cleared | 4/29/2020 | PAMELA TENEZA |
| Green Code | Cleared | 10/27/2020 | KHEDER ALRAZAA |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| HAMIK HARTOUNIAN, (213) 202-3275 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Wood Construction | 11/17/2020 | No Access for Inspection | ELMER BLAND |
| Excavation/Setback/Form/Re-Bar | 11/18/2020 | Approved | KATHRYN BUTTERWORTH |
| Footing/Foundation/Slab | 11/18/2020 | Approved | KATHRYN BUTTERWORTH |
| Floor/Roof Diaphrgm/Shear Wall | 11/25/2020 | Partial Approval | KATHRYN BUTTERWORTH |
| PLUMBING-Rough | 11/25/2020 | Partial Approval | KATHRYN BUTTERWORTH |
| BUILDING-Rough-Frame | 12/24/2020 | Corrections Issued | RUBEN SALAS |
| ELECTRICAL-Rough | 12/24/2020 | Approved | RUBEN SALAS |
| Green Building Rough | 12/24/2020 | Approved | RUBEN SALAS |
| HVAC-Rough | 12/24/2020 | Approved | RUBEN SALAS |
| MERV13>=Rough | 12/24/2020 | Approved | RUBEN SALAS |
| PLUMBING-Rough | 12/24/2020 | Approved | RUBEN SALAS |
| Underground Mechanical | 12/24/2020 | Not Ready for Inspection | RUBEN SALAS |
| Insulation | 12/31/2020 | Partial Approval | RUBEN SALAS |
| Underground Mechanical | 12/31/2020 | Approved | RUBEN SALAS |
| Drywall Nailing | 1/8/2021 | Partial Approval | KATHRYN BUTTERWORTH |
| Interior/Exterior Lathing | 1/8/2021 | Partial Approval | KATHRYN BUTTERWORTH |
| Interior/Exterior Lathing | 1/15/2021 | Partial Approval | COREY HUPP |
| Shower Pan | 1/15/2021 | Approved | COREY HUPP |
| BUILDING-Rough-Frame | 2/2/2021 | Approved | HAMIK HARTOUNIAN |
| ELECTRICAL-Final | 3/3/2021 | Approved | RUBEN SALAS |
| Final | 3/3/2021 | Corrections Issued | RUBEN SALAS |
| Gas Test | 3/3/2021 | Approved | RUBEN SALAS |
| Green Building Final | 3/3/2021 | Approved | RUBEN SALAS |
| HVAC-Final | 3/3/2021 | Not Ready for Inspection | RUBEN SALAS |
| MERV13>=Final | 3/3/2021 | Not Ready for Inspection | RUBEN SALAS |
| PLUMBING-Final | 3/3/2021 | Approved | RUBEN SALAS |
| SGSOV-Seismic Gas S/O Valve | 3/3/2021 | SGSOV Approved | RUBEN SALAS |
| Service/Power Release | 3/3/2021 | Approved | RUBEN SALAS |
| Smoke Detectors | 3/3/2021 | Approved | RUBEN SALAS |
| ELECTRICAL-Final | 3/9/2021 | Approved | RUBEN SALAS |
| HVAC-Final | 3/9/2021 | Approved | RUBEN SALAS |
| Final | 3/24/2021 | Conditional Approval | RUBEN SALAS |
| MERV13>=Final | 3/24/2021 | Conditional Approval | RUBEN SALAS |